NYSDOT contract D265505 bid tabulation

HIGHWAY RECONSTRUCTION - US 219 & Miller Rd Site Number: 01 Days Road User Cost Per Time Unit: $ 10000. Let by New York State DOT on July 10, 2025, Cattaraugus, Region 05. 5 bids received; low bid $5,116,456 by Union Concrete & Construction Corp.

Owner
New York State DOT
Letting
10 JUL 2025
Pay items
140
Data through
15 OCT 2026

Bidders

NYSDOT contract D265505: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Union Concrete & Construction Corp2. McLaughlin Construction Corp/DBA Edbauer Construction3. Cold Spring Construction Company4. D&H Excavating Inc5. Concrete Applied Technologies Corp/DBA:Catco
1Clearing and Grubbing (201.06)LS1$66,500$120,000$30,000$194,000$10,000
2Unclassified Excavation and Disposal (203.02)CY19,346$12.00$20.00$20.00$22.50$35.00
3Embankment In Place (203.03)CY13,890$10.60$14.00$14.00$25.00$35.00
4Select Granular Fill (203.07)CY219$86.00$65.00$40.00$80.00$85.00
5Trench and Culvert Excavation (206.0201)CY2,039$31.50$24.00$0.01$28.00$60.00
6Conduit Excavation and Backfill including Surface Restoration (206.03)LF239$100.00$23.00$46.00$230.00$150.00
7 (206.03050005)90$75.00$60.00$45.00$65.00$150.00
8 (206.03060005)1,895$23.00$20.00$12.00$22.00$65.00
9Geotextile Separation (207.21)SY260$4.00$3.00$2.25$6.50$6.00
10Geotextile Drainage (207.22)SY1,786$2.90$2.00$1.65$7.00$5.50
11 (208.01030022)223$91.00$135.00$140.00$100.00$170.00
12Mulch – Temporary (209.100101)SY1,273$2.00$3.00$3.05$1.75$5.00
13Seed – Temporary (209.100102)SY1,273$1.00$3.50$3.05$1.75$1.00
14Check Dam, Prefabricated – Temporary (209.1105)LF72$21.00$24.00$25.00$30.00$80.00
15Silt Fence - Temporary (209.13)LF7,460$1.55$2.00$3.50$5.25$6.00
16Drainage Structure Inlet Protection, Silt Fence – Temporary (209.1701)LF12$31.00$10.00$15.00$8.50$50.00
17Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901)SY1,036$2.75$5.10$10.00$5.50$9.00
18Soil Stabilizers, Class IV Type A (209.2101)SY3,420$1.85$2.50$2.50$2.75$3.00
19Stabilized Construction Access (209.22)SY223$20.00$10.00$25.00$1.00$50.00
20 (304.15200005)8,138$67.50$72.00$95.00$64.00$85.00
21 (404.0001)TON532$100.00$100.00$100.00$100.00$100.00
22 (404.0982)TON1,700$129.00$130.00$125.00$123.00$145.00
23 (404.1989)TON3,314$110.00$128.00$100.00$103.00$135.00
24 (404.2589)TON4,941$104.00$114.00$95.00$95.00$125.00
25 (404.4189)TON297$106.00$164.00$110.00$95.00$180.00
26 (404.4489)TON388$104.00$130.00$100.00$80.00$165.00
27Diluted Tack Coat (407.0102)GAL3,052$7.00$12.00$9.00$9.50$6.00
28 (412.10010010)35$50.00$92.00$41.00$22.00$515.00
29Asphalt Pavement Joint Adhesive (418.7603)LF19,399$0.25$0.25$0.90$0.60$1.00
30Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY4,088$5.00$10.00$5.50$8.00$15.00
31 (502.11110018)242$922.00$693.00$770.00$1,040.00$920.00
32 (502.12110018)132$1,040.00$956.00$1,050.00$1,600.00$1,450.00
33 (502.9101)1,385$13.00$44.00$42.00$60.00$56.00
34 (502.9111)802$13.00$38.00$37.00$62.00$56.00
35Sealing Transverse Joints-Preformed Elastic Joint Sealer (502.9201)LF1,385$18.50$18.00$30.00$0.01$18.00
36Sealing Longitudinal Joints -Preformed Elastic Joint Sealer (502.9301)LF802$18.10$21.00$33.00$0.01$18.00
37 (601.01110001)1,088$40.00$48.00$25.00$79.00$75.00
38 (603.14352404)1$3,000.00$3,770.00$6,000.00$4,300.00$3,300.00
39 (603.171216)EACH1$260.00$834.00$775.00$525.00$1,400.00
40 (603.541216)EACH3$650.00$1,210.00$750.00$925.00$1,400.00
41 (603.6602)LF6$875.00$628.00$500.00$1,200.00$800.00
42 (603.98100602)1,476$5.55$17.00$8.00$11.50$12.00
43 (603.9815)LF540$14.65$48.00$90.00$54.00$30.00
44 (604.301990)LF11$455.00$773.00$1,200.00$660.00$500.00
45 (604.500501)LF9$375.00$535.00$1,200.00$58.00$600.00
46Underdrain Filter, Type II (605.1001)CY722$66.00$55.00$125.00$92.00$70.00
47 (605.1701)LF8,180$1.60$8.50$11.00$10.00$6.50
48Box Beam Guide Railing (606.10)LF2,034$50.00$53.00$49.00$44.00$51.00
49Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF367$52.50$54.00$51.00$51.00$55.00
50Box Beam Guide Railing With Extra Long Posts (606.1001)LF417$52.50$55.00$51.00$48.00$55.00
51Box Beam Guide Railing with Extra Long Posts (Shop Bent or Shop Mitered) (606.100102)LF270$57.00$58.00$56.00$58.00$60.00
52Box Beam Guide Railing End Assembly Type I (606.120102)EACH2$4,100.00$4,245.00$4,100.00$4,050.00$4,400.00
53Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH4$2,000.00$2,034.00$2,000.00$2,000.00$2,100.00
54Removing and Storing Box Beam Guide Railing (606.63)LF2,473$5.00$5.50$9.00$5.50$5.50
55Removing and Storing Box Beam Guide Railing End Assembly (606.6920)EACH7$31.25$344.00$275.00$210.00$200.00
56 (607.41010010)682$9.00$1.50$6.00$11.00$4.00
57Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON175$216.00$284.00$275.00$265.00$250.00
58 (609.0401)LF1,465$58.00$65.00$80.00$90.00$65.00
59 (609.0407)LF346$66.00$89.00$118.00$117.00$90.00
60Topsoil – Reuse On-Site Materials (610.1401)CY423$12.50$50.00$50.00$85.00$55.00
61Topsoil - Roadside (610.1402)CY1,269$46.25$82.00$85.00$1.00$95.00
62Turf Establishment - Roadside (610.1601)SY3,553$0.90$0.01$1.50$3.00$2.00
63 (614.060104)EACH4$125.00$470.00$1,000.00$310.00$660.00
64 (614.060204)EACH2$625.00$600.00$1,500.00$620.00$800.00
65 (614.060404)EACH3$1,565.00$4,400.00$2,000.00$1,600.00$1,600.00
66 (617.01010024)1,125$1.00$2.00$3.00$0.01$4.00
67 (617.10000024)188$15.00$25.00$68.00$10.00$130.00
68 (617.11000024)LS1$500.00$150.00$400.00$300.00$2,500.00
69Basic Work Zone Traffic Control (619.01)LS1$190,000$211,367$444,000$118,000$262,000
70Type III Construction Barricades (619.04)EACH77$90.00$150.00$125.00$48.00$150.00
71 (619.100101)LF3,840$0.55$0.55$0.50$0.60$1.20
72 (619.100104)LF226$2.70$13.00$12.00$15.00$20.00
73 (619.100201)EACH2$165.00$170.00$160.00$175.00$170.00
74 (619.111113)EACH6$6,375.00$8,500.00$10,000$5,200.00$8,400.00
75 (619.130101)EACH1$62,000$72,000$30,000$110,000$20,000
76Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611)MONTH50$297.00$10.00$400.00$230.00$50.00
77 (619.17060005)578$2.00$2.00$0.01$5.50$7.00
78Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF140$34.00$45.00$26.00$105.00$50.00
79Temporary Positive Barrier – Category 2 (Pinning Permitted) (619.1712)LF1,570$18.00$32.00$26.00$54.00$45.00
80Pavement Patching (Tonnage) (619.2602)TON5$688.00$750.00$800.00$1,200.00$300.00
81Stone Filling (Light) (620.03)CY26$343.00$375.00$300.00$250.00$250.00
82Survey Operations (625.01)LS1$30,000$104,000$135,000$91,237$60,000
83Steel Pin and Cap Right of Way Markers (625.05)EACH6$300.00$320.00$200.00$300.00$650.00
84Permanent Survey Markers (625.06)EACH2$910.00$1,200.00$1,500.00$1,300.00$2,000.00
85 (625.09010015)LS1$950.00$0.01$9,000.00$5,500.00$100.00
86 (627.50140008)2,046$1.50$8.00$5.00$6.50$6.00
87Concrete Cylinder Curing Equipment (637.04)EACH1$1,565.00$750.00$300.00$2,000.00$4,000.00
88Engineer’s Field Office – Type 2 (637.12)MONTH18$2,500.00$2,200.00$2,500.00$2,200.00$200.00
89Office Technology and Supplies (637.34)DOL500$1.00$1.00$1.00$1.00$1.00
90Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00$1.00$1.00
91Anchor Bolts (644.11)LB682$15.00$14.00$13.00$18.00$14.00
92Drilled Shaft for Overhead Sign Structures (644.20)CY27$2,867.00$2,800.00$2,700.00$4,750.00$2,500.00
93 (644.432060)EACH1$116,500$152,000$150,000$132,500$190,000
94Performance Concrete Quality Adjustment (644.99)QUALITY UNIT1$16.25$16.25$16.25$16.25$16.25
95Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF1,200$38.50$40.00$38.00$37.00$41.00
96Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103)SF812$33.50$35.00$34.00$35.00$36.00
97Overhead Sign Panels (645.61)SF361$46.00$63.00$43.00$36.00$53.00
98Type A Sign Posts (645.81)EACH143$225.00$235.00$225.00$240.00$250.00
99High-Capacity Type A Sign Posts with Soil Plates Only (645.8106)EACH4$1,459.50$1,512.00$1,450.00$1,200.00$1,600.00
100Concrete Footing for Type A, or Breakaway Wooden Sign Posts with Steel Tube Inserts (645.8107)EACH19$1,210.00$777.00$750.00$1,250.00$1,400.00
101 (645.81090003)62$82.50$90.00$81.00$51.00$88.00
102 (645.830202)EACH6$2,000.00$2,023.00$1,950.00$3,600.00$2,100.00
103 (645.830402)EACH2$3,500.00$3,627.00$3,500.00$3,900.00$3,800.00
104 (645.830802)EACH3$11,750$12,077$11,700$8,200.00$12,500
105Reference Marker Panel (646.21)EACH6$45.00$50.00$45.00$32.00$50.00
106Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH27$22.50$25.00$22.00$21.00$24.00
107Steel Post, 2.0 lb/ft (646.32)EACH28$100.00$110.00$98.00$63.00$105.00
108Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41)EACH17$74.00$10.00$6.75$56.00$8.00
109Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51)EACH40$74.00$10.00$6.75$58.00$8.00
110 (647.83001002)17$31.00$10.00$5.50$11.00$6.00
111Parallel Bar Frame 10 PCB & Parallel Bar Grate 10 PCB (655.0901)EACH1$1,310.00$2,044.00$1,650.00$2,900.00$1,500.00
112 (670.2005)LF1,985$43.00$43.00$35.00$47.00$55.00
113Pullboxes less than 5 cubic feet, inside volume (Lighting) (670.3001)EACH10$2,825.00$2,358.00$2,500.00$2,500.00$2,700.00
114 (680.05010007)1$26,400$28,033$25,000$26,000$26,500
115 (680.05020007)1$1,980.00$3,421.00$7,000.00$5,500.00$5,200.00
116Pole Excavation and Concrete Foundation (680.5001)CY4$3,575.00$2,400.00$6,000.00$3,400.00$3,500.00
117Concrete Work Pad (5 feet x 5 feet x 4 inches) (680.5003)EACH1$4,180.00$820.00$4,000.00$4,000.00$1,500.00
118 (680.50500005)7$30.00$100.00$325.00$550.00$750.00
119 (680.510301)EACH2$2,090.00$2,713.00$3,000.00$3,500.00$2,700.00
120 (680.520508)LF239$18.00$9.00$14.00$23.00$20.00
121 (680.6712)EACH2$5,025.00$1,636.00$2,500.00$4,800.00$2,300.00
122Riser Assembly, 4-inch Diameter (680.700610)EACH12$1,100.00$913.00$2,500.00$1,000.00$1,700.00
123 (680.730514)LF126$12.00$6.00$6.00$6.00$12.00
124 (680.79000105)1$6,160.00$1,356.00$4,000.00$5,800.00$4,500.00
125 (680.79000205)1$7,700.00$1,356.00$4,000.00$5,800.00$4,500.00
126Solar Power System (680.81)EACH1$10,670$19,437$5,000.00$35,000$11,500
127Flashing Beacon Sign Assembly (680.8220)EACH2$7,725.00$4,910.00$15,000$12,000$10,500
128 (680.82250801)2$2,057.00$670.00$500.00$600.00$800.00
129Performance Concrete Quality Adjustment (680.99)QUALITY UNIT1$8.50$8.50$8.50$8.50$8.50
130White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF19,629$0.65$0.64$0.60$0.75$0.70
131Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF14,109$0.65$0.64$0.60$0.75$0.70
132White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304)EACH20$87.00$85.00$80.00$92.00$90.00
133White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404)EACH25$325.00$320.00$300.00$350.00$330.00
134 (686.05000011)1$3,080.00$3,046.00$2,900.00$3,300.00$3,200.00
135Field Change Payment (FCP) (697.03)DOL250,000$1.00$1.00$1.00$1.00$1.00
136Asphalt Price Adjustment (698.04)DOL100$1.00$1.00$1.00$1.00$1.00
137Fuel Price Adjustment (698.05)DOL100$1.00$1.00$1.00$1.00$1.00
138Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00
139 (698.93000091)LS1$60,000$60,000$60,000$60,000$60,000
140Mobilization (699.040001)LS1$196,500$228,000$237,000$220,000$275,000
NYSDOT contract D265505: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of July 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy