INDOT contract R-43788-A bid tabulation

SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on December 10, 2025, Ripley, Seymour. 8 bids received; low bid $466,102 by Olco Inc.

Owner
Indiana DOT
Letting
10 DEC 2025
Pay items
59
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Olco Inc$466,102Low
2Dave Omara Contractor Inc$466,3800.0%
35 Star Company Inc$468,1660.0%
4Paul H Rohe Company Inc$525,542+13%
5Morphey Construction Inc.$554,554+19%
6Paf Construction, LLC$586,473+26%
7Force Construction Co Inc$640,000+37%
8Sunesis Construction Company$659,746+42%
INDOT contract R-43788-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Olco Inc2. Dave Omara Contractor Inc3. 5 Star Company Inc4. Paul H Rohe Company Inc5. Morphey Construction Inc.6. Paf Construction, LLC
0001Construction engineering (105-06845)LS1$9,900.00$9,000.00$18,500$8,900.00$7,000.00$80,000
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0007Project estimate adjustment (109-08463)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0008Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0009Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0010Mobilization and demobilization (110-01001)LS1$10,577$23,319$39,200$21,280$25,000$25,000
0011Clearing right-of-way (201-52370)LS1$22,979$9,327.60$5,500.00$9,855.00$10,000$16,875
0012Excavation, common (203-02000)CYS410$50.49$30.00$45.00$80.00$50.00$45.00
0013Excavation, rock (203-02010)CYS6$109.40$95.00$350.00$250.00$320.00$250.00
0014Borrow (203-02070)CYS65$83.90$39.00$22.00$70.00$45.00$100.00
0015Pump around (205-11626)EACH2$5,375.03$3,700.00$6,450.00$7,770.00$15,000$7,500.00
0016Stormwater management budget (205-12108)DOL1,866$1.00$1.00$1.00$1.00$1.00$1.00
0017Stormwater management implementation (205-12616)LS1$5,670.00$2,800.00$4,200.00$3,500.00$1,500.00$15,000
0018Subgrade treatment, type IC (207-09935)SYS312$48.33$46.50$45.00$54.00$45.00$40.00
0019Structure backfill, type 2 (211-09265)CYS131$76.25$94.00$120.00$100.00$75.00$85.00
0020Structure backfill, type 5 (211-09268)CYS89$256.60$295.00$200.00$240.00$180.00$125.00
0021Geotextile for pavement, type 2B (214-12239)SYS312$6.03$6.25$5.00$5.80$6.00$5.00
0022Compacted aggregate, no. 5 (301-12232)CYS38$95.59$104.00$100.00$150.00$130.00$95.00
0023Compacted aggregate, no. 8 (301-12233)CYS27$85.92$98.00$100.00$160.00$140.00$90.00
0024Compacted aggregate, no. 53 (303-01180)TON174$56.35$37.00$50.00$65.00$85.00$50.00
0025Milling, transition (306-08043)SYS646$13.32$5.00$7.00$10.00$18.00$8.00
0026QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002)TON76$233.37$350.00$185.00$280.00$290.00$265.00
0027QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038)TON38$215.96$350.00$180.00$270.00$285.00$250.00
0028QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON88$215.96$350.00$150.00$240.00$270.00$225.00
0029Joint adhesive (401-11526)LFT490$1.79$0.50$1.00$1.60$1.75$1.00
0030Asphalt for tack coat (406-05521)SYS1,186$1.14$0.50$0.85$1.00$1.10$1.00
0031Right-of-way marker (615-06490)EACH10$207.00$210.00$220.00$207.00$207.00$240.00
0032Monument, type B (615-06505)EACH4$1,300.00$1,350.00$1,350.00$1,300.00$1,300.00$1,500.00
0033Riprap, class 1 (616-05688)TON165$57.19$95.00$100.00$115.00$115.00$95.00
0034Riprap, revetment (616-06405)TON114$74.60$63.00$90.00$110.00$110.00$90.00
0035Geotextile for riprap, type 1A (616-12246)SYS436$3.61$4.50$5.00$2.60$3.00$5.00
0036Mobilization and demobilization for seeding (621-01004)EACH2$228.42$1,025.00$350.00$1,000.00$1,000.00$1,150.00
0037Seed mixture, native (621-03909)LBS1$174.62$1,525.00$200.00$1,500.00$2,200.00$1,725.00
0038Seed mixture , pollinator mix (621-04258)LBS1$210.18$1,525.00$200.00$1,500.00$2,500.00$1,725.00
0039Seed mixture , stream mix (621-04258)LBS1$314.78$1,525.00$200.00$1,500.00$2,200.00$1,725.00
0040Mulched seeding, type R (621-06559)SYS1,445$1.93$1.50$2.00$1.45$8.00$3.00
0041Mulching material (621-06565)TON1$3,084.41$925.00$150.00$900.00$900.00$1,000.00
0042Sodding (621-06574)SYS123$16.64$31.00$19.00$30.00$35.00$35.00
0043Computer system equipment (628-11976)EACH2$700.00$250.00$400.00$900.00$1,000.00$850.00
0044Field office, type D (628-12683)MOS6$900.00$2,000.00$1,500.00$3,500.00$2,000.00$4,000.00
0045Waterproofing membrane, type 2 (714-000086)SFT1,855$4.98$3.50$3.20$4.15$6.00$10.00
0046Structure, reinforced concrete, box sections, 8 FT X 4 FT (714-11177)LFT40$1,941.89$1,960.00$1,750.00$1,885.00$2,500.00$1,975.00
0047Structure, reinforced concrete, box sections, 7 FT X 5 FT (714-11311)LFT45$1,995.79$1,603.00$1,120.00$2,205.00$2,050.00$1,850.00
0048Geotextile for underdrains, type 2A (718-12307)SYS256$3.41$4.50$5.00$4.00$4.00$5.00
0049Construction sign, type C (801-03290)EACH4$250.00$325.00$251.00$250.00$120.00$287.50
0050Road closure sign assembly (801-04308)EACH16$150.00$125.00$155.00$150.00$170.00$172.50
0051Detour route marker assembly (801-06625)EACH78$75.00$130.00$79.00$75.00$85.00$90.00
0052Construction sign, type A (801-06640)EACH41$150.00$200.00$155.00$150.00$120.00$170.00
0053Maintaining traffic (801-06775)LS1$14,162$8,184.40$56,000$8,930.00$11,977$9,500.00
0054Barricade, type III-B (801-07119)LFT288$13.00$6.25$14.00$13.00$16.00$15.00
0055Line, paint, broken, yellow, 6 in. (808-12764)LFT50$2.00$14.00$2.20$2.00$1.10$2.00
0056Line, paint, solid, white, 6 in. (808-75007)LFT780$1.00$3.25$1.10$1.00$1.10$2.00
0057Line, paint, solid, yellow, 6 in. (808-75047)LFT580$1.00$3.25$1.10$1.00$1.10$2.00
0058Snowplowable raised pavement marker, remove (808-75996)EACH10$19.26$5.00$20.00$42.00$10.00$150.00
0059Snowplowable raised pavement marker (808-75998)EACH10$100.00$110.00$110.00$100.00$100.00$150.00
INDOT contract R-43788-A: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of December 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy