INDOT contract R-42797-A bid tabulation

BIKE AND PEDESTRIAN FACILITIES. Let by Indiana DOT on November 13, 2025, Rush, Greenfield. 8 bids received; low bid $1,814,802 by Olco Inc.

Owner
Indiana DOT
Letting
13 NOV 2025
Pay items
67
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Olco Inc$1,814,802Low
2Morphey Construction Inc.$1,939,000+7.0%
3Calumet Civil Contractors Inc$2,078,000+15%
4Edward & Jones Concrete Inc$2,177,486+20%
5Beaty Construction Inc$2,255,736+24%
6Dave Omara Contractor Inc$2,268,147+25%
73D Company Inc$2,437,000+34%
8Paul H Rohe Company Inc$2,575,640+42%
INDOT contract R-42797-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Olco Inc2. Morphey Construction Inc.3. Calumet Civil Contractors Inc4. Edward & Jones Concrete Inc5. Beaty Construction Inc6. Dave Omara Contractor Inc
0001Construction engineering (105-06845)LS1$44,900$38,900$45,000$34,900$45,000$27,540
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0006Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0007Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0008Mobilization and demobilization (110-01001)LS1$24,965$96,950$80,000$50,385$112,750$111,000
0009Tree, 6 in., remove (201-02245)EACH7$762.29$350.00$300.00$550.00$275.00$275.00
0010Tree, 10 in., remove (201-02250)EACH1$925.50$850.00$400.00$1,000.00$500.00$825.00
0011Tree, 18 in., remove (201-02255)EACH11$1,957.31$1,350.00$750.00$1,600.00$1,100.00$1,320.00
0012Tree, 30 in., remove (201-02260)EACH6$2,747.30$3,300.00$3,000.00$3,000.00$2,675.00$2,420.00
0013Tree, 48 in., remove (201-02265)EACH2$3,546.62$5,400.00$4,000.00$4,800.00$5,800.00$3,400.00
0014Clearing right-of-way (201-52370)LS1$22,053$77,560$80,385$29,500$135,325$134,000
0015Pavement removal (202-02240)SYS780$20.37$20.00$20.00$35.00$55.50$34.00
0016Curb, concrete, remove (202-02278)LFT676$18.90$15.00$15.50$22.00$24.50$12.00
0017Curb and gutter, remove (202-02279)LFT704$18.90$15.00$20.00$23.00$17.75$12.00
0018Sidewalk concrete, remove (202-52710)SYS3,090$18.31$20.00$16.75$36.00$18.00$34.00
0019Sign, remove (202-74035)EACH14$41.05$50.00$50.00$50.00$125.00$185.00
0020Stump, remove (202-91922)EACH6$138.24$500.00$700.00$450.00$500.00$100.00
0021Fire hydrant assembly, remove (202-97009)EACH5$5,523.79$2,500.00$1,100.00$2,500.00$4,000.00$1,750.00
0022Excavation, common (203-02000)CYS500$61.96$50.00$50.00$45.00$109.50$39.00
0023Stormwater management budget (205-12108)DOL11,940$1.00$1.00$1.00$1.00$1.00$1.00
0024Stormwater management implementation (205-12616)LS1$14,850$500.00$35,000$15,000$12,000$18,700
0025SWQCP preparation (205-12618)LS1$3,000.00$2,000.00$2,500.00$2,500.00$3,250.00$2,750.00
0026Subgrade treatment, type II (207-08264)SYS1,304$28.00$30.00$28.00$59.00$36.75$61.00
0027Structure backfill, type 1 (211-09264)CYS69$97.75$68.00$67.00$85.00$86.75$55.00
0028Geogrid, type IB (214-11796)SYS589$3.86$2.50$4.00$4.50$4.75$9.00
0029Dense graded subbase (302-07455)CYS98$95.66$180.00$150.00$98.00$139.00$157.00
0030Compacted aggregate, no. 53 (303-01180)TON215$63.05$120.00$72.00$95.00$113.25$83.00
0031HMA patching, full depth, type B (304-12623)TON110$193.44$200.00$185.00$425.00$500.00$300.00
0032Sidewalk, concrete (604-06070)SYS3,620$82.72$100.00$62.00$92.00$102.25$73.00
0033Curb ramp, concrete (604-08086)SYS775$269.07$290.00$175.00$249.00$175.00$197.00
0034Curb, island concrete (605-02493)SYS74$202.16$135.00$160.00$75.00$90.50$243.00
0035Curb, concrete (605-06120)LFT1,288$46.30$50.00$44.00$55.00$76.00$60.00
0036Curb and gutter, concrete (605-06140)LFT1,120$60.16$50.00$53.00$64.00$81.00$60.00
0037PCCP for approaches, 6 in. (610-08446)SYS222$178.95$115.00$113.00$110.00$135.00$155.00
0038PCCP for approaches, 9 in. (610-09108)SYS367$203.29$135.00$125.00$125.00$150.00$167.00
0039Sodding, nursery (621-06575)SYS2,860$15.48$22.50$17.75$6.50$6.50$12.50
0040Tapping sleeve with valve (621-90853)EACH5$10,551$7,500.00$9,500.00$15,000$6,850.00$7,550.00
0041Plant, deciduous tree, single stem, over 2 in. to 2.5 in. (622-05650)EACH43$545.21$450.00$875.00$450.00$450.00$950.00
0043HMA for structure installation, type B (715-08305)TON33$214.53$200.00$360.00$475.00$300.00$300.00
0044Casting, inlet, adjust to grade (720-12797)EACH12$381.51$500.00$550.00$700.00$1,425.00$875.00
0045Casting, water valve, adjust to grade (720-94840)EACH5$293.98$500.00$400.00$700.00$500.00$675.00
0046Casting, water meter, adjust to grade (720-94841)EACH25$328.37$500.00$1,100.00$700.00$675.00$525.00
0047Fire hydrant assembly (720-96999)EACH5$10,966$10,000$10,500$13,500$10,000$9,550.00
0048Road closure sign assembly (801-04308)EACH7$406.00$295.00$406.00$150.00$295.00$450.00
0049Detour route marker assembly (801-06625)EACH6$198.00$138.00$198.00$100.00$138.00$215.00
0050Construction sign, type A (801-06640)EACH32$252.00$180.00$252.00$300.00$182.00$275.00
0051Construction sign, type B (801-06645)EACH12$185.00$110.00$185.00$150.00$110.00$200.00
0052Maintaining traffic (801-06775)LS1$75,618$97,382$100,000$65,000$99,553$169,959
0053Barricade, type III-A (801-07118)LFT60$19.00$17.00$19.00$20.00$17.00$20.00
0054Temporary curb ramp (801-11990)EACH5$475.89$4,500.00$2,200.00$2,250.00$2,300.00$3,278.00
0055Temporary accessible pedestrian path (801-12641)SYS161$15.11$25.00$45.00$55.00$165.00$78.00
0056Temporary pedestrian channelizer (801-12862)LFT56$7.00$75.00$22.00$50.00$120.00$84.00
0057Conduit, PVC, 2 in. (805-06595)LFT784$26.02$20.00$36.00$27.00$76.00$27.81
0058Conduit, PVC, 2 in. , SDR 11 fiber optics (805-06595)LFT8,986$10.11$10.00$38.00$28.00$10.75$28.84
0059Conduit, PVC, 2 in. schedule 40 (805-08214)LFT468$43.78$35.00$36.00$27.00$94.25$27.81
0060Conduit, PVC, 2 in. schedule 40 , street lighting (805-08214)LFT3,709$11.47$12.00$36.00$28.00$17.25$28.84
0061Light structure, remove and reset (807-02370)EACH10$3,500.00$1,000.00$2,200.00$1,500.00$2,200.00$1,545.00
0062Handhole , fiber optics (807-78590)EACH11$3,358.37$2,500.00$2,200.00$1,900.00$2,725.00$1,957.00
0063Pavement message marking, paint, lane indication arrow (808-06723)EACH2$129.00$135.00$129.00$150.00$135.00$142.00
0064Pavement message marking, paint, only (808-06724)EACH2$173.00$155.00$173.00$200.00$155.00$190.00
0065Transverse marking, paint, stop line, white, 24 in. (808-06726)LFT263$5.38$8.45$5.38$12.00$8.45$6.00
0066Transverse marking, paint, crosswalk line, white, 6 in. (808-75100)LFT1,568$2.61$3.00$2.61$5.00$3.10$3.00
0067Detectable warning surfaces (604-12083)SYS174$395.19$350.00$270.16$525.00$475.00$240.00
0068Water main, 6 in. (715-93912)LFT62$244.17$160.00$250.00$205.00$315.00$129.00
INDOT contract R-42797-A: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of November 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy