NYSDOT contract D265549 bid tabulation
Replacement/Repair of 7 Culverts in Ontario County. Let by New York State DOT on September 25, 2025, Ontario, Region 04. 5 bids received; low bid $8,027,963 by C P Ward Inc.
- Owner
- New York State DOT
- Letting
- 25 SEP 2025
- Pay items
- 121
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | C P Ward Inc | $8,027,963 | Low |
| 2 | Cold Spring Construction Company | $8,927,303 | +11% |
| 3 | Sealand Contractors Corp. | $9,061,000 | +13% |
| 4 | Ramsey Constructors Inc | $9,152,571 | +14% |
| 5 | Slate Hill Constructors Inc | $11,622,955 | +45% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C P Ward Inc | 2. Cold Spring Construction Company | 3. Sealand Contractors Corp. | 4. Ramsey Constructors Inc | 5. Slate Hill Constructors Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $200,000 | $125,000 | $75,000 | $125,000 | $2,500,000 |
| 2 | Removal of Substructures (202.19) | CY | 70 | $400.00 | $250.00 | $500.00 | $230.00 | $375.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 621 | $50.00 | $60.00 | $70.00 | $41.00 | $50.00 |
| 4 | Embankment In Place (203.03) | CY | 3,738 | $65.00 | $35.00 | $31.00 | $45.00 | $35.00 |
| 5 | Select Granular Fill (203.07) | CY | 954 | $98.00 | $90.00 | $170.00 | $120.00 | $110.00 |
| 6 | Select Structural Fill (203.21) | CY | 350 | $102.00 | $90.00 | $110.00 | $118.00 | $120.00 |
| 7 | (203.24010017) | 7 | $77.00 | $300.00 | $400.00 | $165.00 | $300.00 | |
| 8 | Controlled Low Strength Material (CLSM) (204.01) | CY | 29 | $600.00 | $300.00 | $500.00 | $260.00 | $970.00 |
| 9 | Structure Excavation (206.01) | CY | 7,547 | $53.00 | $45.00 | $48.00 | $55.00 | $50.00 |
| 10 | Trench and Culvert Excavation (206.0201) | CY | 483 | $80.00 | $90.00 | $300.00 | $50.00 | $50.00 |
| 11 | Geotextile Bedding (207.20) | SY | 1,182 | $11.00 | $3.50 | $6.00 | $4.00 | $8.00 |
| 12 | Prefabricated Composite Structural Drain (207.26) | SY | 740 | $25.00 | $12.00 | $27.00 | $14.00 | $18.00 |
| 13 | Seed and Mulch – Temporary (209.1003) | SY | 4,189 | $9.00 | $3.50 | $2.35 | $2.25 | $2.50 |
| 14 | Check Dam (Ditch Bottom Width 0.0 to 3′), Stone – Temporary (209.110101) | EACH | 3 | $800.00 | $1,000.00 | $2,500.00 | $600.00 | $600.00 |
| 15 | Drainage Structure Inlet Protection, Gravel Bag – Temporary (209.1702) | CY | 4 | $550.00 | $750.00 | $1,500.00 | $1,100.00 | $1,200.00 |
| 16 | Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901) | SY | 3,698 | $3.00 | $4.00 | $7.65 | $8.00 | $8.00 |
| 17 | Stabilized Construction Access (209.22) | SY | 670 | $60.00 | $80.00 | $80.00 | $55.00 | $52.00 |
| 18 | Sediment Filter Log, 12″ (209.2301) | LF | 843 | $20.00 | $10.00 | $11.50 | $12.00 | $12.00 |
| 19 | Subbase Course, Type 2 (304.12) | CY | 1,060 | $90.00 | $125.00 | $115.00 | $90.00 | $120.00 |
| 20 | (404.0001) | TON | 66 | $95.00 | $95.00 | $95.00 | $95.00 | $95.00 |
| 21 | (404.0189) | TON | 41 | $200.00 | $250.00 | $400.00 | $210.00 | $260.00 |
| 22 | (404.0983) | TON | 300 | $260.00 | $200.00 | $220.00 | $175.00 | $260.00 |
| 23 | (404.1989) | TON | 365 | $240.00 | $180.00 | $205.00 | $165.00 | $260.00 |
| 24 | (404.3789) | TON | 610 | $195.00 | $150.00 | $170.00 | $165.00 | $260.00 |
| 25 | Diluted Tack Coat (407.0102) | GAL | 473 | $27.00 | $15.00 | $40.00 | $12.00 | $11.00 |
| 26 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,480 | $5.00 | $1.50 | $2.80 | $1.00 | $2.00 |
| 27 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 971 | $50.00 | $25.00 | $60.00 | $52.00 | $45.00 |
| 28 | (553.030002) | EACH | 1 | $5,000.00 | $5,000.00 | $10,000 | $35,000 | $1.00 |
| 29 | (553.030003) | EACH | 1 | $5,000.00 | $5,000.00 | $10,000 | $35,000 | $1.00 |
| 30 | (553.030004) | EACH | 1 | $15,000 | $5,000.00 | $10,000 | $35,000 | $1.00 |
| 31 | (553.030005) | EACH | 1 | $15,000 | $5,000.00 | $10,000 | $35,000 | $1.00 |
| 32 | (553.030006) | EACH | 1 | $5,000.00 | $5,000.00 | $10,000 | $35,000 | $1.00 |
| 33 | (553.030007) | EACH | 1 | $10,000 | $5,000.00 | $10,000 | $35,000 | $1.00 |
| 34 | Footing Concrete, Performance (555.0011) | CY | 186 | $1,100.00 | $1,100.00 | $1,800.00 | $800.00 | $1,500.00 |
| 35 | Concrete for Structures, Performance (555.0021) | CY | 30 | $3,000.00 | $5,000.00 | $6,000.00 | $2,400.00 | $3,300.00 |
| 36 | (555.05010001) | 40 | $700.00 | $1,000.00 | $2,000.00 | $1,300.00 | $1,700.00 | |
| 37 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 2 | $7.50 | $7.50 | $7.50 | $7.50 | $7.50 |
| 38 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 2 | $8.04 | $8.04 | $8.04 | $8.04 | $8.04 |
| 39 | Epoxy-Coated Steel Fabric Reinforcement (556.0102) | SY | 107 | $90.00 | $50.00 | $60.00 | $26.00 | $200.00 |
| 40 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 10,993 | $4.00 | $10.00 | $4.00 | $4.00 | $4.00 |
| 41 | (562.0101) | SY | 61 | $3,000.00 | $4,500.00 | $3,000.00 | $3,100.00 | $2,800.00 |
| 42 | Performance Concrete Quality Adjustment (562.99) | QUALITY UNIT | 1 | $40.00 | $40.00 | $40.00 | $40.00 | $40.00 |
| 43 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 74 | $350.00 | $375.00 | $395.00 | $400.00 | $345.00 |
| 44 | Transition Bridge Railing (568.70) | LF | 271 | $200.00 | $225.00 | $215.00 | $250.00 | $210.00 |
| 45 | Removal of Structural Concrete (580.01) | CY | 6 | $13,000 | $6,000.00 | $5,500.00 | $2,500.00 | $10,000 |
| 46 | Removal and Replacement of Structural Concrete (582.0051) | CY | 1 | $30,000 | $25,000 | $33,000 | $7,000.00 | $21,500 |
| 47 | Removal of Structural Concrete- Replacement with Vertical and Overhead Patching Material (582.0061) | SF | 71 | $600.00 | $1,400.00 | $900.00 | $140.00 | $550.00 |
| 48 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 1,003 | $40.00 | $60.00 | $105.00 | $36.00 | $75.00 |
| 49 | (595.50000018) | 6,470 | $6.00 | $7.00 | $4.00 | $4.00 | $5.00 | |
| 50 | (602.90100707) | 131 | $6,200.00 | $6,500.00 | $6,600.00 | $6,000.00 | $5,600.00 | |
| 51 | (602.90200307) | 196 | $6,200.00 | $6,750.00 | $5,850.00 | $6,000.00 | $4,800.00 | |
| 52 | (602.90200407) | 141 | $4,200.00 | $4,250.00 | $4,200.00 | $4,300.00 | $3,600.00 | |
| 53 | (603.171316) | EACH | 2 | $1,000.00 | $1,500.00 | $1,000.00 | $190.00 | $600.00 |
| 54 | (603.63140515) | 38 | $4,000.00 | $5,000.00 | $4,000.00 | $5,000.00 | $4,500.00 | |
| 55 | (603.64120515) | 40 | $4,000.00 | $5,000.00 | $4,030.00 | $5,000.00 | $4,500.00 | |
| 56 | (603.64120715) | 112 | $2,400.00 | $3,500.00 | $2,800.00 | $4,000.00 | $2,800.00 | |
| 57 | (603.67000001) | 178 | $1,200.00 | $2,750.00 | $2,750.00 | $2,200.00 | $2,500.00 | |
| 58 | (603.9818) | LF | 31 | $400.00 | $165.00 | $200.00 | $95.00 | $60.00 |
| 59 | (603.9824) | LF | 28 | $625.00 | $165.00 | $250.00 | $300.00 | $80.00 |
| 60 | (603.99050002) | 4 | $1,200.00 | $2,500.00 | $1,000.00 | $600.00 | $2,600.00 | |
| 61 | (604.070401) | EACH | 5 | $1,000.00 | $7,500.00 | $6,000.00 | $2,200.00 | $5,800.00 |
| 62 | Box Beam Guide Railing (606.10) | LF | 2,530 | $50.00 | $55.00 | $52.00 | $62.00 | $50.00 |
| 63 | Box Beam Guide Railing (Shop Mitered) (606.100003) | LF | 47 | $145.00 | $150.00 | $155.00 | $180.00 | $150.00 |
| 64 | Box Beam End Piece (606.120101) | EACH | 4 | $650.00 | $1,000.00 | $670.00 | $785.00 | $650.00 |
| 65 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 9 | $4,200.00 | $5,000.00 | $4,400.00 | $5,000.00 | $4,200.00 |
| 66 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 10 | $2,100.00 | $2,500.00 | $2,150.00 | $2,400.00 | $2,100.00 |
| 67 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 2,157 | $8.00 | $20.00 | $5.00 | $3.00 | $12.00 |
| 68 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 201 | $8.00 | $25.00 | $6.00 | $7.00 | $12.00 |
| 69 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 22 | $500.00 | $1,250.00 | $500.00 | $600.00 | $600.00 |
| 70 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 3 | $500.00 | $1,250.00 | $500.00 | $70.00 | $850.00 |
| 71 | Guide Rail Transition Weak-Post Corrugated Beam to Box Beam Guide Rail (One or Two Way Operation) (606.8101) | EACH | 1 | $6,800.00 | $7,500.00 | $7,400.00 | $8,000.00 | $7,000.00 |
| 72 | (607.41010010) | 160 | $15.00 | $10.00 | $30.00 | $2.00 | $16.00 | |
| 73 | (607.96000008) | 33 | $20.00 | $20.00 | $20.00 | $25.00 | $35.00 | |
| 74 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $95.00 | $95.00 | $95.00 | $95.00 | $95.00 |
| 75 | Concrete Sidewalks and Driveways (608.0101) | CY | 8 | $2,600.00 | $2,500.00 | $2,700.00 | $2,400.00 | $3,800.00 |
| 76 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 72 | $300.00 | $500.00 | $400.00 | $350.00 | $260.00 |
| 77 | Stone Curb – Near Vertical Face (NVF) (609.0212) | LF | 92 | $150.00 | $150.00 | $250.00 | $170.00 | $130.00 |
| 78 | Turf Establishment – Performance (610.1605) | SY | 4,218 | $22.00 | $25.00 | $20.00 | $24.00 | $36.00 |
| 79 | (613.04000001) | 171 | $100.00 | $65.00 | $300.00 | $200.00 | $90.00 | |
| 80 | (614.060101) | EACH | 21 | $230.00 | $1,000.00 | $300.00 | $500.00 | $800.00 |
| 81 | (614.060201) | EACH | 22 | $370.00 | $1,000.00 | $425.00 | $600.00 | $900.00 |
| 82 | (614.060301) | EACH | 20 | $725.00 | $1,500.00 | $850.00 | $1,000.00 | $1,200.00 |
| 83 | (614.060401) | EACH | 21 | $1,400.00 | $1,750.00 | $1,500.00 | $1,600.00 | $1,400.00 |
| 84 | (615.01010108) | 43 | $30.00 | $60.00 | $400.00 | $215.00 | $240.00 | |
| 85 | (617.10000024) | 760 | $15.00 | $15.00 | $100.00 | $37.00 | $90.00 | |
| 86 | (617.11000024) | LS | 1 | $3,000.00 | $1,500.00 | $3,000.00 | $24,000 | $12,000 |
| 87 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $250,000 | $400,000 | $443,060 | $920,000 | $1,300,000 |
| 88 | Type III Construction Barricades (619.04) | EACH | 96 | $100.00 | $125.00 | $350.00 | $250.00 | $60.00 |
| 89 | (619.110611) | WEEK | 22 | $900.00 | $1,200.00 | $1,500.00 | $1,800.00 | $7,000.00 |
| 90 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 270 | $100.00 | $80.00 | $80.00 | $90.00 | $115.00 |
| 91 | Mailboxes (619.27) | EACH | 1 | $600.00 | $500.00 | $500.00 | $400.00 | $110.00 |
| 92 | Stone Filling (Medium) (620.04) | CY | 280 | $190.00 | $250.00 | $270.00 | $115.00 | $130.00 |
| 93 | Stone Filling (Heavy) (620.05) | CY | 351 | $200.00 | $300.00 | $370.00 | $300.00 | $160.00 |
| 94 | Bedding Material, Type 1 (620.0801) | CY | 71 | $125.00 | $125.00 | $240.00 | $145.00 | $160.00 |
| 95 | (620.14020009) | 146 | $220.00 | $350.00 | $480.00 | $360.00 | $275.00 | |
| 96 | Crushed Stone (In-Place Measure) (623.12) | CY | 159 | $160.00 | $150.00 | $280.00 | $200.00 | $150.00 |
| 97 | Survey Operations (625.01) | LS | 1 | $90,000 | $75,000 | $62,000 | $250,000 | $60,000 |
| 98 | Concrete Right of Way Markers Type H (High) (625.03) | EACH | 24 | $1,300.00 | $500.00 | $1,150.00 | $1,300.00 | $1,500.00 |
| 99 | Concrete Right of Way Markers Type L (Low) (625.04) | EACH | 4 | $1,700.00 | $500.00 | $1,450.00 | $1,800.00 | $1,400.00 |
| 100 | Steel Pin and Cap Right of Way Markers (625.05) | EACH | 6 | $1,500.00 | $250.00 | $720.00 | $500.00 | $1,000.00 |
| 101 | (625.09010015) | LS | 1 | $28,000 | $2,500.00 | $10,400 | $6,000.00 | $2,000.00 |
| 102 | (627.50140008) | 853 | $9.00 | $15.00 | $12.00 | $12.00 | $7.00 | |
| 103 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $5,000.00 | $1,500.00 | $10,000 | $4,000.00 | $800.00 |
| 104 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 36 | $2,200.00 | $3,100.00 | $2,000.00 | $3,200.00 | $3,400.00 |
| 105 | White Paint Reflectorized Pavement Stripes – 20 mils (640.20) | LF | 1,690 | $4.00 | $3.25 | $0.30 | $3.00 | $4.00 |
| 106 | Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21) | LF | 1,580 | $4.00 | $3.25 | $0.30 | $3.00 | $4.00 |
| 107 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 18 | $70.00 | $70.00 | $75.00 | $75.00 | $70.00 |
| 108 | Type A Sign Posts (645.81) | EACH | 4 | $400.00 | $450.00 | $430.00 | $500.00 | $400.00 |
| 109 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 39 | $19.00 | $20.00 | $20.00 | $24.00 | $19.00 |
| 110 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 18 | $23.00 | $25.00 | $26.00 | $30.00 | $25.00 |
| 111 | Steel Post, 2.0 lb/ft (646.32) | EACH | 45 | $88.00 | $100.00 | $96.00 | $115.00 | $90.00 |
| 112 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 3 | $300.00 | $300.00 | $300.00 | $350.00 | $280.00 |
| 113 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 2 | $25.00 | $30.00 | $30.00 | $33.00 | $11.00 |
| 114 | (647.83001002) | 13 | $160.00 | $80.00 | $55.00 | $30.00 | $11.00 | |
| 115 | Centerline Audible Roadway Delineators (CARDs) (649.11) | LF | 520 | $38.00 | $30.00 | $51.00 | $12.00 | $50.00 |
| 116 | Welded Frame & Rectangular Grate 11 (655.1011) | EACH | 1 | $1,200.00 | $2,500.00 | $2,000.00 | $2,500.00 | $1,500.00 |
| 117 | Field Change Payment (FCP) (697.03) | DOL | 370,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 118 | Asphalt Price Adjustment (698.04) | DOL | 2,550 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 119 | Fuel Price Adjustment (698.05) | DOL | 4,373 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 120 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 121 | Mobilization (699.040001) | LS | 1 | $300,000 | $343,001 | $348,000 | $315,000 | $400,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.