KYTC contract 25-2971 bid tabulation
BRIDGE REPLACEMENT KY HWY 805 (KY 805). Let by Kentucky Transportation Cabinet on February 20, 2025, Letcher, District 12. 6 bids received; low bid $609,509 by Central Bridge Co LLC, -3.3% against the engineer's estimate of $630,464.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 FEB 2025
- Pay items
- 25
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Central Bridge Co LLC | $609,509 | Low | -3.0% |
| 2 | Frederick & May Construction Co | $633,980 | +4.0% | +1.0% |
| 3 | Bush & Burchett Inc | $655,980 | +8.0% | +4.0% |
| 4 | Irvine Contracting Limited Liability Company | $717,091 | +18% | +14% |
| 5 | Jave LLC | $732,689 | +20% | +16% |
| 6 | Hinkle Construction Services LLC | $749,541 | +23% | +19% |
Engineer's estimate: $630,464.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Central Bridge Co LLC | 2. Frederick & May Construction Co | 3. Bush & Burchett Inc | 4. Irvine Contracting Limited Liability Company | 5. Jave LLC | 6. Hinkle Construction Services LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A | 197 | $69.00 | $82.85 | $82.85 | $82.85 | $85.34 | $87.00 |
| 0020 | CL2 asph base 1.00D PG64-22 | TON A | 243 | $269.80 | $269.80 | $269.80 | $269.80 | $277.89 | $284.00 |
| 0030 | CL2 asph surf 0.38D PG64-22 | TON A | 39 | $311.50 | $311.50 | $311.50 | $311.50 | $320.85 | $328.00 |
| 0040 | Delineator for guardrail BI directional white | EACH A | 8 | $15.00 | $15.00 | $15.00 | $15.00 | $15.45 | $15.80 |
| 0050 | Fence-4 FT chain link | LF A | 93 | $75.00 | $60.00 | $75.00 | $20.00 | $87.75 | $67.00 |
| 0060 | Guardrail-steel W beam-S face | LF A | 212.50 | $60.00 | $67.50 | $67.50 | $67.50 | $69.53 | $72.00 |
| 0070 | Guardrail terminal section no 1 | EACH A | 3 | $200.00 | $110.00 | $110.00 | $110.00 | $113.30 | $116.00 |
| 0080 | Guardrail end treatment type 1 | EACH A | 1 | $5,000.00 | $4,500.00 | $4,500.00 | $4,500.00 | $4,635.00 | $4,735.00 |
| 0090 | Channel lining class II | TON A | 146 | $75.00 | $50.00 | $60.00 | $67.00 | $78.39 | $64.00 |
| 0100 | Temporary signs | SQFT A | 200 | $18.00 | $21.00 | $25.00 | $18.00 | $12.88 | $20.00 |
| 0110 | Edge key | LF A | 40 | $54.40 | $54.40 | $54.40 | $54.40 | $56.03 | $57.00 |
| 0120 | Maintain & control traffic | LS A | 1 | $25,000 | $38,085 | $60,000 | $50,510 | $40,704 | $108,000 |
| 0125 | Portable changeable message sign | EACH A | 3 | $2,900.00 | $4,240.00 | $1,000.00 | $2,968.00 | $2,292.78 | $3,365.00 |
| 0130 | Staking | LS A | 1 | $10,000 | $6,500.00 | $5,000.00 | $5,000.00 | $5,850.00 | $4,040.00 |
| 0140 | Remove structure | LS A | 1 | $30,000 | $61,277 | $40,000 | $45,458 | $41,041 | $25,100 |
| 0145 | Temp signal multi phase | EACH A | 1 | $15,000 | $30,000 | $20,000 | $18,700 | $18,540 | $21,085 |
| 0150 | Remove & relocate signs | EACH A | 2 | $1,000.00 | $100.00 | $1,000.00 | $375.00 | $877.50 | $2,275.00 |
| 0160 | Erosion control | LS A | 1 | $8,500.00 | $5,000.00 | $15,000 | $9,000.00 | $7,956.00 | $9,910.00 |
| 0170 | Segmental retaining wall | SQFT A | 50 | $100.00 | $25.00 | $50.00 | $150.00 | $87.75 | $150.00 |
| 0180 | Waterproofing membrane | SQYD A | 135 | $50.00 | $30.00 | $50.00 | $55.00 | $58.50 | $46.00 |
| 0190 | Foundation preparation | LS A | 1 | $45,000 | $25,100 | $50,000 | $110,000 | $59,257 | $80,000 |
| 0200 | Concrete-class A | CUYD A | 237.80 | $975.00 | $945.86 | $1,000.00 | $967.00 | $1,244.88 | $1,042.00 |
| 0210 | Steel reinforcement | LB A | 18,157 | $2.10 | $2.08 | $1.75 | $2.06 | $2.21 | $1.80 |
| 0220 | Steel reinforcement-epoxy coated | LB A | 20,525 | $2.00 | $2.20 | $1.75 | $2.18 | $2.45 | $1.95 |
| 0230 | Demobilization | LS A | 1 | $9,050.00 | $9,370.00 | $10,000 | $11,000 | $10,828 | $11,250 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of February 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.