INDOT contract R-43164-A bid tabulation

SLIDE CORRECTION. Let by Indiana DOT on July 9, 2025, Dearborn, Seymour. 9 bids received; low bid $2,390,727 by Paul H Rohe Company Inc.

Owner
Indiana DOT
Letting
09 JUL 2025
Pay items
70
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Paul H Rohe Company Inc$2,390,727Low
2Force Construction Co Inc$2,421,396+1.0%
3Milestone Contractors LP$2,436,000+2.0%
45 Star Company Inc$2,525,605+6.0%
5Beaty Construction Inc$2,532,342+6.0%
6Morphey Construction Inc.$2,624,000+10%
7Sunesis Construction Company$2,779,680+16%
8Dave Omara Contractor Inc$2,824,063+18%
9Olco Inc$3,838,610+61%
INDOT contract R-43164-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Paul H Rohe Company Inc2. Force Construction Co Inc3. Milestone Contractors LP4. 5 Star Company Inc5. Beaty Construction Inc6. Morphey Construction Inc.
0001Construction engineering (105-06845)LS1$12,630$13,120$15,000$17,500$42,500$15,000
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0007Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0008Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0009Mobilization and demobilization (110-01001)LS1$72,960$120,000$123,250$72,000$126,617$130,000
0010Clearing right-of-way (201-52370)LS1$31,696$68,990$58,559$37,500$50,645$140,000
0011Guardrail end treatment, remove (202-93741)EACH1$1,050.00$468.00$450.00$300.00$450.00$430.00
0012Pipe, remove (202-96133)LFT72$37.00$74.00$73.65$25.00$40.00$28.00
0013Fence, farm field, remove (202-99187)LFT22$16.50$17.00$53.40$10.00$30.00$4.00
0014Excavation, common (203-02000)CYS19,525$21.00$16.00$26.35$30.00$28.25$19.00
0015Excavation, rock (203-02010)CYS597$180.00$77.00$105.45$46.00$74.25$110.00
0016Pump around (205-11626)EACH2$2,900.00$12,630$11,200$6,500.00$18,250$40,000
0017Stormwater management budget (205-12108)DOL17,443$1.00$1.00$1.00$1.00$1.00$1.00
0018Stormwater management implementation (205-12616)LS1$5,150.00$21,750$14,121$5,500.00$22,500$2,500.00
0019SWQCP preparation (205-12618)LS1$1,600.00$3,637.00$3,500.00$2,900.00$3,000.00$3,450.00
0020Subgrade treatment, type II (207-08264)SYS81$38.00$21.00$40.60$30.00$49.00$32.00
0021Subgrade treatment, type IC (207-09935)SYS2,419$38.00$23.00$26.95$29.00$37.00$38.00
0022Structure backfill, type 1 (211-09264)CYS46$110.00$68.00$114.20$40.00$60.00$87.00
0023Compacted aggregate, no. 2 (301-12231)CYS718$70.00$51.00$62.40$54.00$60.00$97.00
0024Compacted aggregate, no. 8 (301-12233)CYS629$86.00$57.00$66.35$64.00$62.50$107.00
0025Compacted aggregate, no. 53 (301-12234)CYS789$70.00$56.00$68.00$61.00$67.25$97.00
0026Dense graded subbase (302-07455)CYS7$180.00$185.00$201.15$70.00$215.00$145.00
0027Compacted aggregate, no. 53 (303-01180)TON471$50.00$32.00$68.55$40.00$52.00$52.00
0028Widening with HMA, type B (304-07493)TON19$250.00$160.00$264.50$180.00$105.00$350.00
0029Milling, profile (306-11872)SYS339$11.30$15.00$26.85$12.00$21.25$18.00
0030QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001)TON249$135.00$109.00$124.95$165.00$105.00$145.00
0031QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037)TON440$103.00$109.00$122.85$155.00$105.00$125.00
0032QC/QA-HMA, 2, 58S, base, 25.0 MM (401-000046)TON1,027$90.00$109.00$108.70$155.00$105.00$116.00
0033Joint adhesive, surface (401-10258)LFT1,150$0.50$1.00$0.52$1.00$1.00$0.50
0034Joint adhesive, intermediate (401-10259)LFT1,000$0.70$1.00$0.94$1.00$1.00$0.70
0035Asphalt for tack coat (406-05520)TON2$950.00$743.00$797.30$1,500.00$715.00$925.00
0036Guardrail transition, type TGB (601-01522)EACH2$2,550.00$2,858.00$2,750.00$2,850.00$2,750.00$2,750.00
0037Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT1,035$22.00$19.00$18.75$20.00$18.75$18.75
0038Guardrail end treatment, type OS (601-94689)EACH3$3,250.00$3,117.00$3,000.00$3,150.00$3,000.00$3,000.00
0039HMA for approaches, type B (610-07487)TON10$240.00$109.00$494.15$200.00$105.00$350.00
0040PCCP for approaches, 6 in. (610-08446)SYS39$150.00$208.00$158.15$130.00$122.00$90.00
0041Mailbox assembly, single (611-06497)EACH2$195.00$283.00$272.00$285.00$272.00$272.00
0042Monument, type B (615-06505)EACH7$865.00$1,273.00$1,225.00$1,320.00$1,225.00$1,225.00
0043Monument, type C (615-06510)EACH3$600.00$779.00$750.00$840.00$750.00$750.00
0044Riprap, revetment (616-06405)TON23,394$45.00$38.00$38.50$44.00$35.00$40.00
0045Riprap, uniform (616-06451)TON151$80.00$59.00$69.60$49.00$110.00$107.00
0046Geotextile for riprap, type 1B (616-12247)SYS200$4.00$8.20$8.20$4.00$6.00$10.00
0047Geotextile for riprap, type 2A (616-12248)SYS6,221$2.20$5.40$3.20$3.75$3.25$2.50
0048Mobilization and demobilization for seeding (621-01004)EACH2$100.00$104.00$100.00$500.00$100.00$100.00
0049Fertilizer, for permanent seeding , for permanent seeding (621-06545)TON1$50.00$52.00$10.00$500.00$10.00$10.00
0050Seed mixture, type R (621-06553)LBS210$26.00$27.00$27.00$10.00$27.00$145.00
0051Mulching material (621-06565)TON2$1,000.00$1,039.00$700.00$250.00$700.00$700.00
0052Sodding (621-06574)SYS154$40.00$42.00$26.00$12.00$26.00$31.00
0053Computer system equipment (628-11976)EACH3$915.00$267.00$545.50$500.00$1,600.00$800.00
0054Field office, type D (628-12683)MOS12$3,300.00$5,819.00$3,858.45$1,550.00$7,000.00$2,400.00
0055Pipe end section, diameter 48 in. (715-02246)EACH1$4,160.00$1,750.00$2,824.10$2,800.00$3,275.00$6,700.00
0056Pipe, type 1, circular, diameter 15 in. , RCP (715-05119)LFT51$145.00$121.00$70.10$100.00$91.25$178.00
0057Pipe, type 3, circular, diameter 15 in. , RCP (715-05169)LFT29$130.00$98.00$76.00$100.00$132.35$178.00
0058Pipe extension, circular, diameter 36 in. , CMP (715-05757)LFT26$195.00$309.00$384.70$195.00$285.00$220.00
0059Pipe extension, circular, diameter 48 in. , CMP (715-06337)LFT27$206.00$264.00$268.30$275.00$295.00$325.00
0060Pipe end section, diameter 15 in. (715-46005)EACH5$2,550.00$492.00$3,480.10$1,500.00$1,830.00$1,800.00
0061Pipe end section, diameter 36 in. (715-46040)EACH2$2,205.00$2,041.00$2,167.55$1,700.00$2,400.00$3,000.00
0062Road closure sign assembly (801-04308)EACH4$350.00$234.00$371.00$240.00$349.68$350.00
0063Detour route marker assembly (801-06625)EACH34$147.00$99.00$185.00$112.00$146.57$100.00
0064Construction sign, type A (801-06640)EACH4$250.00$130.00$323.00$136.00$249.61$250.00
0065Maintaining traffic (801-06775)LS1$7,800.00$276,150$25,000$54,000$119,899$79,450
0066Barricade, type III-B (801-07119)LFT96$17.00$17.00$16.45$17.00$16.89$22.00
0067Sign post, square, type 1, reinforced anchor base (802-05701)LFT52$35.50$33.00$32.00$37.00$35.18$32.00
0068Sign, sheet, and supports, remove (802-07059)EACH1$39.00$239.00$230.00$220.00$38.69$230.00
0069Sign, sheet, with legend, 0.080 in. thickness (802-09838)SFT14$39.00$76.00$73.00$33.00$38.31$73.00
0070Line, paint, solid, yellow, 4 in. (808-06714)LFT2,300$1.00$1.00$0.52$1.00$0.96$1.00
INDOT contract R-43164-A: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy