INDOT contract R-43004-A bid tabulation

CONCRETE PAVEMENT RESTORATION AND BRIDGE DECK REPLACEMENT. Let by Indiana DOT on January 15, 2025, Laporte, LaPorte. 5 bids received; low bid $10,719,759 by Dunnet Bay Construction Company.

Owner
Indiana DOT
Letting
15 JAN 2025
Pay items
148
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Dunnet Bay Construction Company$10,719,759Low
2Superior Construction Co Inc$10,799,990+1.0%
3Rieth-Riley Construction Co., Inc.$11,990,441+12%
4F H Paschen S N Nielsen & Associates LLC$12,097,313+13%
5Milestone Contractors LP$13,163,000+23%
INDOT contract R-43004-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Dunnet Bay Construction Company2. Superior Construction Co Inc3. Rieth-Riley Construction Co., Inc.4. F H Paschen S N Nielsen & Associates LLC5. Milestone Contractors LP
0001Construction engineering (105-06845)LS1$565,939$373,455$80,000$300,000$105,067
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, PCCP (109-08441)DOL1$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00
0007Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00
0008Project estimate adjustment (109-08463)DOL1$1.00$1.00$1.00$1.00$1.00
0009Quality adjustments, pavement traffic markings (109-09377)DOL1$1.00$1.00$1.00$1.00$1.00
0010Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00
0011Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00
0012Special maintenance , pothole patching (109-12573)DOL15,000$1.00$1.00$1.00$1.00$1.00
0013Mobilization and demobilization (110-01001)LS1$530,000$560,000$595,000$600,000$658,000
0014Clearing right-of-way (201-52370)LS1$50,000$56,000$42,000$60,000$65,800
0015Pavement removal (202-02240)SYS5,041$45.00$30.00$32.00$31.45$55.00
0016Present structure, remove portions, structure no. 1 (202-51328)LS1$5,000.00$60,000$22,500$7,500.00$10,000
0017Present structure, remove portions, structure no. 2 (202-51328)LS1$5,000.00$60,000$22,500$7,500.00$10,000
0018Present structure, remove portions, structure no. 3 (202-51328)LS1$400,000$400,000$810,000$360,000$340,000
0019Inlet, remove (202-91385)EACH2$1,200.00$2,000.00$760.00$1,326.08$1,200.00
0020Fence, chain link, remove (202-91840)LFT516$8.00$8.00$22.50$8.00$12.00
0021Guardrail end treatment, remove (202-93741)EACH3$730.00$730.00$400.00$730.00$525.00
0022Barrier wall, concrete, remove (202-94954)LFT76$100.00$100.00$150.00$35.00$50.00
0023Excavation, common (203-02000)CYS233$55.00$155.00$155.00$77.69$245.00
0024Stormwater management budget (205-12108)DOL11,000$1.00$1.00$1.00$1.00$1.00
0025Stormwater management implementation (205-12616)LS1$15,000$20,000$10,000$1,601.00$28,000
0026Subgrade treatment, type II (207-08264)SYS1,459$27.00$44.00$78.00$34.69$27.00
0027Subgrade treatment, type IC (207-09935)SYS5,373$45.00$44.00$49.00$48.96$84.00
0028Aggregate for end bent backfill (211-06467)CYS60$290.00$80.00$180.00$147.32$360.00
0029Structure backfill, type 5 (211-09268)CYS20$185.00$220.00$163.00$163.02$267.00
0030Flowable backfill, non- removable (213-09269)CYS112$190.00$180.00$195.00$224.87$239.00
0031Geogrid, type IB (214-11796)SYS1,459$2.00$4.00$1.00$5.34$0.73
0032Geotextile for pavement, type 2B (214-12239)SYS5,373$3.00$4.50$3.00$4.33$1.74
0033Compacted aggregate, no. 53 (301-12234)CYS43$95.00$120.00$265.00$129.97$167.00
0034Subbase for PCCP (302-06464)CYS1,199$120.00$130.00$100.00$137.57$230.00
0035Compacted aggregate, no. 53 (303-01180)TON915$50.00$35.00$55.00$51.90$37.00
0036Lean concrete base, 9 in. (305-12695)SYS1,459$80.00$185.00$60.00$127.84$94.00
0037Milling, transition (306-08043)SYS232$15.00$13.00$49.00$36.18$34.00
0038QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002)TON39$400.00$230.00$230.00$230.00$400.00
0039QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038)TON33$410.00$252.00$252.00$252.00$410.00
0040QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON146$240.00$133.00$133.00$133.00$240.00
0041Asphalt for tack coat (406-05520)TON1$1.00$2,065.00$2,065.00$2,065.00$1.00
0042QC/QA-PCCP, 15 in. (501-06326)SYS2,532$230.00$170.00$135.00$119.55$225.00
0043Retrofitted tie bars (503-03489)EACH1,402$70.00$38.00$85.00$32.11$13.00
0044D-1 contraction joint (503-05240)LFT2,117$16.00$25.00$34.00$20.41$40.00
0045Terminal joint, type HMA (503-12477)LFT73$300.00$290.00$400.00$335.52$450.00
0046Terminal joint, type PCCP (503-12478)LFT254$250.00$300.00$355.00$289.52$400.00
0047Expansion joint with load transfer (503-12479)LFT255$18.00$60.00$70.00$62.69$37.81
0049PCCP patching, full depth (506-06333)SYS1,459$300.00$425.00$598.00$294.23$611.00
0051Joints in PCCP, saw and seal (507-08272)LFT1,041$1.50$1.50$15.00$2.45$3.10
0052Joint repair, partial depth (509-12191)SFT864$60.00$120.00$367.00$128.13$305.00
0053Guardrail, remove (601-02241)LFT1,477$6.00$6.00$8.00$6.00$8.00
0054Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT888$20.00$20.00$23.00$20.00$20.00
0055Guardrail height transition, MGS (601-12289)EACH5$1,362.00$1,362.00$950.00$1,362.00$850.00
0056Guardrail transition, MGS with curb (601-12291)EACH6$3,430.00$3,430.00$3,600.00$3,430.00$2,800.00
0057Guardrail transition, MGS without curb (601-12292)EACH2$3,297.00$3,297.00$3,450.00$3,297.00$2,700.00
0058Guardrail end treatment, type OS (601-94689)EACH3$3,193.00$3,193.00$3,200.00$3,193.00$3,050.00
0059Barrier delineator (602-06729)EACH20$23.11$23.11$23.11$23.11$23.11
0060Concrete median barrier, modified (602-91266)LFT116$175.00$350.00$235.00$318.21$275.00
0061Curb, integral concrete, type B (605-06095)LFT98$80.00$90.00$91.00$93.23$109.00
0062Curb, concrete, type B (605-06121)LFT156$60.00$166.00$110.00$93.22$107.00
0063Reinforced concrete bridge approach, 10 in. (609-06257)SYS236$140.00$130.00$120.00$165.00$235.00
0064Reinforced concrete bridge approach, 15 in. (609-06263)SYS1,095$165.00$160.00$190.00$210.00$300.00
0065Riprap, revetment (616-06405)TON364$170.00$104.00$153.00$100.00$150.00
0066Geotextile for riprap, type 1A (616-12246)SYS837$3.00$6.00$4.50$2.79$1.25
0067Inspection hole (616-93772)EACH6$400.00$600.00$235.00$286.11$550.00
0068Clean steel bridge, partial, QP-2, bridge no. 3 (619-11050)LS1$10,000$600.00$600.00$25,000$600.00
0069Clean steel bridge, QP-2, bridge no. 3 (619-11052)LS1$160,000$142,000$142,000$356,836$142,000
0070Disposal of cleaning waste, hazardous, bridge no. 3 (619-12459)LS1$4,000.00$5,000.00$5,000.00$5,000.00$5,000.00
0071Clean steel bridge, top flanges, type QP-2, bridge no. 3 (619-12506)LS1$20,000$1,000.00$1,000.00$25,000$11,000
0072Coat steel bridge, bridge no. 3 (619-51859)LS1$40,000$91,000$91,000$50,000$91,000
0073Coat steel bridge, partial, bridge no. 3 (619-51860)LS1$2,000.00$200.00$200.00$200.00$200.00
0074Mobilization and demobilization for seeding (621-01004)EACH4$500.00$500.00$300.00$400.00$300.00
0075Erosion control blanket (621-02770)SYS605$1.88$1.88$5.75$1.30$5.75
0076Mulched seeding, type R (621-06559)SYS605$1.50$1.50$3.28$1.30$3.28
0077Water (621-06567)KGAL4$50.00$50.00$5.00$50.00$5.00
0078Sodding (621-06574)SYS409$16.00$16.00$22.50$8.00$19.25
0079Seed mixture, emergent wetland (621-06737)LBS5$400.00$400.00$530.00$50.00$530.00
0080Computer system equipment (628-11976)EACH3$200.00$500.00$750.00$291.79$810.00
0081Field office, type D (628-12683)MOS18$3,200.00$2,500.00$3,500.00$4,500.00$3,900.00
0082Field drilled hole in concrete (702-51863)EACH200$60.00$35.00$20.00$25.32$55.00
0083Concrete, C, substructure (702-92857)CYS3.50$1,800.00$7,600.00$5,900.00$5,000.00$8,500.00
0084Reinforcing bars, epoxy coated (703-06029)LBS185,149$1.20$1.30$1.45$1.16$2.00
0085Threaded tie bar assembly, epoxy coated (703-97936)EACH666$39.00$45.00$50.00$45.36$60.00
0086Concrete, C, superstructure (704-51002)CYS296$950.00$1,000.00$1,150.00$1,350.00$1,900.00
0087Bridge railing pedestrian fence (706-11455)LFT520$93.00$93.00$147.50$93.00$85.00
0088Railing, concrete type FC (706-11600)CYS50$1,200.00$650.00$650.00$1,320.36$650.00
0089Concrete bridge railing transition, type TFC (706-11620)EACH4$4,500.00$2,000.00$4,250.00$2,946.14$2,000.00
0090Concrete bridge railing transition, type TFT (706-11621)EACH4$4,500.00$6,000.00$5,000.00$4,690.90$4,000.00
0091Grout, non-shrink (708-01112)CYS0.60$5,000.00$16,400$6,500.00$11,316$30,000
0092Welded steel wire reinforcement (708-51814)SFT29$10.00$40.00$10.00$10.00$10.00
0093Surface seal , bridge no. 1 (709-51821)LS1$3,000.00$3,000.00$3,000.00$3,100.00$3,000.00
0094Surface seal , bridge no. 2 (709-51821)LS1$3,000.00$3,000.00$3,000.00$3,100.00$3,000.00
0095Surface seal , bridge no. 3 (709-51821)LS1$3,000.00$5,000.00$5,500.00$5,600.00$0.01
0096Patching concrete structures (710-09158)SFT29$279.00$400.00$305.00$279.00$279.00
0097Structural steel (711-51038)LS1$292,847$300,000$290,000$350,000$290,000
0098Drilled hole (711-51864)EACH3,240$34.00$35.00$26.00$34.00$75.00
0099Jacking and supporting beams , bridge no. 3 (711-51877)LS1$99,421$100,000$25,000$75,000$100,000
0100Bolt, remove (711-96479)EACH168$392.00$10.00$55.40$392.00$275.00
0101Stud shear connectors (711-96800)EACH4,428$5.68$5.08$11.50$5.08$7.00
0102Casting, inlet, adjust to grade (720-12797)EACH2$1,300.00$800.00$1,525.00$2,391.76$1,100.00
0103Hydrodemolition (722-01066)SYS1,368$125.00$150.00$88.00$119.21$125.00
0104Bridge deck overlay budget (722-12380)DOL40,200$1.00$1.00$1.00$1.00$1.00
0105Bridge deck, remove existing concrete surface (722-12464)SYS1,368$20.50$15.00$21.00$29.68$20.00
0106Longitudinal grooving (722-12732)SYS3,685$8.50$8.00$32.00$7.42$10.00
0107Bridge deck patching, full depth (722-51401)SFT616$75.00$30.00$5.00$112.15$25.00
0108Bridge deck overlay, latex modified (722-51842)SYS1,368$110.00$120.00$160.00$175.00$225.00
0109Overlay dam (722-51874)SFT292$20.00$80.00$40.00$77.76$100.00
0110Bearing assembly, elastomeric (726-92406)EACH30$4,590.85$3,000.00$2,100.00$1,174.95$2,750.00
0111Construction sign, type C (801-03290)EACH4$271.00$271.00$271.00$271.00$271.00
0112Road closure sign assembly (801-04308)EACH4$274.00$274.00$274.00$274.00$274.00
0113Temporary pavement marking, removable, 6 in. (801-06209)LFT287,478$1.59$1.59$1.59$1.59$1.59
0114Temporary pavement marking, removable, 8 in. (801-06469)LFT180$5.12$5.12$5.12$5.12$5.12
0115Detour route marker assembly (801-06625)EACH19$166.00$166.00$166.00$166.00$166.00
0116Construction sign, type A (801-06640)EACH178$234.00$234.00$234.00$234.00$234.00
0117Construction sign, type B (801-06645)EACH34$117.00$117.00$117.00$117.00$117.00
0118Temporary raised pavement marker, grade 2 (801-06650)EACH2,441$9.85$9.85$9.85$9.85$9.85
0119Flashing arrow sign (801-06710)DAY438$16.00$16.00$16.00$16.00$16.00
0120Maintaining traffic (801-06775)LS1$500,000$1,800,000$820,000$778,734$490,000
0121Energy absorbing terminal, CZ, TL-3 (801-07024)EACH10$7,408.00$5,000.00$7,500.00$7,408.00$7,335.00
0122Barricade, type III-A (801-07118)LFT164$15.43$15.43$15.43$15.43$15.43
0123Barricade, type III-B (801-07119)LFT24$15.43$15.43$15.43$15.43$15.43
0124Temporary traffic barrier, type 2 (801-08401)LFT32,965$35.00$1.00$43.85$68.00$50.00
0125Temporary traffic barrier, anchored, type 2 (801-08508)LFT4,740$19.00$10.00$43.85$37.66$65.00
0126Portable changeable message sign (801-11642)EACH4$5,853.00$5,853.00$5,853.00$5,853.00$5,853.00
0127Truck mounted attenuator (801-12042)DAY150$475.00$100.00$10.00$475.00$1,000.00
0128Automated work zone information system (801-12544)EACH4$20,165$20,165$20,165$20,165$20,165
0129Temporary worksite speed limit sign assembly, continuous (801-12883)EACH12$3,988.00$3,988.00$3,988.00$3,988.00$3,988.00
0130Temporary buzz strips (801-97643)LFT2,592$19.20$19.20$19.20$19.20$19.20
0131Reference post (802-04893)EACH2$474.00$298.85$300.00$474.00$250.00
0132Sign post, square, type 1, reinforced anchor base (802-05701)LFT20$42.00$34.44$34.00$42.00$25.00
0133Sign post, square, type 1, unreinforced anchor base (802-05704)LFT10$84.00$33.04$30.00$84.00$24.00
0134Sign, sheet, with legend, 0.100 in. thickness (802-09840)SFT22$48.00$30.95$40.00$48.00$44.00
0135Conduit, PVC, 3 in. (805-06600)LFT100$40.00$5.00$60.00$26.15$4.00
0136Line, paint, solid, white, 4 in. (808-06713)LFT964$2.11$2.11$2.11$2.11$2.11
0137Line, paint, solid, yellow, 4 in. (808-06714)LFT964$2.11$2.11$2.11$2.11$2.11
0138Line, remove (808-06716)LFT172,896$0.51$0.51$0.51$0.51$0.51
0139Retro-reflectivity testing (808-09381)LS1$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00
0140Line, multi-component, solid, white, 6 in. (808-10049)LFT8,252$1.06$1.06$1.06$1.06$1.06
0141Line, multi-component, solid, yellow, 6 in. (808-10057)LFT11,969$1.06$1.06$1.06$1.06$1.06
0142Line, multi-component, broken, white, 6 in. (808-10071)LFT5,970$1.33$1.33$1.33$1.33$1.33
0143Grooving for pavement markings (808-12032)LFT163,611$0.67$0.67$0.67$0.67$0.67
0144Prismatic reflector (808-75994)EACH272$9.15$9.15$9.15$9.15$9.15
0145Jointed reinforced concrete pavement, 15 in. (503-12668)SYS1,126$255.00$200.00$240.00$147.89$280.00
0146Line, preformed plastic, solid, white, 6 in. (808-75052)LFT57,320$6.89$6.89$6.89$6.89$6.89
0147Line, preformed plastic, broken, white, 6 in. (808-75055)LFT28,660$7.71$7.71$7.71$7.71$7.71
0148Line, preformed plastic, solid, yellow, 6 in. (808-75057)LFT57,320$6.89$6.89$6.89$6.89$6.89
0149Snowplowable raised pavement marker, remove (808-75996)EACH1,188$18.65$18.65$18.65$18.65$18.65
0150Snowplowable raised pavement marker (808-75998)EACH1,188$31.55$31.55$31.55$31.55$31.55
INDOT contract R-43004-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy