MoDOT contract 250418-C02 bid tabulation
JKU0120 - ROUTE 45 - PLATTE COUNTY. Let by Missouri DOT on April 18, 2025, Platte, Kansas City. 2 bids received; low bid $1,339,403 by Leavenworth Excavating & Equipment Company, Inc..
- Owner
- Missouri DOT
- Letting
- 18 APR 2025
- Pay items
- 59
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Leavenworth Excavating & Equipment Company, Inc. | $1,339,403 | Low |
| 2 | Freeman Concrete Construction LLC | $1,359,505 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Leavenworth Excavating & Equipment Company, Inc. | 2. Freeman Concrete Construction LLC |
|---|---|---|---|---|---|
| 0010 | Signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 |
| 0020 | Clearing and grubbing (2013000) | ACRE | 1 | $12,000 | $4,312.50 |
| 0030 | Removal of improvements (2022010) | LS | 1 | $166,000 | $48,284 |
| 0040 | Class A excavation (2031000) | CY | 735 | $64.30 | $88.94 |
| 0050 | Embankment in place (2035500) | CY | 1,477 | $43.60 | $22.42 |
| 0060 | Compacting embankment (2036000) | CY | 588 | $2.00 | $37.38 |
| 0070 | Class 4 excavation (2063300) | CY | 346 | $92.85 | $84.99 |
| 0080 | Porous backfill (2064000) | CY | 13 | $218.10 | $345.00 |
| 0090 | Linear grading class 1 (2071000) | STA | 3 | $1,100.00 | $1,035.00 |
| 0100 | Subgrade compaction (6-inch depth) (2101006A) | 100F | 15 | $472.20 | $287.50 |
| 0110 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 3,068 | $18.20 | $23.95 |
| 0120 | Gravel (A) or crushed stone (B) (3105002) | TON | 10 | $100.20 | $178.83 |
| 0130 | Asphaltic concrete mixture PG 64-22 (SP125C mix) (4030101) | TON | 382.10 | $111.74 | $117.33 |
| 0140 | Misc.optional pavement (4039905) | SY | 2,778.80 | $66.54 | $97.54 |
| 0150 | Tack coat (4071005) | GAL | 343 | $3.15 | $3.31 |
| 0160 | Concrete pavement (8 1/2 in. non-reinforced, 15 FT. joints) (5021332) | SY | 288.40 | $133.65 | $157.75 |
| 0170 | Modified concrete gutter type B (6071102) | LF | 524 | $62.45 | $46.94 |
| 0180 | Rock lining (6097000) | CY | 284 | $81.10 | $202.79 |
| 0190 | Impact attenuator 55 MPH (sand barrel array) (6122012) | EACH | 2 | $2,500.00 | $2,625.00 |
| 0200 | Replacement sand barrel (6122020) | EACH | 18 | $400.00 | $420.00 |
| 0210 | Impact attenuator (relocation) (6122030) | EACH | 2 | $1,250.00 | $1,312.50 |
| 0220 | Construction signs (6161005) | SF | 621 | $6.00 | $6.30 |
| 0230 | Channelizer (trim line) (6161025) | EACH | 65 | $15.00 | $15.75 |
| 0240 | Type III moveable barricade (6161030) | EACH | 5 | $175.00 | $183.75 |
| 0250 | Flashing arrow panel (6161040) | EACH | 2 | $150.00 | $157.50 |
| 0260 | Changeable message sign with communication interface, contractor furnished, contractor retained (6161099) | EACH | 6 | $2,100.00 | $2,205.00 |
| 0270 | Temporary long-term rumble strips (6162002) | EACH | 4 | $1,850.00 | $1,942.50 |
| 0280 | Concrete traffic barrier, type D (6173100) | LF | 524 | $150.75 | $125.35 |
| 0290 | Temporary traffic barrier, contractor furnished retained (6173600D) | LF | 1,612 | $27.50 | $28.88 |
| 0300 | Temporary traffic barrier height transition (6174000A) | EACH | 1 | $850.00 | $892.50 |
| 0310 | Relocating temporary traffic barrier (6175010A) | LF | 2,068 | $12.00 | $12.60 |
| 0320 | Mobilization (6181000) | LS | 1 | $130,000 | $133,505 |
| 0330 | Additional mobilization for seeding (6181020) | EACH | 2 | $600.00 | $600.00 |
| 0340 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 38 | $28.00 | $29.40 |
| 0350 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 95 | $28.00 | $29.40 |
| 0360 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 2 | $350.00 | $367.50 |
| 0370 | 4 in. white standard waterborne pavement marking paint, type P beads (6206000C) | LF | 5,132 | $0.41 | $0.43 |
| 0380 | 4 in. yellow standard waterborne pavement marking paint, type P beads (6206001C) | LF | 5,870 | $0.41 | $0.43 |
| 0390 | Pavement marking removal (6207001) | LF | 58,920 | $0.25 | $0.26 |
| 0400 | 4 in temporary pavement marking paint (6208076) | LF | 39,280 | $0.16 | $0.17 |
| 0410 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 3,434 | $3.44 | $3.61 |
| 0420 | Permanent erosion control geotextile (6240103A) | SY | 369 | $3.80 | $5.75 |
| 0430 | Bituminous shoulder rumble strip (6261000A) | STA | 25.40 | $98.50 | $599.41 |
| 0440 | Contractor furnished surveying and staking (6274000) | LS | 1 | $10,000 | $13,125 |
| 0450 | Class B-1 concrete (culverts) (7034041) | CY | 77.30 | $1,575.70 | $1,413.92 |
| 0460 | Reinforcing steel (culverts) (7061030) | LB | 14,750 | $0.75 | $0.61 |
| 0470 | Seeding - cool season grasses (8051000A) | ACRE | 1 | $2,000.00 | $2,100.00 |
| 0480 | Sediment trap rock (8061004) | CY | 5 | $116.50 | $230.00 |
| 0490 | Rock ditch check (8061005) | LF | 20 | $61.50 | $48.88 |
| 0500 | Silt fence (8061019) | LF | 1,797 | $3.85 | $1.89 |
| 0510 | Type 1B erosion control blanket (8064132) | SY | 3,421 | $1.50 | $1.58 |
| 0520 | Guardrail type A (6061010) | LF | 113 | $31.54 | $33.12 |
| 0530 | MGS guardrail (6061060) | LF | 250 | $29.79 | $31.28 |
| 0540 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 1 | $4,549.15 | $4,776.61 |
| 0550 | MGS long span guardrail section (6061075) | EACH | 1 | $4,913.94 | $5,159.64 |
| 0560 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 3 | $3,623.94 | $3,805.14 |
| 0570 | Type A crashworthy end terminal (6063015) | EACH | 2 | $3,199.07 | $3,359.03 |
| 0580 | Type C crashworthy end terminal (6063017) | EACH | 2 | $28,328 | $29,744 |
| 0590 | Misc.relocation of existing sign assemblies (9039902) | EACH | 3 | $949.62 | $997.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of April 18, 2025. Compiled by Mirage Metrics.