NJDOT contract 24474 bid tabulation
MTN Pier Protection Contract 2024-1. Let by New Jersey DOT on February 19, 2026, Essex, Hunterdon, Middlesex, Morris, Somerset,, H4. 4 bids received; low bid $2,650,533 by Berto Construction, Inc..
- Owner
- New Jersey DOT
- Letting
- 19 FEB 2026
- Pay items
- 56
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Berto Construction, Inc. | $2,650,533 | Low |
| 2 | Green Construction, Inc. | $3,845,528 | +45% |
| 3 | Power Concrete Co., Inc. | $3,924,924 | +48% |
| 4 | Sparwick Contracting, Inc. | $4,866,644 | +84% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Berto Construction, Inc. | 2. Green Construction, Inc. | 3. Power Concrete Co., Inc. | 4. Sparwick Contracting, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 170,000 | $0.12 | $0.15 | $1.00 | $0.18 |
| 0003 | Mobilization (154003P) | LS | 1 | $134,000 | $180,000 | $164,000 | $240,000 |
| 0004 | Heavy duty silt fence, orange (158009M) | LF | 1,462 | $20.00 | $8.00 | $5.00 | $6.00 |
| 0005 | Inlet filter type 2, 2' X 4' (158030M) | U | 33 | $100.00 | $300.00 | $200.00 | $55.00 |
| 0006 | Breakaway barricade (159003M) | U | 74 | $1.00 | $0.01 | $10.00 | $17.00 |
| 0007 | Drum (159006M) | U | 212 | $1.00 | $0.01 | $1.00 | $1.00 |
| 0008 | Traffic cone (159009M) | U | 212 | $1.00 | $0.01 | $1.00 | $1.00 |
| 0009 | Construction signs (159012M) | SF | 2,346 | $20.00 | $19.00 | $10.00 | $5.00 |
| 0010 | Arrow board, 4' X 8' (159027M) | U | 16 | $1.00 | $0.01 | $500.00 | $1.00 |
| 0011 | Traffic control truck with mounted crash cushion (159108M) | U | 10 | $1.00 | $100.00 | $5,000.00 | $1.00 |
| 0012 | Fuel price adjustment (160004M) | DOL | 1,800 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0013 | Asphalt price adjustment (160007M) | DOL | 1,400 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0014 | Steel price adjustment (160009M) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Clearing site (201003P) | LS | 1 | $10,000 | $268,294 | $40,000 | $177,000 |
| 0016 | Crash cushion, compressive barrier, type 2, width narrow (611300M) | U | 4 | $32,000 | $150,000 | $35,000 | $60,000 |
| 0017 | Regulatory and warning sign (612003P) | SF | 42 | $50.00 | $65.00 | $60.00 | $40.00 |
| 0018 | Roadway junction box (MME090M) | U | 14 | $2,000.00 | $0.01 | $3,000.00 | $5,500.00 |
| 0019 | Pollution liability insurance (152015P) | DOL | 35,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0020 | Chain-link fence, 6' high (605045P) | LF | 88 | $150.00 | $120.00 | $65.00 | $78.00 |
| 0021 | Gate, chain-link fence, 10' wide (605147M) | U | 1 | $5,000.00 | $3,500.00 | $8,000.00 | $5,500.00 |
| 0022 | Field office type B set UP (155006M) | U | 1 | $30,000 | $65,000 | $30,000 | $11,000 |
| 0023 | Field office type B maintenance (155024M) | MO | 12 | $4,000.00 | $10,000 | $3,000.00 | $2,500.00 |
| 0024 | I-5 soil aggregate (203005P) | CY | 142 | $42.00 | $100.00 | $100.00 | $165.00 |
| 0025 | Subbase (301006P) | CY | 125 | $44.00 | $150.00 | $200.00 | $275.00 |
| 0026 | Dense-graded aggregate base course, 8" thick (302042P) | SY | 735 | $24.00 | $50.00 | $35.00 | $83.00 |
| 0027 | Dense-graded aggregate base course, variable thickness (302051P) | CY | 20 | $46.00 | $100.00 | $125.00 | $99.00 |
| 0028 | HMA milling, 3" or less (401009P) | SY | 2,071 | $11.00 | $20.00 | $40.00 | $33.00 |
| 0029 | Hot mix asphalt pavement repair (401021M) | SY | 293 | $163.00 | $0.01 | $300.00 | $40.00 |
| 0030 | Polymerized joint adhesive (401027M) | LF | 9,980 | $0.05 | $2.00 | $2.00 | $2.00 |
| 0031 | Tack coat (401030M) | GAL | 1,097 | $1.00 | $0.01 | $1.00 | $12.00 |
| 0032 | Hot mix asphalt 12.5 M E surface course (401061M) | T | 257 | $100.00 | $200.00 | $400.00 | $440.00 |
| 0033 | Hot mix asphalt 19 M 64 intermediate course (401084M) | T | 100 | $70.00 | $200.00 | $400.00 | $880.00 |
| 0034 | Hot mix asphalt 25 M 64 base course (401099M) | T | 169 | $70.00 | $200.00 | $400.00 | $880.00 |
| 0035 | Core samples, hot mix asphalt (401108M) | U | 4 | $180.00 | $300.00 | $400.00 | $495.00 |
| 0036 | Curb piece (602213M) | U | 8 | $600.00 | $550.00 | $850.00 | $2,200.00 |
| 0037 | Rock backfill (603057P) | T | 597 | $67.00 | $160.00 | $90.00 | $110.00 |
| 0038 | Concrete sidewalk, 4" thick (606012P) | SY | 3,305 | $150.00 | $130.00 | $220.00 | $145.00 |
| 0039 | Concrete island, 4" thick (606075P) | SY | 1,051 | $200.00 | $130.00 | $220.00 | $121.00 |
| 0040 | Concrete island, 6" thick (606078P) | SY | 35 | $300.00 | $175.00 | $220.00 | $220.00 |
| 0041 | Detectable warning surface (606084P) | SY | 1 | $500.00 | $600.00 | $480.00 | $2,750.00 |
| 0042 | 24" X 41" concrete barrier curb (607012P) | LF | 242 | $200.00 | $800.00 | $330.00 | $550.00 |
| 0043 | 9" X 16" concrete vertical curb (607018P) | LF | 3,001 | $75.00 | $100.00 | $110.00 | $170.00 |
| 0044 | 9" X 14" concrete vertical curb (607034P) | LF | 1,576 | $75.00 | $100.00 | $110.00 | $170.00 |
| 0045 | 15" X 51" F shape concrete barrier curb (607110P) | LF | 1,590 | $200.00 | $250.00 | $330.00 | $600.00 |
| 0046 | Nonvegetative surface, hot mix asphalt (608003P) | SY | 2,401 | $65.00 | $60.00 | $60.00 | $70.00 |
| 0047 | Nonvegetative surface, broken stone, ___ " thick , (4" thick) (608015P) | SY | 250 | $60.00 | $70.00 | $55.00 | $45.00 |
| 0048 | Beam guide rail (609003M) | LF | 4,348 | $38.00 | $44.00 | $50.00 | $70.00 |
| 0049 | Tangent guide rail terminal (609027M) | U | 12 | $4,000.00 | $4,000.00 | $4,200.00 | $9,900.00 |
| 0050 | Beam guide rail anchorage (609039M) | U | 16 | $1,500.00 | $1,800.00 | $2,000.00 | $8,250.00 |
| 0051 | Beam guide rail post (609042M) | U | 72 | $100.00 | $100.00 | $120.00 | $245.00 |
| 0052 | Removal of beam guide rail (609075M) | LF | 1,748 | $1.00 | $1.00 | $5.00 | $22.00 |
| 0053 | Reset fire hydrant (651252M) | U | 1 | $15,000 | $5,500.00 | $6,564.00 | $5,500.00 |
| 0054 | Topsoil spreading __" thick , (4" thick) (804000P) | SY | 2,442 | $7.00 | $10.00 | $7.00 | $6.00 |
| 0055 | Fertilizing and seeding, type A (806003P) | SY | 2,442 | $1.00 | $2.50 | $5.00 | $1.00 |
| 0056 | Straw mulching (809003M) | SY | 2,442 | $1.00 | $2.50 | $5.00 | $1.00 |
| 0057 | Concrete washout system (MMR091M) | U | 9 | $4,500.00 | $2,500.00 | $2,500.00 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of February 19, 2026. Compiled by Mirage Metrics.