INDOT contract R-43777-A bid tabulation
SMALL STRUCTURE REPLACEMENT AND BRIDGE DECK OVERLAY. Let by Indiana DOT on October 8, 2025, Decatur, Seymour. 7 bids received; low bid $2,982,539 by Dave Omara Contractor Inc.
- Owner
- Indiana DOT
- Letting
- 08 OCT 2025
- Pay items
- 125
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dave Omara Contractor Inc | $2,982,539 | Low |
| 2 | 5 Star Company Inc | $3,242,503 | +9.0% |
| 3 | His Constructors Inc | $3,446,718 | +16% |
| 4 | Paul H Rohe Company Inc | $3,450,850 | +16% |
| 5 | Force Construction Co Inc | $3,551,520 | +19% |
| 6 | Milestone Contractors LP | $3,657,422 | +23% |
| 7 | Morphey Construction Inc. | $3,785,000 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dave Omara Contractor Inc | 2. 5 Star Company Inc | 3. His Constructors Inc | 4. Paul H Rohe Company Inc | 5. Force Construction Co Inc | 6. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $31,900 | $65,000 | $35,000 | $16,720 | $66,550 | $27,500 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $150,001 | $250,000 | $240,546 | $104,467 | $175,000 | $184,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $60,000 | $21,500 | $52,000 | $59,190 | $32,040 | $325,000 |
| 0012 | Pavement removal (202-02240) | SYS | 130 | $80.00 | $15.00 | $46.00 | $53.00 | $48.00 | $149.05 |
| 0013 | Curb, concrete, remove (202-02278) | LFT | 65 | $20.00 | $26.00 | $26.00 | $43.00 | $19.00 | $25.00 |
| 0014 | Curb and gutter, remove (202-02279) | LFT | 54 | $25.00 | $25.00 | $26.00 | $44.00 | $29.00 | $25.00 |
| 0015 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $5,000.00 | $15,000 | $10,000 | $23,485 | $8,974.00 | $25,000 |
| 0016 | Present structure, remove, structure no. , CV 421-016-40.30 (202-51330) | LS | 1 | $19,000 | $15,000 | $58,000 | $37,490 | $22,500 | $65,938 |
| 0017 | Present structure, remove, structure no. , CV 421-016-46.91 (202-51330) | LS | 1 | $20,000 | $15,000 | $50,000 | $33,050 | $14,800 | $31,442 |
| 0018 | Present structure, remove, structure no. CV 421-016-47.74 (202-51330) | LS | 1 | $7,000.00 | $15,000 | $32,000 | $22,780 | $14,800 | $21,931 |
| 0019 | Sidewalk concrete, remove (202-52710) | SYS | 45 | $60.00 | $35.00 | $37.00 | $60.00 | $35.00 | $35.00 |
| 0020 | Guardrail end treatment, remove (202-93741) | EACH | 10 | $450.00 | $500.00 | $475.00 | $450.00 | $463.00 | $450.00 |
| 0021 | Pipe, remove (202-96133) | LFT | 127 | $27.00 | $15.00 | $99.00 | $45.00 | $29.00 | $60.00 |
| 0022 | Excavation, common (203-02000) | CYS | 2,475 | $45.00 | $40.00 | $31.00 | $70.00 | $53.00 | $57.10 |
| 0023 | Borrow (203-02070) | CYS | 1,923 | $28.00 | $35.00 | $38.00 | $55.00 | $50.00 | $0.01 |
| 0024 | Pump around (205-11626) | EACH | 6 | $12,500 | $4,500.00 | $26,000 | $6,900.00 | $13,400 | $17,000 |
| 0025 | Stormwater management budget (205-12108) | DOL | 46,974 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0026 | Stormwater management implementation (205-12616) | LS | 1 | $2,400.00 | $5,500.00 | $20,000 | $5,500.00 | $33,000 | $67,118 |
| 0027 | Subgrade treatment, type II (207-08264) | SYS | 375 | $29.00 | $33.00 | $16.00 | $36.00 | $28.00 | $31.00 |
| 0028 | Subgrade treatment, type IC (207-09935) | SYS | 5,102.20 | $25.00 | $35.00 | $33.00 | $45.00 | $43.00 | $42.30 |
| 0029 | Structure backfill, type 2 (211-09265) | CYS | 1,537 | $90.00 | $68.00 | $65.00 | $88.00 | $101.00 | $94.20 |
| 0030 | Structure backfill, type 5 (211-09268) | CYS | 130 | $150.00 | $169.00 | $169.00 | $250.00 | $216.00 | $169.75 |
| 0031 | Geotextile for pavement, type 2B (214-12239) | SYS | 3,712.20 | $3.50 | $3.50 | $4.25 | $4.00 | $5.20 | $4.25 |
| 0032 | Compacted aggregate, no. 8 (301-12233) | CYS | 239 | $75.00 | $65.00 | $90.00 | $130.00 | $71.00 | $102.90 |
| 0033 | Compacted aggregate, no. 53 (301-12234) | CYS | 62 | $70.00 | $61.00 | $73.00 | $120.00 | $79.00 | $98.00 |
| 0034 | Compacted aggregate, no. 53 (303-01180) | TON | 856 | $35.00 | $41.00 | $37.00 | $57.00 | $46.00 | $64.00 |
| 0035 | Widening with HMA, type C (304-07494) | TON | 696 | $130.00 | $160.00 | $137.00 | $170.00 | $172.00 | $140.25 |
| 0036 | HMA patching, full depth, type B (304-12623) | TON | 12 | $130.00 | $250.00 | $137.00 | $260.00 | $252.00 | $218.00 |
| 0037 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 5,919.70 | $7.40 | $4.00 | $7.00 | $6.00 | $7.90 | $6.75 |
| 0038 | Lean concrete base, 9 in. (309-12695) | SYS | 265 | $20.00 | $145.00 | $215.00 | $100.00 | $84.00 | $100.85 |
| 0039 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 748.20 | $130.00 | $164.00 | $137.00 | $170.00 | $134.00 | $172.65 |
| 0040 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 434.60 | $130.00 | $160.00 | $137.00 | $160.00 | $134.00 | $122.80 |
| 0041 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 1,382.90 | $130.00 | $145.00 | $137.00 | $120.00 | $134.00 | $114.00 |
| 0042 | Joint adhesive (401-11526) | LFT | 11,605 | $0.50 | $0.85 | $0.55 | $1.10 | $0.50 | $1.14 |
| 0043 | HMA wedge and level, type C (402-07452) | TON | 51 | $130.00 | $165.00 | $137.00 | $180.00 | $134.00 | $171.15 |
| 0044 | Asphalt for tack coat (406-05520) | TON | 7.20 | $650.00 | $1,000.00 | $680.00 | $950.00 | $669.00 | $651.15 |
| 0045 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 1 | $2,500.00 | $1,500.00 | $2,600.00 | $5,500.00 | $2,572.00 | $3,500.00 |
| 0046 | Guardrail, remove (601-02241) | LFT | 2,674 | $3.25 | $5.00 | $3.50 | $3.25 | $3.30 | $3.25 |
| 0047 | Impact attenuator, SD-W1, TL-2 (601-08146) | EACH | 2 | $24,250 | $35,000 | $30,000 | $27,430 | $24,940 | $29,600 |
| 0048 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 2,445 | $21.00 | $25.00 | $22.00 | $21.00 | $22.00 | $21.00 |
| 0049 | Guardrail, MGS, long span, type 2 (601-12288) | EACH | 2 | $1,200.00 | $1,825.00 | $1,260.00 | $1,200.00 | $1,234.00 | $1,200.00 |
| 0050 | Guardrail end treatment, type OS (601-94689) | EACH | 16 | $2,250.00 | $3,200.00 | $2,375.00 | $2,250.00 | $2,314.00 | $2,250.00 |
| 0051 | Sidewalk, concrete (604-06070) | SYS | 23 | $190.00 | $96.00 | $100.00 | $200.00 | $222.00 | $95.00 |
| 0052 | Curb ramp, concrete (604-08086) | SYS | 33 | $200.00 | $199.00 | $205.00 | $210.00 | $179.00 | $195.00 |
| 0053 | Detectable warning surfaces (604-12083) | SYS | 3 | $350.00 | $400.00 | $420.00 | $250.00 | $395.00 | $400.00 |
| 0054 | Curb, concrete (605-06120) | LFT | 65 | $50.00 | $46.00 | $47.00 | $96.00 | $81.00 | $45.00 |
| 0055 | Curb and gutter, concrete (605-06140) | LFT | 28 | $115.00 | $46.00 | $47.00 | $115.00 | $127.00 | $45.00 |
| 0056 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 245 | $200.00 | $231.00 | $300.00 | $186.00 | $203.00 | $283.00 |
| 0057 | HMA for approaches, type B (610-07487) | TON | 81 | $130.00 | $185.00 | $137.00 | $170.00 | $134.00 | $163.00 |
| 0058 | Right-of-way marker (615-06490) | EACH | 46 | $175.00 | $235.00 | $185.00 | $175.00 | $180.00 | $175.00 |
| 0059 | Monument, type B (615-06505) | EACH | 14 | $1,000.00 | $1,000.00 | $1,050.00 | $1,000.00 | $1,029.00 | $1,000.00 |
| 0060 | Riprap, class 1 (616-05688) | TON | 725 | $95.00 | $79.00 | $98.00 | $94.00 | $101.00 | $100.00 |
| 0061 | Riprap, revetment (616-06405) | TON | 1,160 | $75.00 | $65.00 | $64.00 | $70.00 | $81.00 | $84.00 |
| 0062 | Geotextile for riprap, type 1A (616-12246) | SYS | 2,380 | $2.50 | $3.00 | $2.50 | $2.75 | $3.80 | $4.65 |
| 0063 | Geotextile for riprap, type 2A (616-12248) | SYS | 330 | $4.00 | $4.00 | $4.50 | $3.20 | $8.30 | $6.50 |
| 0064 | Mobilization and demobilization for seeding (621-01004) | EACH | 9 | $1,000.00 | $750.00 | $1,050.00 | $1,000.00 | $1,029.00 | $1,000.00 |
| 0065 | Mulched seeding, type R (621-06559) | SYS | 9,221 | $3.00 | $1.50 | $0.50 | $3.00 | $3.10 | $3.00 |
| 0066 | Water (621-06567) | KGAL | 3 | $10.00 | $1.00 | $26.00 | $0.01 | $0.01 | $0.01 |
| 0067 | Sodding (621-06574) | SYS | 281 | $20.00 | $29.00 | $105.00 | $20.00 | $21.00 | $20.00 |
| 0068 | Sodding, nursery (621-06575) | SYS | 28 | $130.00 | $25.00 | $130.00 | $130.00 | $134.00 | $130.00 |
| 0069 | Computer system equipment (628-11976) | EACH | 2 | $900.00 | $500.00 | $450.00 | $930.00 | $889.00 | $3,015.00 |
| 0070 | Field office, type D (628-12683) | MOS | 10 | $2,500.00 | $3,500.00 | $5,180.00 | $3,250.00 | $4,445.00 | $2,500.00 |
| 0071 | Field drilled hole in concrete (702-51863) | EACH | 52 | $19.00 | $21.00 | $50.00 | $33.00 | $52.00 | $22.00 |
| 0072 | Reinforcing bars, epoxy coated (703-06029) | LBS | 15,627 | $1.70 | $2.10 | $1.75 | $1.60 | $1.90 | $2.05 |
| 0073 | Concrete, C, superstructure (704-51002) | CYS | 24 | $1,200.00 | $1,341.00 | $810.00 | $1,540.00 | $1,228.00 | $1,050.00 |
| 0074 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $1,892.35 | $2,500.00 | $2,100.00 | $1,895.00 | $1,947.00 | $1,892.35 |
| 0075 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $3,877.40 | $4,000.00 | $3,100.00 | $3,880.00 | $3,988.00 | $3,877.40 |
| 0076 | Waterproofing membrane, type 2 (714-000086) | SFT | 7,793 | $3.00 | $2.40 | $10.00 | $2.50 | $3.00 | $1.90 |
| 0077 | Structure, reinforced concrete, box sections, 11 FT X 6 FT (714-11078) | LFT | 56 | $2,100.00 | $1,824.00 | $2,350.00 | $2,630.00 | $2,093.00 | $2,181.08 |
| 0078 | Structure, reinforced concrete, box sections, 13 FT X 5 FT (714-11167) | LFT | 92 | $1,700.00 | $1,650.00 | $1,420.00 | $2,015.00 | $1,360.00 | $1,800.50 |
| 0079 | Structure, reinforced concrete, box sections, 8 FT X 5 FT (714-11178) | LFT | 57 | $2,000.00 | $1,196.00 | $2,070.00 | $1,910.00 | $1,303.00 | $1,606.00 |
| 0080 | Structure, reinforced concrete, box sections, 8 FT X 7 FT (714-11180) | LFT | 59 | $1,600.00 | $1,205.00 | $1,120.00 | $1,460.00 | $992.00 | $1,463.00 |
| 0081 | Structure, coated reinforced concrete, box sections, 11 FT X 4 FT (714-12522) | LFT | 44 | $1,800.00 | $1,552.00 | $1,860.00 | $1,900.00 | $2,238.00 | $1,750.35 |
| 0082 | Structure, coated reinforced concrete, box sections, 5 FT X 4 FT (714-12807) | LFT | 53 | $1,400.00 | $915.00 | $1,470.00 | $1,820.00 | $988.00 | $1,047.00 |
| 0083 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 55 | $72.00 | $61.00 | $136.00 | $140.00 | $109.00 | $125.00 |
| 0084 | Pipe, type 1, deformed, min. area 7.4 SFT (715-05239) | LFT | 75 | $80.00 | $280.00 | $326.00 | $415.00 | $354.00 | $319.00 |
| 0085 | Pipe end section, diameter 12 in. (715-46000) | EACH | 1 | $750.00 | $275.00 | $1,575.00 | $1,755.00 | $1,075.00 | $2,432.00 |
| 0086 | Pipe end section, diameter 24 in. (715-46020) | EACH | 1 | $1,000.00 | $450.00 | $2,025.00 | $1,530.00 | $1,028.00 | $2,887.00 |
| 0087 | Pipe end section, min. area 7.4 SFT (715-97804) | EACH | 1 | $1,000.00 | $1,200.00 | $2,900.00 | $3,700.00 | $4,049.00 | $5,660.00 |
| 0088 | Casting, manhole, adjust to grade (720-12798) | EACH | 2 | $400.00 | $790.00 | $950.00 | $1,480.00 | $934.00 | $1,577.00 |
| 0089 | Casting, type 8, furnish and adjust to grade (720-44045) | EACH | 2 | $1,200.00 | $1,250.00 | $1,320.00 | $2,785.00 | $1,903.00 | $2,340.00 |
| 0090 | Casting, type 15, furnish and adjust to grade (720-44080) | EACH | 1 | $1,600.00 | $1,250.00 | $1,850.00 | $3,490.00 | $2,233.00 | $2,890.00 |
| 0091 | Bridge deck overlay, rigid (722-000134) | SYS | 176 | $265.00 | $300.00 | $275.00 | $450.00 | $302.00 | $291.50 |
| 0092 | Hydrodemolition (722-01066) | SYS | 176 | $220.00 | $150.00 | $305.00 | $360.00 | $321.00 | $261.75 |
| 0093 | Bridge deck overlay budget (722-12380) | DOL | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0094 | Bridge deck, remove concrete surface (722-12464) | SYS | 176 | $55.00 | $30.00 | $57.00 | $35.00 | $57.00 | $23.00 |
| 0095 | Longitudinal grooving (722-12732) | SYS | 258 | $10.00 | $19.00 | $19.00 | $9.60 | $11.00 | $17.90 |
| 0096 | Bridge deck patching, full depth (722-51401) | SFT | 50 | $77.00 | $175.00 | $196.00 | $299.66 | $103.00 | $50.00 |
| 0097 | Bridge deck patching, partial depth (722-51852) | SFT | 97 | $3.77 | $3.00 | $108.00 | $5.00 | $5.10 | $5.00 |
| 0098 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 10 | $58.82 | $12.00 | $10.50 | $15.00 | $15.00 | $15.00 |
| 0099 | Epoxy injection, crack preparation (727-90308) | LFT | 150 | $37.41 | $2.50 | $2.65 | $25.00 | $26.00 | $25.00 |
| 0100 | Epoxy injection, furnishing equipment , bridge no. 2 (727-93560) | LS | 1 | $965.08 | $100.00 | $106.00 | $2,500.00 | $2,572.00 | $2,500.00 |
| 0101 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 538 | $52.91 | $59.00 | $58.00 | $53.00 | $61.00 | $52.91 |
| 0102 | Road closure sign assembly (801-04308) | EACH | 10 | $274.00 | $300.00 | $350.00 | $274.00 | $334.00 | $325.00 |
| 0103 | Detour route marker assembly (801-06625) | EACH | 44 | $171.00 | $85.00 | $160.00 | $171.00 | $156.00 | $152.00 |
| 0104 | Construction sign, type A (801-06640) | EACH | 68 | $231.00 | $180.00 | $195.00 | $231.00 | $190.00 | $185.00 |
| 0105 | Construction sign, type B (801-06645) | EACH | 20 | $124.00 | $80.00 | $125.00 | $124.00 | $118.00 | $115.00 |
| 0106 | Maintaining traffic (801-06775) | LS | 1 | $85,000 | $235,000 | $30,000 | $38,940 | $309,084 | $55,000 |
| 0107 | Barricade, type III-A (801-07118) | LFT | 216 | $15.44 | $20.00 | $18.00 | $15.44 | $17.00 | $17.00 |
| 0108 | Barricade, type III-B (801-07119) | LFT | 180 | $15.44 | $20.00 | $18.00 | $15.44 | $17.00 | $17.00 |
| 0109 | Portable changeable message sign (801-11642) | EACH | 2 | $5,281.00 | $6,050.00 | $7,000.00 | $5,281.00 | $6,743.00 | $6,555.00 |
| 0110 | Temporary curb ramp (801-11990) | EACH | 3 | $1,100.00 | $2,500.00 | $6,900.00 | $1,040.00 | $4,134.00 | $4,200.00 |
| 0111 | Temporary pedestrian channelizer (801-12862) | LFT | 260 | $19.24 | $31.00 | $72.00 | $12.00 | $24.00 | $21.55 |
| 0112 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 49 | $24.00 | $29.00 | $25.00 | $24.00 | $25.00 | $24.00 |
| 0113 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 16 | $25.00 | $25.00 | $26.00 | $25.00 | $26.00 | $25.00 |
| 0114 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 32 | $35.00 | $31.00 | $37.00 | $35.00 | $36.00 | $35.00 |
| 0115 | Delineator post, flexible, type I (804-11920) | EACH | 8 | $100.00 | $68.00 | $40.00 | $205.57 | $283.00 | $38.00 |
| 0116 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 5,305 | $0.91 | $2.10 | $1.20 | $0.91 | $1.20 | $1.15 |
| 0117 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 3,442 | $0.91 | $2.10 | $1.20 | $0.91 | $1.20 | $1.15 |
| 0118 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 1,769 | $1.54 | $2.10 | $1.20 | $1.54 | $1.20 | $1.15 |
| 0119 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 200 | $2.19 | $3.70 | $2.10 | $2.19 | $2.10 | $2.00 |
| 0120 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 241 | $2.19 | $3.70 | $2.10 | $2.19 | $2.10 | $2.00 |
| 0121 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 52 | $14.81 | $16.00 | $17.00 | $14.81 | $16.00 | $16.00 |
| 0122 | Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300) | LFT | 107 | $6.91 | $6.00 | $6.00 | $6.91 | $5.70 | $5.55 |
| 0123 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 15 | $121.21 | $20.00 | $25.00 | $22.00 | $206.00 | $85.95 |
| 0124 | Snowplowable raised pavement marker (808-75998) | EACH | 15 | $92.00 | $155.00 | $58.00 | $92.00 | $57.00 | $55.00 |
| 0125 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 25 | $4.59 | $6.00 | $5.25 | $4.59 | $5.10 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of October 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.