NYSDOT contract D265423 bid tabulation
Highway Reconstruction Rt 370 Liverpool. Let by New York State DOT on February 27, 2025, Onondaga, Region 03. 5 bids received; low bid $13,885,115 by Rifenburg Construction Inc.
- Owner
- New York State DOT
- Letting
- 27 FEB 2025
- Pay items
- 182
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rifenburg Construction Inc | $13,885,115 | Low |
| 2 | Economy Paving Co Inc | $14,470,105 | +4.0% |
| 3 | Cci Companies Inc | $14,663,898 | +6.0% |
| 4 | Sealand Contractors Corp. | $16,252,000 | +17% |
| 5 | Barrett Paving Materials Inc | $19,898,990 | +43% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rifenburg Construction Inc | 2. Economy Paving Co Inc | 3. Cci Companies Inc | 4. Sealand Contractors Corp. | 5. Barrett Paving Materials Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $28,500 | $200,000 | $50,000 | $25,000 | $15,500 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 17,875 | $35.00 | $10.00 | $85.00 | $58.00 | $85.00 |
| 3 | Embankment In Place (203.03) | CY | 2,684 | $12.00 | $1.00 | $12.00 | $17.00 | $12.20 |
| 4 | Select Granular Fill (203.07) | CY | 6,956 | $53.75 | $65.00 | $95.00 | $82.00 | $85.00 |
| 5 | (205.0201) | LS | 1 | $500.00 | $1,000.00 | $2,500.00 | $2,000.00 | $1,200.00 |
| 6 | (205.0202) | LS | 1 | $500.00 | $1,000.00 | $2,500.00 | $2,000.00 | $1,200.00 |
| 7 | (205.0203) | LS | 1 | $500.00 | $1,000.00 | $2,500.00 | $2,000.00 | $1,200.00 |
| 8 | (205.0204) | LS | 1 | $500.00 | $1,000.00 | $2,500.00 | $2,000.00 | $1,200.00 |
| 9 | (205.0205) | LS | 1 | $500.00 | $1,000.00 | $2,500.00 | $3,000.00 | $1,200.00 |
| 10 | Field Organic Vapor Monitoring of Contaminated Soil (205.03) | HR | 50 | $150.00 | $125.00 | $175.00 | $160.00 | $175.00 |
| 11 | (205.050201) | TON | 15 | $125.00 | $100.00 | $85.00 | $250.00 | $138.00 |
| 12 | (205.050202) | TON | 16 | $125.00 | $100.00 | $85.00 | $250.00 | $138.00 |
| 13 | (205.050203) | TON | 14 | $125.00 | $100.00 | $85.00 | $250.00 | $138.00 |
| 14 | (205.050204) | TON | 16 | $125.00 | $100.00 | $85.00 | $250.00 | $138.00 |
| 15 | (205.050205) | TON | 29 | $125.00 | $100.00 | $85.00 | $250.00 | $130.00 |
| 16 | Trench and Culvert Excavation (206.0201) | CY | 9,904 | $67.00 | $1.00 | $90.00 | $75.00 | $81.00 |
| 17 | (206.03180010) | 160 | $46.00 | $1.00 | $150.00 | $65.00 | $59.75 | |
| 18 | (206.03200010) | 75 | $46.00 | $1.00 | $48.00 | $39.00 | $35.60 | |
| 19 | Geotextile Drainage (207.22) | SY | 3,283 | $1.50 | $1.70 | $2.25 | $4.50 | $0.94 |
| 20 | SWTD - Maximum Treatment Flow Rate over 2.8 cfs up to 3.8 cfs (208.5401) | EACH | 1 | $40,000 | $45,000 | $32,000 | $40,000 | $97,000 |
| 21 | SWTD - Maximum Treatment Flow Rate over 3.8 cfs up to 5.0 cfs (208.5501) | EACH | 1 | $45,000 | $55,000 | $35,000 | $43,000 | $40,000 |
| 22 | SWTD - Maximum Treatment Flow Rate over 7.0 cfs up to 10.0 cfs (208.5701) | EACH | 1 | $80,000 | $65,000 | $60,000 | $83,000 | $80,000 |
| 23 | Mulch – Temporary (209.100101) | SY | 10,600 | $0.85 | $1.00 | $1.00 | $0.95 | $0.93 |
| 24 | Seed and Mulch – Temporary (209.1003) | SY | 2,500 | $1.30 | $1.50 | $1.50 | $1.48 | $1.46 |
| 25 | (209.11010024) | 70 | $350.00 | $100.00 | $500.00 | $330.00 | $269.03 | |
| 26 | Silt Fence - Temporary (209.13) | LF | 100 | $8.00 | $5.00 | $25.00 | $25.00 | $20.86 |
| 27 | Soil Stabilizers, Class IV Type C (209.2103) | SY | 100 | $13.90 | $15.00 | $16.00 | $13.25 | $13.07 |
| 28 | (209.23010009) | 584 | $15.00 | $8.50 | $12.00 | $14.00 | $10.95 | |
| 29 | Subbase Course, Type 2 (304.12) | CY | 10,103 | $83.00 | $75.00 | $110.00 | $81.00 | $133.00 |
| 30 | (404.0179) | TON | 103 | $160.00 | $225.00 | $170.00 | $220.00 | $300.00 |
| 31 | (404.2569) | TON | 5,109 | $121.00 | $155.00 | $150.00 | $123.00 | $185.00 |
| 32 | (404.4489) | TON | 618 | $118.00 | $175.00 | $300.00 | $300.00 | $295.00 |
| 33 | (406.0962) | TON | 2,391 | $156.00 | $175.00 | $175.00 | $157.00 | $162.00 |
| 34 | (406.1969) | TON | 3,193 | $133.50 | $155.00 | $150.00 | $136.00 | $250.00 |
| 35 | Diluted Tack Coat (407.0102) | GAL | 34,257 | $3.00 | $2.10 | $4.75 | $9.30 | $1.91 |
| 36 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 106,439 | $0.50 | $0.35 | $0.25 | $1.10 | $0.23 |
| 37 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 5,546 | $9.50 | $12.00 | $12.00 | $20.00 | $18.00 |
| 38 | Shields and Shoring (552.17) | SF | 102,662 | $0.10 | $0.01 | $0.25 | $0.10 | $1.00 |
| 39 | Concrete for Structures, Performance (555.0021) | CY | 1 | $1,250.00 | $1,000.00 | $2,000.00 | $10,000 | $2,500.00 |
| 40 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 41 | (603.6001) | LF | 40 | $374.50 | $100.00 | $200.00 | $200.00 | $130.00 |
| 42 | (603.6002) | LF | 1,240 | $128.00 | $125.00 | $88.00 | $120.00 | $125.00 |
| 43 | (603.6003) | LF | 3,306 | $150.00 | $150.00 | $90.00 | $132.00 | $190.00 |
| 44 | (603.6005) | LF | 509 | $143.25 | $250.00 | $110.00 | $135.00 | $200.00 |
| 45 | (603.6009) | LF | 40 | $668.00 | $250.00 | $275.00 | $400.00 | $265.00 |
| 46 | Concrete Collars (603.77) | EACH | 31 | $1,950.00 | $1,375.00 | $500.00 | $2,500.00 | $2,000.00 |
| 47 | (604.070101) | EACH | 4 | $2,200.00 | $1,050.00 | $1,400.00 | $3,000.00 | $2,200.00 |
| 48 | (604.070102) | EACH | 1 | $2,200.00 | $1,350.00 | $1,400.00 | $4,000.00 | $2,200.00 |
| 49 | (604.310673) | LF | 230 | $1,125.00 | $1,750.00 | $1,250.00 | $1,350.00 | $1,300.00 |
| 50 | (604.4048) | LF | 41 | $1,036.00 | $1,750.00 | $1,100.00 | $1,700.00 | $1,100.00 |
| 51 | (604.4060) | LF | 6 | $2,000.00 | $1,750.00 | $1,350.00 | $2,100.00 | $1,350.00 |
| 52 | (604.50180010) | 21 | $5,000.00 | $1,350.00 | $2,750.00 | $6,700.00 | $1,700.00 | |
| 53 | Underdrain Filter, Type I (605.0901) | CY | 503 | $133.00 | $115.00 | $185.00 | $120.00 | $350.00 |
| 54 | (605.1501) | LF | 10,172 | $4.75 | $20.00 | $7.00 | $11.00 | $9.00 |
| 55 | Corrugated Beam Guide Railing End Terminal (Energy-Absorbing) (606.26) | EACH | 2 | $9,700.00 | $10,000 | $10,000 | $10,700 | $9,700.00 |
| 56 | HPBO (Mod.) Corrugated Beam Guide Railing (606.2701) | LF | 60 | $70.00 | $70.00 | $75.00 | $80.00 | $70.00 |
| 57 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 60 | $12.50 | $10.00 | $17.00 | $7.00 | $5.36 |
| 58 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 2 | $640.00 | $250.00 | $750.00 | $500.00 | $434.80 |
| 59 | (607.41010010) | 3,300 | $7.00 | $5.00 | $6.00 | $5.00 | $4.51 | |
| 60 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 26 | $70.00 | $70.00 | $70.00 | $70.00 | $70.00 |
| 61 | Concrete Sidewalks and Driveways (608.0101) | CY | 678 | $845.00 | $1,500.00 | $800.00 | $1,250.00 | $1,300.00 |
| 62 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 528 | $256.50 | $225.00 | $350.00 | $285.00 | $290.00 |
| 63 | (608.21000003) | 78 | $450.00 | $470.00 | $300.00 | $600.00 | $405.00 | |
| 64 | Stone Curb – Near Vertical Face (NVF) (609.0212) | LF | 2,177 | $89.00 | $125.00 | $125.00 | $115.00 | $88.00 |
| 65 | Resetting Existing Curb (609.15) | LF | 8,233 | $59.00 | $75.00 | $75.00 | $42.00 | $71.00 |
| 66 | (610.14000011) | 2,189 | $204.50 | $200.00 | $140.00 | $225.00 | $205.00 | |
| 67 | Topsoil - Lawns (610.1403) | CY | 635 | $99.90 | $54.00 | $200.00 | $195.00 | $210.00 |
| 68 | Sodding (610.18) | SY | 7,600 | $9.60 | $12.50 | $12.00 | $11.85 | $11.72 |
| 69 | Watering Vegetation (610.19) | 1,000 GALLONS | 371 | $22.60 | $10.00 | $40.00 | $35.00 | $36.31 |
| 70 | (611.0152) | EACH | 15 | $630.00 | $1,150.00 | $850.00 | $820.00 | $824.84 |
| 71 | (611.0281) | EACH | 5 | $583.00 | $1,150.00 | $700.00 | $700.00 | $705.52 |
| 72 | Portable Drip Irrigation System (611.17) | EACH | 20 | $97.10 | $40.00 | $38.00 | $37.00 | $36.31 |
| 73 | Removal of Portable Drip Irrigation System (611.18) | EACH | 20 | $32.10 | $40.00 | $38.00 | $37.00 | $36.31 |
| 74 | (614.060401) | EACH | 2 | $2,890.00 | $3,000.00 | $2,200.00 | $2,400.00 | $1,725.00 |
| 75 | (614.060501) | EACH | 2 | $4,590.00 | $5,000.00 | $3,300.00 | $3,200.00 | $2,300.00 |
| 76 | (614.060601) | EACH | 2 | $6,790.00 | $7,000.00 | $4,700.00 | $4,700.00 | $3,450.00 |
| 77 | Pre-Existing Stump Removal up to 24” diameter at 6 inches above grade (614.0701) | EACH | 2 | $650.00 | $600.00 | $800.00 | $1,100.00 | $745.00 |
| 78 | Pre-Existing Stump Removal over 24” to 48” diameter at 6 inches above grade (614.0702) | EACH | 4 | $700.00 | $1,200.00 | $1,750.00 | $1,400.00 | $950.00 |
| 79 | (614.08110009) | 794 | $414.00 | $300.00 | $200.00 | $316.00 | $275.94 | |
| 80 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,377,496 | $1,152,919 | $325,000 | $1,226,453 | $1,784,254 |
| 81 | Type III Construction Barricades (619.04) | EACH | 81 | $110.00 | $100.00 | $150.00 | $300.00 | $30.00 |
| 82 | (619.080102) | LF | 31,110 | $1.00 | $1.00 | $1.10 | $1.00 | $1.00 |
| 83 | Cover Existing Pavement Marking Letters or Symbols (Removable Tape) (619.0804) | EACH | 5 | $100.00 | $100.00 | $110.00 | $320.00 | $100.00 |
| 84 | (619.100102) | LF | 20,830 | $0.55 | $1.00 | $0.60 | $0.58 | $1.22 |
| 85 | (619.111112) | EACH | 8 | $1,300.00 | $15,000 | $7,500.00 | $20,000 | $27,000 |
| 86 | Maintain Traffic Signal Equipment (Requirement C) Intersection (619.1613) | MONTH | 24 | $135.00 | $100.00 | $150.00 | $79.00 | $75.00 |
| 87 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $50,000 | $75,000 | $35,000 | $50,000 | $40,000 |
| 88 | Traffic Control Supervisor (619.25) | MONTH | 1 | $20,000 | $10,000 | $25,000 | $25,000 | $40,000 |
| 89 | Cleaning Drainage Structures (621.04) | EACH | 6 | $658.00 | $550.00 | $700.00 | $1,000.00 | $658.33 |
| 90 | Survey Operations (625.01) | LS | 1 | $100,000 | $50,000 | $150,000 | $120,000 | $90,000 |
| 91 | (627.50140008) | 32,127 | $3.50 | $0.10 | $7.00 | $6.20 | $5.51 | |
| 92 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $3,500.00 | $3,000.00 | $2,500.00 | $10,000 | $5,000.00 |
| 93 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 18 | $3,500.00 | $3,000.00 | $3,500.00 | $2,800.00 | $3,825.00 |
| 94 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 95 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 96 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 35 | $66.75 | $65.00 | $70.00 | $74.00 | $66.75 |
| 97 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 750 | $40.00 | $40.00 | $42.00 | $44.00 | $40.00 |
| 98 | Type A Sign Posts (645.81) | EACH | 208 | $189.00 | $200.00 | $200.00 | $209.00 | $189.00 |
| 99 | (645.81090003) | 56 | $73.75 | $75.00 | $80.00 | $82.00 | $73.75 | |
| 100 | Reference Marker Panel (646.21) | EACH | 10 | $39.00 | $40.00 | $42.00 | $43.00 | $39.00 |
| 101 | Steel Post, 2.0 lb/ft (646.32) | EACH | 10 | $86.25 | $100.00 | $90.00 | $96.00 | $86.25 |
| 102 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 129 | $6.50 | $50.00 | $7.50 | $7.50 | $6.50 |
| 103 | (655.07030010) | 9 | $1,850.00 | $2,025.00 | $2,500.00 | $1,800.00 | $1,100.00 | |
| 104 | Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706) | EACH | 46 | $1,800.00 | $1,750.00 | $2,900.00 | $2,100.00 | $3,200.00 |
| 105 | Welded Frame & Reticuline Grate 22 (655.1122) | EACH | 6 | $1,500.00 | $1,750.00 | $2,225.00 | $1,500.00 | $2,500.00 |
| 106 | Manhole Frame & Grate (655.1201) | EACH | 1 | $1,400.00 | $1,325.00 | $2,000.00 | $850.00 | $2,000.00 |
| 107 | Manhole Frame & Cover (655.1202) | EACH | 4 | $1,225.00 | $1,325.00 | $2,000.00 | $820.00 | $1,880.00 |
| 108 | (662.60000115) | LS | 1 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 109 | (662.60000215) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 110 | (662.60000315) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 111 | (662.60000415) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 112 | (663.0104) | LF | 100 | $168.00 | $150.00 | $200.00 | $250.00 | $300.00 |
| 113 | (663.0106) | LF | 60 | $157.25 | $150.00 | $350.00 | $155.00 | $325.00 |
| 114 | (663.0108) | LF | 5,685 | $143.00 | $250.00 | $74.00 | $170.00 | $335.00 |
| 115 | (663.0603) | LF | 3,679 | $21.25 | $8.15 | $75.00 | $120.00 | $70.00 |
| 116 | (663.0604) | LF | 60 | $26.50 | $15.50 | $110.00 | $125.00 | $70.00 |
| 117 | (663.0607) | LF | 114 | $57.00 | $31.50 | $120.00 | $140.00 | $74.00 |
| 118 | (663.1008) | EACH | 12 | $3,275.00 | $3,500.00 | $2,750.00 | $3,800.00 | $4,000.00 |
| 119 | (663.1301) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,000 | $10,000 |
| 120 | (663.1302) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,000 | $10,000 |
| 121 | (663.1303) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,800 | $10,000 |
| 122 | (663.1304) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,200 | $10,000 |
| 123 | (663.1305) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,000 | $10,000 |
| 124 | (663.1306) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,200 | $10,000 |
| 125 | (663.1307) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,200 | $10,000 |
| 126 | (663.1308) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,500 | $10,000 |
| 127 | (663.1309) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,500 | $10,000 |
| 128 | (663.1310) | EACH | 1 | $11,300 | $15,000 | $10,000 | $12,800 | $10,000 |
| 129 | (663.160404) | EACH | 9 | $8,000.00 | $8,000.00 | $7,500.00 | $8,500.00 | $6,000.00 |
| 130 | (663.160606) | EACH | 7 | $8,750.00 | $12,000 | $8,000.00 | $9,200.00 | $8,000.00 |
| 131 | (663.160808) | EACH | 1 | $10,100 | $20,000 | $9,500.00 | $11,000 | $90,000 |
| 132 | (663.1708) | EACH | 1 | $17,000 | $25,000 | $10,000 | $20,000 | $20,000 |
| 133 | Iron Water Main Fittings (3 - 8 inch diameter) (663.2001) | LB | 8,536 | $7.25 | $6.00 | $5.50 | $19.00 | $12.00 |
| 134 | (663.2104) | EACH | 37 | $89.00 | $75.00 | $70.00 | $250.00 | $125.00 |
| 135 | (663.2106) | EACH | 104 | $104.00 | $95.00 | $100.00 | $300.00 | $160.00 |
| 136 | (663.2108) | EACH | 39 | $200.00 | $125.00 | $130.00 | $350.00 | $200.00 |
| 137 | (663.2304) | LF | 486 | $1.50 | $0.50 | $0.10 | $1.00 | $5.00 |
| 138 | (663.2306) | LF | 278 | $1.25 | $1.00 | $0.10 | $1.00 | $5.00 |
| 139 | (663.2308) | LF | 4,960 | $1.00 | $0.50 | $0.10 | $1.00 | $5.00 |
| 140 | (663.2503) | EACH | 91 | $2,050.00 | $4,000.00 | $450.00 | $300.00 | $2,000.00 |
| 141 | (663.2504) | EACH | 1 | $2,100.00 | $6,000.00 | $450.00 | $500.00 | $1,200.00 |
| 142 | (663.2507) | EACH | 2 | $2,500.00 | $6,000.00 | $850.00 | $1,000.00 | $1,000.00 |
| 143 | (663.2603) | EACH | 91 | $430.00 | $500.00 | $500.00 | $600.00 | $1,400.00 |
| 144 | (663.2604) | EACH | 1 | $485.00 | $500.00 | $550.00 | $1,000.00 | $1,950.00 |
| 145 | (663.2607) | EACH | 2 | $1,000.00 | $1,000.00 | $1,000.00 | $2,000.00 | $2,000.00 |
| 146 | Disconnect and Cap Existing Water Main (663.40) | EACH | 19 | $2,200.00 | $5,000.00 | $10,000 | $1,800.00 | $11,000 |
| 147 | Remove and Dispose of Existing Hydrant (663.43) | EACH | 8 | $2,750.00 | $2,000.00 | $500.00 | $1,500.00 | $1,000.00 |
| 148 | (680.05010007) | 2 | $19,500 | $20,000 | $20,000 | $23,000 | $21,995 | |
| 149 | Pole Excavation and Concrete Foundation (680.5001) | CY | 16.30 | $1,445.00 | $2,500.00 | $1,650.00 | $2,600.00 | $2,720.00 |
| 150 | (680.510501) | EACH | 2 | $1,430.00 | $4,000.00 | $1,500.00 | $1,900.00 | $1,795.00 |
| 151 | (680.51100010) | 9 | $155.00 | $350.00 | $165.00 | $240.00 | $225.00 | |
| 152 | (680.520106) | LF | 200 | $21.60 | $30.00 | $22.50 | $32.00 | $30.25 |
| 153 | (680.53010010) | 495 | $7.25 | $5.00 | $7.50 | $3.40 | $3.25 | |
| 154 | (680.53080305) | 42 | $11.00 | $5.00 | $12.00 | $9.00 | $8.20 | |
| 155 | Inductance Loop Installation (680.54) | LF | 803 | $13.65 | $15.00 | $14.00 | $15.75 | $15.00 |
| 156 | (680.670802) | EACH | 14 | $1,400.00 | $1,000.00 | $1,450.00 | $1,200.00 | $1,135.00 |
| 157 | Riser Assembly, 1-inch Diameter (680.700603) | EACH | 2 | $675.00 | $500.00 | $700.00 | $550.00 | $525.00 |
| 158 | Inductance Loop Wire (680.72) | LF | 2,296 | $0.70 | $0.25 | $0.75 | $0.53 | $0.50 |
| 159 | (680.730714) | LF | 1,675 | $4.00 | $5.00 | $4.25 | $5.70 | $5.45 |
| 160 | (680.79000105) | 1 | $3,500.00 | $2,000.00 | $3,750.00 | $3,550.00 | $3,375.00 | |
| 161 | (680.79000205) | 1 | $3,500.00 | $2,000.00 | $3,750.00 | $3,800.00 | $3,625.00 | |
| 162 | (680.80324515) | 2 | $1,500.00 | $8,000.00 | $1,600.00 | $2,400.00 | $2,280.00 | |
| 163 | Pedestrian Signal Module - 12-inch, Bi-Modal Hand/Man Symbols, LED (680.813105) | EACH | 14 | $235.00 | $400.00 | $250.00 | $210.00 | $200.00 |
| 164 | Pedestrian Signal Section - Polycarbonate, Type I, 12-inch (680.813106) | EACH | 28 | $260.00 | $200.00 | $275.00 | $290.00 | $275.00 |
| 165 | Pedestrian Signal Post Top Mount Assembly (680.8142) | EACH | 14 | $315.00 | $600.00 | $325.00 | $290.00 | $275.00 |
| 166 | Pedestrian Signal Module - 12-inch Countdown Timer, LED (680.815001) | EACH | 14 | $1,305.00 | $400.00 | $250.00 | $212.00 | $203.00 |
| 167 | (680.8151) | EACH | 14 | $235.00 | $100.00 | $1,400.00 | $1,100.00 | $1,050.00 |
| 168 | (680.82254110) | 6 | $13,925 | $7,000.00 | $15,000 | $15,000 | $14,325 | |
| 169 | (680.90920103) | 2 | $735.00 | $700.00 | $800.00 | $805.00 | $765.00 | |
| 170 | Install Electrical Disconnect/Generator Transfer Switch (680.9499) | EACH | 2 | $380.00 | $500.00 | $400.00 | $710.00 | $675.00 |
| 171 | (680.950106) | LF | 250 | $3.70 | $1.50 | $3.75 | $2.62 | $2.50 |
| 172 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $12.50 | $12.50 | $12.50 | $12.50 | $12.50 |
| 173 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 899 | $1.25 | $1.50 | $1.30 | $0.58 | $1.25 |
| 174 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 9,805 | $0.75 | $1.00 | $0.80 | $0.58 | $0.75 |
| 175 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 4,033 | $2.25 | $2.50 | $2.35 | $2.90 | $2.25 |
| 176 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 9 | $200.00 | $200.00 | $210.00 | $310.00 | $200.00 |
| 177 | (691.04000020) | 75,600 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 178 | Field Change Payment (FCP) (697.03) | DOL | 995,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 179 | Asphalt Price Adjustment (698.04) | DOL | 21,340.85 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 180 | Fuel Price Adjustment (698.05) | DOL | 8,397 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 181 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 182 | Mobilization (699.040001) | LS | 1 | $533,500 | $460,000 | $500,000 | $625,000 | $760,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.