INDOT contract R-43940-A bid tabulation
PAVEMENT REPLACEMENT, SMALL STRUCTURE AND DRAINS. Let by Indiana DOT on March 11, 2026, Hancock, Madison, Greenfield. 4 bids received; low bid $5,644,918 by William Charles Construction Company.
- Owner
- Indiana DOT
- Letting
- 11 MAR 2026
- Pay items
- 113
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | William Charles Construction Company | $5,644,918 | Low |
| 2 | E & B Paving LLC | $5,660,890 | 0.0% |
| 3 | Calumet Civil Contractors Inc | $6,630,000 | +17% |
| 4 | Milestone Contractors LP | $6,703,776 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. William Charles Construction Company | 2. E & B Paving LLC | 3. Calumet Civil Contractors Inc | 4. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $64,000 | $65,500 | $82,000 | $79,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $320,000 | $283,044 | $259,914 | $335,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $139,900 | $39,000 | $65,000 | $134,000 |
| 0012 | Pavement removal (202-02240) | SYS | 3,328 | $13.00 | $22.00 | $26.00 | $24.50 |
| 0013 | Headwall, remove (202-02271) | EACH | 2 | $620.00 | $500.00 | $1,340.00 | $660.00 |
| 0014 | Curb, concrete, remove (202-02278) | LFT | 382 | $7.00 | $20.00 | $25.00 | $18.00 |
| 0015 | Catch basin, remove (202-02928) | EACH | 6 | $500.00 | $800.00 | $1,110.00 | $940.00 |
| 0016 | Sidewalk concrete, remove (202-52710) | SYS | 2,923 | $8.00 | $7.00 | $18.00 | $17.00 |
| 0017 | Inlet, remove (202-91385) | EACH | 6 | $450.00 | $750.00 | $1,108.00 | $658.00 |
| 0018 | Pipe, remove (202-96133) | LFT | 534 | $40.00 | $10.00 | $42.00 | $57.00 |
| 0019 | Excavation, common (203-02000) | CYS | 4,180 | $40.00 | $69.00 | $58.00 | $118.00 |
| 0020 | Stormwater management budget (205-12108) | DOL | 28,967 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0021 | Stormwater management implementation (205-12616) | LS | 1 | $12,500 | $9,500.00 | $70,000 | $40,000 |
| 0022 | SWQCP preparation (205-12618) | LS | 1 | $3,390.00 | $2,100.00 | $5,000.00 | $2,600.00 |
| 0023 | Subgrade treatment, type II (207-08264) | SYS | 2,865 | $30.00 | $31.00 | $32.00 | $34.00 |
| 0024 | Subgrade treatment, type IC (207-09935) | SYS | 17,923 | $40.00 | $38.50 | $40.00 | $45.10 |
| 0025 | Structure backfill, type 2 (211-09265) | CYS | 2,527 | $70.00 | $77.00 | $68.00 | $76.00 |
| 0026 | Structure backfill, type 5 (211-09268) | CYS | 6 | $270.00 | $200.00 | $288.00 | $255.00 |
| 0027 | Geogrid, type IB (214-11796) | SYS | 872 | $3.00 | $3.00 | $2.50 | $3.70 |
| 0028 | Dense graded subbase (302-07455) | CYS | 450 | $100.00 | $100.00 | $220.00 | $135.00 |
| 0029 | Compacted aggregate, no. 53 (303-01180) | TON | 480 | $65.00 | $24.00 | $67.00 | $70.00 |
| 0030 | Milling, transition (306-08043) | SYS | 706 | $3.50 | $10.00 | $26.00 | $8.00 |
| 0031 | Milling, approach (306-08432) | SYS | 176 | $3.50 | $14.00 | $55.00 | $30.00 |
| 0032 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 1,140 | $110.00 | $110.00 | $135.00 | $140.00 |
| 0033 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 1,706 | $100.00 | $100.00 | $135.00 | $145.00 |
| 0034 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 5,923 | $88.00 | $88.00 | $116.00 | $120.00 |
| 0035 | Joint adhesive (401-11526) | LFT | 5,980 | $1.00 | $0.75 | $1.00 | $2.00 |
| 0037 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 6,528 | $4.00 | $3.75 | $4.50 | $4.50 |
| 0038 | Asphalt for tack coat (406-05520) | TON | 16 | $1.00 | $0.01 | $1.00 | $800.00 |
| 0039 | Sidewalk, concrete (604-06070) | SYS | 2,986 | $80.00 | $92.00 | $75.00 | $96.00 |
| 0040 | Curb ramp, concrete (604-08086) | SYS | 227 | $305.00 | $175.00 | $370.00 | $300.00 |
| 0041 | Detectable warning surfaces (604-12083) | SYS | 36 | $200.00 | $250.00 | $462.00 | $275.00 |
| 0042 | Curb, concrete (605-06120) | LFT | 74 | $35.00 | $125.00 | $121.00 | $93.00 |
| 0043 | Curb and gutter, concrete, type B (605-06145) | LFT | 6,349 | $33.00 | $34.00 | $51.00 | $43.00 |
| 0044 | HMA for approaches, type B (610-07487) | TON | 11 | $225.00 | $225.00 | $362.00 | $125.00 |
| 0045 | HMA for approaches, type C (610-07488) | TON | 1,361 | $140.00 | $140.00 | $195.00 | $125.00 |
| 0046 | PCCP for approaches, 6 in. (610-08446) | SYS | 1,823 | $120.00 | $195.00 | $127.00 | $137.00 |
| 0047 | PCCP for approaches, 9 in. (610-09108) | SYS | 872 | $135.00 | $125.00 | $127.00 | $155.00 |
| 0048 | Mailbox assembly, single (611-06497) | EACH | 32 | $265.00 | $460.00 | $460.00 | $311.00 |
| 0049 | Mailbox assembly, double (611-06498) | EACH | 2 | $375.00 | $560.00 | $560.00 | $527.00 |
| 0050 | Right-of-way marker (615-06490) | EACH | 38 | $185.00 | $250.00 | $250.00 | $295.00 |
| 0051 | Monument, type B (615-06505) | EACH | 4 | $1,300.00 | $1,125.00 | $1,125.00 | $1,345.00 |
| 0052 | Riprap, revetment (616-06405) | TON | 13 | $115.00 | $65.00 | $72.00 | $220.00 |
| 0053 | Riprap, uniform (616-06451) | TON | 96 | $30.00 | $70.00 | $75.00 | $105.00 |
| 0054 | Geotextile for riprap, type 1A (616-12246) | SYS | 210 | $3.00 | $6.00 | $4.00 | $8.00 |
| 0055 | Water (621-06567) | KGAL | 26 | $1.00 | $1.00 | $1.00 | $1.05 |
| 0056 | Sodding, nursery (621-06575) | SYS | 6,273 | $4.00 | $4.50 | $13.00 | $4.75 |
| 0057 | Field office, type C (628-09403) | MOS | 24 | $1,900.00 | $2,250.00 | $3,200.00 | $3,900.00 |
| 0058 | Topsoil processing and distribution (629-000149) | SYS | 6,213 | $2.00 | $2.50 | $9.75 | $7.50 |
| 0059 | Topsoil amendment budget (629-000150) | DOL | 12,426 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0060 | Pipe, type 1, circular, diameter 15 in. (715-05119) | LFT | 48 | $94.00 | $85.00 | $96.00 | $140.00 |
| 0061 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 3,284 | $87.00 | $74.00 | $79.00 | $85.00 |
| 0062 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 91 | $97.00 | $85.00 | $85.00 | $110.00 |
| 0063 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 1,049 | $105.00 | $98.00 | $90.00 | $108.00 |
| 0064 | Pipe, type 2, circular, diameter 24 in. (715-05154) | LFT | 1,532 | $130.00 | $130.00 | $125.00 | $137.00 |
| 0065 | Pipe, type 2, circular, diameter 30 in. (715-05156) | LFT | 8 | $515.00 | $355.00 | $200.00 | $350.00 |
| 0066 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 36 | $130.00 | $85.00 | $120.00 | $130.00 |
| 0067 | HMA for structure installation, type B (715-08305) | TON | 25 | $385.00 | $385.00 | $272.00 | $300.00 |
| 0068 | HMA for structure installation, type C (715-08306) | TON | 45 | $125.00 | $125.00 | $340.00 | $300.00 |
| 0069 | Video inspection for pipe (715-09064) | LFT | 6,000 | $1.00 | $1.60 | $2.00 | $1.75 |
| 0070 | Pipe end section, diameter 15 in. (715-46005) | EACH | 7 | $450.00 | $1,350.00 | $2,700.00 | $840.00 |
| 0071 | Pipe end section, diameter 24 in. (715-46020) | EACH | 1 | $375.00 | $1,750.00 | $3,250.00 | $1,100.00 |
| 0072 | Inlet, type HA5, modified (720-09079) | EACH | 5 | $2,620.00 | $3,400.00 | $4,300.00 | $4,000.00 |
| 0073 | Casting, manhole, adjust to grade (720-12798) | EACH | 8 | $1,500.00 | $1,500.00 | $1,270.00 | $990.00 |
| 0074 | Pipe catch basin, 15 in. (720-45265) | EACH | 14 | $3,000.00 | $1,950.00 | $2,900.00 | $1,900.00 |
| 0075 | Manhole, type C4 (720-45410) | EACH | 17 | $5,600.00 | $5,000.00 | $6,000.00 | $4,300.00 |
| 0076 | Structure, inlet, reconstructed (720-45615) | LFT | 3 | $2,600.00 | $750.00 | $780.00 | $1,050.00 |
| 0077 | Manhole, type J2 (720-90129) | EACH | 2 | $6,600.00 | $5,500.00 | $6,800.00 | $5,800.00 |
| 0078 | Manhole, type C8 (720-90349) | EACH | 1 | $5,400.00 | $4,800.00 | $5,900.00 | $5,000.00 |
| 0079 | Manhole, type C2 (720-90984) | EACH | 5 | $5,500.00 | $4,900.00 | $6,050.00 | $5,000.00 |
| 0080 | Manhole, type K4 (720-94612) | EACH | 2 | $9,500.00 | $9,900.00 | $9,900.00 | $7,000.00 |
| 0081 | Manhole, type J4 (720-95422) | EACH | 8 | $8,000.00 | $5,900.00 | $6,900.00 | $5,200.00 |
| 0082 | Inlet, type B15 (720-98174) | EACH | 51 | $2,700.00 | $3,900.00 | $4,600.00 | $4,000.00 |
| 0083 | Inlet, type C15 (720-98555) | EACH | 43 | $3,500.00 | $4,000.00 | $4,700.00 | $4,000.00 |
| 0084 | Construction sign, type D (801-03291) | EACH | 6 | $113.00 | $200.00 | $113.00 | $119.00 |
| 0085 | Road closure sign assembly (801-04308) | EACH | 26 | $233.00 | $325.00 | $233.00 | $246.00 |
| 0086 | Detour route marker assembly (801-06625) | EACH | 53 | $130.00 | $135.00 | $130.00 | $137.00 |
| 0087 | Construction sign, type A (801-06640) | EACH | 20 | $231.00 | $190.00 | $231.00 | $244.00 |
| 0088 | Construction sign, type B (801-06645) | EACH | 23 | $68.00 | $110.00 | $68.00 | $72.00 |
| 0089 | Maintaining traffic (801-06775) | LS | 1 | $145,000 | $94,584 | $150,000 | $33,965 |
| 0090 | Barricade, type III-A (801-07118) | LFT | 336 | $11.00 | $17.00 | $11.00 | $11.60 |
| 0091 | Barricade, type III-B (801-07119) | LFT | 198 | $13.00 | $17.00 | $13.00 | $13.70 |
| 0092 | Portable changeable message sign (801-11642) | EACH | 2 | $3,220.00 | $5,813.00 | $3,220.00 | $3,390.00 |
| 0093 | Temporary curb ramp (801-11990) | EACH | 36 | $2,500.00 | $700.00 | $1,500.00 | $700.00 |
| 0094 | Law enforcement officer (801-12324) | HRS | 500 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0095 | Temporary accessible pedestrian path (801-12641) | SYS | 429 | $92.00 | $28.00 | $120.00 | $86.00 |
| 0096 | Temporary pedestrian channelizer (801-12862) | LFT | 579 | $30.00 | $14.00 | $50.00 | $79.00 |
| 0097 | Reference post (802-04893) | EACH | 1 | $208.00 | $425.00 | $425.00 | $532.00 |
| 0098 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 336 | $26.00 | $30.50 | $30.50 | $50.00 |
| 0099 | Sign post, square, type 2, reinforced anchor base (802-05702) | LFT | 20 | $21.00 | $28.50 | $28.50 | $44.20 |
| 0100 | Sign, sheet, and supports, remove (802-07059) | EACH | 37 | $61.00 | $150.00 | $150.00 | $100.00 |
| 0101 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 162 | $34.00 | $36.00 | $36.00 | $71.05 |
| 0102 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 10 | $36.00 | $44.00 | $44.00 | $63.20 |
| 0103 | Sign, ground mounted, reset (802-91122) | EACH | 9 | $325.00 | $500.00 | $500.00 | $889.50 |
| 0104 | Conduit, PVC, 2 in. schedule 40 (805-08214) | LFT | 373 | $35.00 | $36.00 | $100.00 | $37.90 |
| 0105 | Transverse marking, thermoplastic, crosswalk line, white, 24 in. (808-03439) | LFT | 30 | $9.00 | $12.00 | $9.40 | $9.90 |
| 0106 | Transverse marking, thermoplastic, yield line, white, 24 in. (808-10118) | LFT | 24 | $20.00 | $12.00 | $23.16 | $24.40 |
| 0107 | Grooving for pavement markings (808-12032) | LFT | 9,637 | $1.00 | $0.55 | $0.69 | $0.70 |
| 0108 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 1,869 | $1.00 | $1.00 | $1.08 | $1.15 |
| 0109 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 7,768 | $1.00 | $1.00 | $1.09 | $1.15 |
| 0110 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 145 | $10.00 | $12.00 | $9.40 | $9.90 |
| 0111 | Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300) | LFT | 785 | $2.00 | $4.50 | $2.35 | $2.50 |
| 0112 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 47 | $250.00 | $11.29 | $100.00 | $68.00 |
| 0113 | Snowplowable raised pavement marker (808-75998) | EACH | 47 | $120.00 | $60.00 | $200.00 | $105.00 |
| 0114 | Compacted aggregate, no. 53, temporary for driveways (303-08210) | TON | 1,943 | $32.00 | $43.00 | $49.00 | $23.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of March 11, 2026. Compiled by Mirage Metrics.