INDOT contract R-43751-A bid tabulation
SMALL STRUCTURES AND DRAINS CONSTRUCTION. Let by Indiana DOT on August 6, 2025, Dearborn, Seymour. 8 bids received; low bid $559,989 by 5 Star Company Inc.
- Owner
- Indiana DOT
- Letting
- 06 AUG 2025
- Pay items
- 63
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | 5 Star Company Inc | $559,989 | Low |
| 2 | Paul H Rohe Company Inc | $564,078 | +1.0% |
| 3 | Olco Inc | $574,955 | +3.0% |
| 4 | Morphey Construction Inc. | $615,680 | +10% |
| 5 | Dave Omara Contractor Inc | $653,364 | +17% |
| 6 | Force Construction Co Inc | $668,135 | +19% |
| 7 | Sunesis Construction Company | $765,694 | +37% |
| 8 | Milestone Contractors LP | $990,377 | +77% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. 5 Star Company Inc | 2. Paul H Rohe Company Inc | 3. Olco Inc | 4. Morphey Construction Inc. | 5. Dave Omara Contractor Inc | 6. Force Construction Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $12,000 | $6,600.00 | $14,600 | $15,000 | $9,000.00 | $8,304.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $28,000 | $26,135 | $17,970 | $32,000 | $32,668 | $37,500 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $13,000 | $28,959 | $23,774 | $14,000 | $20,000 | $33,690 |
| 0011 | Pipe, remove (202-96133) | LFT | 177 | $25.00 | $170.00 | $159.18 | $30.00 | $150.00 | $68.00 |
| 0012 | Excavation, common (203-02000) | CYS | 283 | $35.00 | $70.00 | $54.40 | $70.00 | $50.00 | $79.00 |
| 0013 | Borrow (203-02070) | CYS | 22 | $10.00 | $110.00 | $97.89 | $60.00 | $42.00 | $180.00 |
| 0014 | Stormwater management budget (205-12108) | DOL | 36,898 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $7,500.00 | $2,500.00 | $4,929.57 | $800.00 | $29,625 | $15,790 |
| 0016 | Subgrade treatment, type II (207-08264) | SYS | 62 | $32.00 | $52.00 | $29.37 | $41.00 | $40.00 | $196.00 |
| 0017 | Subgrade treatment, type IC (207-09935) | SYS | 106 | $43.50 | $70.00 | $51.22 | $65.00 | $62.00 | $28.00 |
| 0018 | Structure backfill, type 1 (211-09264) | CYS | 770 | $159.00 | $78.00 | $80.29 | $100.00 | $84.00 | $61.00 |
| 0019 | Structure backfill, type 2 (211-09265) | CYS | 156 | $68.00 | $94.00 | $80.35 | $100.00 | $100.00 | $98.00 |
| 0020 | Geotextile for pavement, type 2B (214-12239) | SYS | 106 | $5.00 | $5.00 | $5.47 | $20.00 | $7.75 | $14.00 |
| 0021 | Compacted aggregate, no. 5 (301-12232) | CYS | 18 | $45.00 | $200.00 | $119.05 | $175.00 | $110.00 | $92.00 |
| 0022 | Compacted aggregate, no. 53 (301-12234) | CYS | 11 | $45.00 | $200.00 | $99.02 | $160.00 | $80.00 | $102.00 |
| 0023 | Compacted aggregate, no. 53 (303-01180) | TON | 344 | $37.00 | $44.00 | $59.69 | $60.00 | $40.00 | $42.00 |
| 0024 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 1,304 | $3.00 | $5.10 | $7.21 | $7.00 | $8.50 | $6.00 |
| 0025 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 117 | $190.00 | $190.00 | $215.67 | $230.00 | $184.00 | $234.00 |
| 0026 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 15 | $180.00 | $250.00 | $186.23 | $295.00 | $184.00 | $234.00 |
| 0027 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 47 | $177.00 | $245.00 | $176.62 | $290.00 | $184.00 | $234.00 |
| 0028 | Joint adhesive, surface (401-10258) | LFT | 419 | $1.00 | $1.10 | $1.89 | $1.10 | $3.75 | $1.00 |
| 0029 | Asphalt for tack coat (406-05520) | TON | 6 | $1,100.00 | $950.00 | $1,999.22 | $1,050.00 | $650.00 | $676.00 |
| 0030 | Guardrail terminal system, W-beam curved, type 1 (601-01700) | EACH | 1 | $3,000.00 | $2,850.00 | $3,350.00 | $3,350.00 | $3,200.00 | $2,966.00 |
| 0031 | Guardrail terminal system, W-beam curved, type 4 (601-01740) | EACH | 1 | $2,850.00 | $2,750.00 | $3,450.00 | $3,450.00 | $3,200.00 | $2,862.00 |
| 0032 | Guardrail, remove (601-02241) | LFT | 987 | $5.00 | $3.00 | $4.50 | $4.50 | $3.50 | $3.10 |
| 0033 | Guardrail, W-beam, cable terminal anchor (601-06855) | EACH | 2 | $1,450.00 | $1,350.00 | $1,225.00 | $1,225.00 | $1,500.00 | $1,405.00 |
| 0034 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 888 | $23.50 | $21.50 | $24.50 | $24.50 | $24.00 | $22.00 |
| 0035 | Guardrail end treatment, type OS (601-94689) | EACH | 2 | $3,200.00 | $3,000.00 | $3,350.00 | $3,350.00 | $3,400.00 | $3,122.00 |
| 0036 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 419 | $14.00 | $12.00 | $12.00 | $34.00 | $7.50 | $1.00 |
| 0037 | HMA for approaches, type B (610-07487) | TON | 14 | $200.00 | $230.00 | $317.29 | $400.00 | $265.00 | $234.00 |
| 0038 | Right-of-way marker (615-06490) | EACH | 6 | $235.00 | $215.00 | $250.00 | $250.00 | $225.00 | $224.00 |
| 0039 | Monument, type B (615-06505) | EACH | 2 | $1,800.00 | $1,700.00 | $1,050.00 | $1,050.00 | $1,900.00 | $1,769.00 |
| 0040 | Riprap, class 1 (616-05688) | TON | 12 | $100.00 | $230.00 | $106.38 | $162.00 | $90.00 | $74.00 |
| 0041 | Riprap, class 2 (616-05689) | TON | 19 | $100.00 | $200.00 | $106.61 | $162.00 | $90.00 | $72.00 |
| 0042 | Geotextile for riprap, type 2B (616-12249) | SYS | 188 | $5.00 | $6.00 | $5.17 | $12.00 | $7.50 | $7.20 |
| 0043 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $400.00 | $200.00 | $203.24 | $100.00 | $225.00 | $1,249.00 |
| 0044 | Mulched seeding, type R (621-06559) | SYS | 1,086 | $2.00 | $8.00 | $5.12 | $27.00 | $8.50 | $1.00 |
| 0045 | Computer system equipment (628-11976) | EACH | 2 | $400.00 | $900.00 | $500.00 | $800.00 | $1,200.00 | $334.00 |
| 0046 | Field office, type D (628-12683) | MOS | 6 | $1,600.00 | $3,500.00 | $1,100.00 | $2,400.00 | $2,200.00 | $8,425.00 |
| 0047 | Concrete, A, structures (702-44240) | CYS | 20 | $850.00 | $1,740.00 | $1,868.22 | $1,000.00 | $3,075.00 | $730.00 |
| 0048 | Concrete, B, footings (702-51015) | CYS | 35 | $850.00 | $440.00 | $748.47 | $1,000.00 | $690.00 | $420.00 |
| 0049 | Reinforcing bars (703-06028) | LBS | 4,000 | $2.00 | $3.45 | $4.33 | $2.52 | $5.50 | $2.30 |
| 0050 | Pipe, type 1, circular, diameter 36 in. (715-05019) | LFT | 94 | $341.00 | $315.00 | $255.40 | $330.00 | $200.00 | $403.00 |
| 0051 | Pipe, type 1, circular, diameter 30 in. (715-05125) | LFT | 81 | $330.00 | $320.00 | $290.90 | $275.00 | $234.00 | $354.00 |
| 0052 | Video inspection for pipe (715-09064) | LFT | 175 | $18.00 | $15.20 | $18.90 | $15.20 | $20.00 | $10.00 |
| 0053 | Road closure sign assembly (801-04308) | EACH | 14 | $215.00 | $200.00 | $175.00 | $175.00 | $350.00 | $318.00 |
| 0054 | Detour route marker assembly (801-06625) | EACH | 20 | $105.00 | $95.00 | $85.00 | $85.00 | $130.00 | $122.00 |
| 0055 | Construction sign, type A (801-06640) | EACH | 20 | $150.00 | $135.00 | $175.00 | $175.00 | $250.00 | $236.00 |
| 0056 | Maintaining traffic (801-06775) | LS | 1 | $25,000 | $9,770.00 | $19,194 | $17,980 | $19,455 | $67,140 |
| 0057 | Barricade, type III-A (801-07118) | LFT | 72 | $16.00 | $14.00 | $15.00 | $15.00 | $14.00 | $13.00 |
| 0058 | Barricade, type III-B (801-07119) | LFT | 96 | $16.00 | $15.00 | $15.00 | $15.00 | $14.00 | $13.00 |
| 0059 | Portable changeable message sign (801-11642) | EACH | 7 | $1,700.00 | $1,500.00 | $3,000.00 | $3,000.00 | $6,500.00 | $5,692.00 |
| 0060 | Law enforcement officer (801-12324) | HRS | 80 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0061 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 838 | $6.00 | $5.00 | $5.00 | $5.00 | $6.50 | $6.10 |
| 0062 | Grooving for pavement markings (808-12032) | LFT | 943 | $3.00 | $3.00 | $2.00 | $2.00 | $5.50 | $5.00 |
| 0063 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 105 | $5.50 | $5.00 | $5.00 | $5.00 | $6.50 | $6.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.