NCDOT contract C204840 bid tabulation
GRADING, DRAINAGE, PAVING, AND SIGNALS. INTERSECTION AT US-321 AND SR-1108 (MISSION RD). Let by North Carolina DOT on October 21, 2025, Caldwell. 4 bids received; low bid $13,348,559 by Hei Civil Carolinas LLC.
- Owner
- North Carolina DOT
- Letting
- 21 OCT 2025
- Pay items
- 192
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hei Civil Carolinas LLC | $13,348,559 | Low |
| 2 | Kemp Sigmon Construction Co Inc | $13,629,385 | +2.0% |
| 3 | Branch Civil Inc | $14,385,000 | +8.0% |
| 4 | Chatham Civil Contracting LLC | $14,909,593 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hei Civil Carolinas LLC | 2. Kemp Sigmon Construction Co Inc | 3. Branch Civil Inc | 4. Chatham Civil Contracting LLC |
|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $625,000 | $650,000 | $700,000 | $745,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $195,000 | $225,000 | $170,000 | $195,500 |
| 0003 | Grading (0043000000-N) | LS | 1 | $1,725,000 | $3,900,000 | $1,626,904 | $1,710,098 |
| 0004 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $6,200.00 | $100.00 | $18,300 | $1.00 |
| 0005 | Undercut excavation (0057000000-E) | CY | 4,000 | $37.00 | $10.00 | $47.50 | $36.25 |
| 0006 | Select granular material (0195000000-E) | CY | 6,400 | $86.00 | $10.00 | $45.00 | $62.00 |
| 0007 | Geotextile for soil stabilization (0196000000-E) | SY | 5,005 | $3.30 | $2.00 | $3.50 | $3.10 |
| 0008 | Generic grading item (TON) - hauling and disposal of petroleum contaminated soil (0255000000-E) | TON | 50 | $130.00 | $300.00 | $114.00 | $174.51 |
| 0009 | Foundation conditioning material, minor structures (0318000000-E) | TON | 370 | $73.00 | $40.00 | $104.00 | $80.00 |
| 0010 | FND condit geotextile (4A) (0321000000-E) | SY | 1,160 | $2.00 | $2.00 | $6.00 | $3.10 |
| 0011 | 15" drainage pipe (0335200000-E) | LF | 340 | $68.00 | $85.00 | $107.00 | $80.00 |
| 0012 | 30" drainage pipe (0335500000-E) | LF | 48 | $136.00 | $135.00 | $177.00 | $157.00 |
| 0013 | 15" RC pipe culverts, class III (0366000000-E) | LF | 1,508 | $83.00 | $95.00 | $122.00 | $115.00 |
| 0014 | 18" RC pipe culverts, class III (0372000000-E) | LF | 348 | $95.00 | $105.00 | $157.00 | $127.00 |
| 0015 | 24" RC pipe culverts, class III (0378000000-E) | LF | 852 | $124.00 | $130.00 | $208.00 | $167.00 |
| 0016 | 30" RC pipe culverts, class III (0384000000-E) | LF | 344 | $207.00 | $160.00 | $242.00 | $197.00 |
| 0017 | 24" CS pipe culverts, 0.064" thick (0594000000-E) | LF | 36 | $330.00 | $110.00 | $263.00 | $126.00 |
| 0018 | Pipe removal (0995000000-E) | LF | 974 | $57.00 | $10.00 | $50.00 | $29.75 |
| 0019 | Shallow undercut (1099500000-E) | CY | 560 | $41.00 | $15.00 | $29.25 | $30.50 |
| 0020 | Class IV subgrade stabilization (1099700000-E) | TON | 1,120 | $70.00 | $25.00 | $77.00 | $47.00 |
| 0021 | Geotextile for subgrade stabilization (1112000000-E) | SY | 1,680 | $4.00 | $5.00 | $5.75 | $4.00 |
| 0022 | Aggregate base course (1121000000-E) | TON | 145 | $76.50 | $60.00 | $88.00 | $53.00 |
| 0023 | Incidental stone base (1220000000-E) | TON | 300 | $100.00 | $75.00 | $62.00 | $52.00 |
| 0024 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 22,600 | $5.80 | $5.00 | $2.50 | $3.15 |
| 0025 | Incidental milling (1330000000-E) | SY | 190 | $88.00 | $75.00 | $45.50 | $35.50 |
| 0026 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 9,100 | $125.00 | $107.00 | $120.00 | $136.00 |
| 0027 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 8,020 | $125.00 | $107.00 | $120.00 | $136.00 |
| 0028 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 10,420 | $125.00 | $107.00 | $120.00 | $136.00 |
| 0029 | Asphalt binder for plant mix (1575000000-E) | TON | 1,410 | $960.00 | $825.00 | $875.00 | $1,050.00 |
| 0030 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 100 | $500.00 | $300.00 | $286.00 | $318.00 |
| 0031 | Subdrain excavation (2022000000-E) | CY | 44.80 | $50.00 | $15.00 | $19.50 | $50.00 |
| 0032 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $7.50 | $3.00 | $6.75 | $1.60 |
| 0033 | Subdrain coarse aggregate (2036000000-E) | CY | 33.60 | $141.00 | $100.00 | $57.00 | $91.00 |
| 0034 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $41.50 | $5.00 | $111.00 | $5.65 |
| 0035 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $2,425.00 | $500.00 | $2,160.00 | $280.00 |
| 0036 | 6" outlet pipe (2077000000-E) | LF | 6 | $83.00 | $50.00 | $265.00 | $24.50 |
| 0037 | Pipe collars (2253000000-E) | CY | 0.45 | $2,100.00 | $3,500.00 | $14,500 | $4,789.00 |
| 0038 | Pipe plugs (2264000000-E) | CY | 0.34 | $2,460.00 | $2,000.00 | $9,800.00 | $6,957.00 |
| 0039 | Flowable fill (2275000000-E) | CY | 10 | $865.00 | $350.00 | $1,110.00 | $400.00 |
| 0040 | Masonry drainage structures (2286000000-N) | EACH | 35 | $3,350.00 | $3,000.00 | $6,510.00 | $3,701.00 |
| 0041 | Masonry drainage structures (2308000000-E) | LF | 86 | $370.00 | $350.00 | $1,290.00 | $245.00 |
| 0042 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 23 | $1,500.00 | $850.00 | $1,680.00 | $1,150.00 |
| 0043 | Frame-GRT-HD 840.03 ** - (G) (2374000000-N) | EACH | 7 | $1,760.00 | $1,100.00 | $2,010.00 | $1,382.00 |
| 0044 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 5 | $1,275.00 | $600.00 | $1,530.00 | $975.00 |
| 0045 | Concrete transitional section for drop inlet (2451000000-N) | EACH | 11 | $2,108.00 | $2,500.00 | $2,090.00 | $3,371.00 |
| 0046 | **"X**" concrete curb - (8" X 12") (2535000000-E) | LF | 72 | $105.00 | $45.00 | $92.00 | $46.50 |
| 0047 | 1'-6" concrete curb & gutter (2542000000-E) | LF | 2,830 | $30.00 | $32.00 | $30.50 | $33.00 |
| 0048 | 2'-6" concrete curb & gutter (2549000000-E) | LF | 370 | $56.00 | $40.00 | $40.00 | $55.00 |
| 0049 | Concrete expressway gutter (2577000000-E) | LF | 230 | $84.00 | $45.00 | $78.00 | $89.50 |
| 0050 | 5" monolithic concrete islands (keyed in) (2655000000-E) | SY | 930 | $110.00 | $125.00 | $105.00 | $140.00 |
| 0051 | Adjustment of drop inlets (2815000000-N) | EACH | 1 | $1,880.00 | $2,000.00 | $2,780.00 | $4,591.00 |
| 0052 | Adjustment of manholes (2830000000-N) | EACH | 5 | $1,880.00 | $1,500.00 | $1,190.00 | $2,674.00 |
| 0053 | Steel beam guardrail (3030000000-E) | LF | 575 | $30.50 | $24.50 | $27.75 | $26.25 |
| 0054 | Additional guardrail posts (3150000000-N) | EACH | 5 | $15.00 | $11.00 | $12.50 | $12.00 |
| 0055 | Guardrail end units, type cat-1 (3210000000-N) | EACH | 1 | $1,054.00 | $850.00 | $959.00 | $910.00 |
| 0056 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 1 | $3,968.00 | $3,200.00 | $3,610.00 | $3,425.00 |
| 0057 | Remove existing guardrail (3360000000-E) | LF | 803 | $1.25 | $1.00 | $1.25 | $1.00 |
| 0058 | Barbed wire fence reset (3569000000-E) | LF | 350 | $15.50 | $12.50 | $14.00 | $13.50 |
| 0059 | Rip rap, class B (3649000000-E) | TON | 40 | $153.50 | $150.00 | $200.00 | $91.01 |
| 0060 | Geotextile for drainage (3656000000-E) | SY | 1,410 | $4.30 | $5.00 | $2.75 | $2.50 |
| 0061 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 815 | $11.00 | $8.00 | $8.50 | $8.10 |
| 0062 | Sign erection, type D (4096000000-N) | EACH | 4 | $310.00 | $250.00 | $288.00 | $305.50 |
| 0063 | Sign erection, type E (4102000000-N) | EACH | 26 | $186.00 | $95.00 | $248.00 | $241.00 |
| 0064 | Sign erection, type F (4108000000-N) | EACH | 6 | $124.00 | $150.00 | $259.00 | $343.00 |
| 0065 | Sign erect, reloc ** GRD MTD - (D) (4116100000-N) | EACH | 5 | $310.00 | $250.00 | $213.00 | $268.00 |
| 0066 | Disposal of sign system, U-channel (4155000000-N) | EACH | 31 | $31.00 | $20.00 | $5.75 | $16.00 |
| 0067 | Work zone signs (stationary) (4400000000-E) | SF | 644 | $9.30 | $7.05 | $7.75 | $8.00 |
| 0068 | Work zone signs (barricade mounted) (4410000000-E) | SF | 149 | $9.00 | $8.85 | $8.25 | $9.50 |
| 0069 | Flashing arrow board (4415000000-N) | EACH | 2 | $2,449.00 | $3,000.00 | $2,390.00 | $3,562.00 |
| 0070 | Portable changeable message sign (4420000000-N) | EACH | 2 | $4,960.00 | $9,600.00 | $10,100 | $12,212 |
| 0071 | Drums (4430000000-N) | EACH | 450 | $52.00 | $125.00 | $63.00 | $56.00 |
| 0072 | Barricades (type III) (4445000000-E) | LF | 144 | $33.50 | $25.00 | $21.00 | $32.00 |
| 0073 | Flagger (4455000000-N) | DAY | 90 | $470.00 | $350.00 | $749.00 | $829.00 |
| 0074 | TMA (4480000000-N) | EACH | 2 | $20,088 | $54,000 | $28,500 | $78,395 |
| 0075 | Skinny drum (4516000000-N) | EACH | 213 | $42.00 | $100.00 | $36.50 | $43.25 |
| 0076 | Temporary raised pavement markers (4650000000-N) | EACH | 146 | $10.00 | $8.00 | $11.00 | $11.00 |
| 0077 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 44,928 | $0.60 | $0.48 | $0.65 | $1.00 |
| 0078 | Thermoplastic pavement marking lines (8", 90 mils) (4695000000-E) | LF | 5,540 | $2.75 | $2.20 | $3.00 | $4.30 |
| 0079 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 390 | $12.00 | $9.50 | $13.25 | $10.70 |
| 0080 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 39 | $93.00 | $75.00 | $104.00 | $160.50 |
| 0081 | Paint pavement marking lines (4") (4810000000-E) | LF | 43,012 | $0.20 | $0.16 | $0.20 | $0.15 |
| 0082 | Paint pavement marking lines (24") (4835000000-E) | LF | 295 | $2.50 | $2.00 | $2.75 | $1.00 |
| 0083 | Paint pavement marking symbol (4845000000-N) | EACH | 20 | $25.00 | $20.00 | $27.75 | $64.25 |
| 0084 | Generic pavement marking item (LF) - yield line thermoplastic pavement marking, (24", 90 mils) (4890000000-E) | LF | 20 | $12.00 | $9.50 | $13.25 | $53.50 |
| 0085 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 146 | $90.50 | $73.00 | $101.00 | $64.25 |
| 0086 | Portable lighting (5255000000-N) | LS | 1 | $123,000 | $500,000 | $64,300 | $497,400 |
| 0087 | 4" water line (5325400000-E) | LF | 219 | $45.00 | $80.00 | $81.00 | $153.00 |
| 0088 | 6" water line (5325600000-E) | LF | 24 | $58.00 | $275.00 | $116.00 | $133.00 |
| 0089 | 8" water line (5325800000-E) | LF | 1,465 | $73.75 | $85.00 | $140.00 | $118.00 |
| 0090 | 12" water line (5326200000-E) | LF | 2,970 | $130.50 | $105.00 | $169.00 | $140.00 |
| 0091 | 16" water line (5326600000-E) | LF | 140 | $142.00 | $95.00 | $209.00 | $153.00 |
| 0092 | DI H2O pipe fittings (5329000000-E) | LB | 6,965 | $12.65 | $15.00 | $17.50 | $17.00 |
| 0093 | 4" valve (5538000000-E) | EACH | 2 | $2,360.00 | $1,750.00 | $3,490.00 | $2,446.00 |
| 0094 | 6" valve (5540000000-E) | EACH | 3 | $2,650.00 | $2,250.00 | $3,840.00 | $2,834.00 |
| 0095 | 8" valve (5546000000-E) | EACH | 2 | $3,860.00 | $3,000.00 | $5,350.00 | $4,363.00 |
| 0096 | 12" valve (5558000000-E) | EACH | 8 | $7,090.00 | $6,000.00 | $10,600 | $7,301.00 |
| 0097 | 4" tapping sleeve & valve (5571400000-E) | EACH | 1 | $7,890.00 | $6,000.00 | $11,100 | $7,382.00 |
| 0098 | 6" tapping sleeve & valve (5571600000-E) | EACH | 1 | $9,533.00 | $6,500.00 | $13,400 | $9,200.00 |
| 0099 | 8" tapping sleeve & valve (5571800000-E) | EACH | 3 | $15,554 | $8,000.00 | $16,300 | $11,300 |
| 0100 | 12" tapping sleeve & valve (5572200000-E) | EACH | 3 | $21,830 | $15,000 | $23,300 | $19,741 |
| 0101 | Relocate water meter (5648000000-N) | EACH | 9 | $1,693.00 | $2,000.00 | $3,840.00 | $2,370.00 |
| 0102 | Reconnect water meter (5649000000-N) | EACH | 1 | $675.00 | $1,500.00 | $1,750.00 | $1,299.00 |
| 0103 | Fire hydrant (5666000000-N) | EACH | 2 | $6,500.00 | $5,500.00 | $11,400 | $6,983.00 |
| 0104 | Relocate fire hydrant (5672000000-N) | EACH | 1 | $3,400.00 | $2,000.00 | $3,490.00 | $2,445.00 |
| 0105 | Fire hydrant leg (5673000000-E) | LF | 32 | $76.00 | $125.00 | $221.00 | $100.00 |
| 0106 | 4" line stop (5678200000-E) | EACH | 1 | $10,400 | $6,500.00 | $10,500 | $11,500 |
| 0107 | 6" line stop (5678400000-E) | EACH | 1 | $11,635 | $7,500.00 | $12,800 | $12,800 |
| 0108 | 8" line stop (5678600000-E) | EACH | 3 | $13,070 | $8,000.00 | $14,000 | $14,300 |
| 0109 | 12" line stop (5679000000-E) | EACH | 3 | $15,000 | $10,000 | $17,500 | $16,200 |
| 0110 | Water service line (<2") (5686500000-E) | LF | 33 | $121.00 | $75.00 | $140.00 | $63.00 |
| 0111 | 8" sanitary gravity sewer (5691300000-E) | LF | 753 | $73.00 | $115.00 | $233.00 | $152.00 |
| 0112 | 4' dia utility manhole (5775000000-E) | EACH | 5 | $3,365.00 | $7,500.00 | $14,000 | $5,747.00 |
| 0113 | Utility manhole wall 4' dia (5781000000-E) | LF | 1.70 | $425.00 | $400.00 | $1,690.00 | $2,850.00 |
| 0114 | Abandon **" utility pipe - (4") (5798000000-E) | LF | 133 | $28.00 | $15.00 | $46.50 | $16.25 |
| 0115 | Abandon 6" utility pipe (5800000000-E) | LF | 65 | $55.00 | $18.00 | $46.50 | $50.00 |
| 0116 | Abandon 8" utility pipe (5801000000-E) | LF | 182 | $50.00 | $20.00 | $46.50 | $30.00 |
| 0117 | Abandon 12" utility pipe (5804000000-E) | LF | 2,831 | $23.00 | $25.00 | $29.00 | $12.00 |
| 0118 | Remove fire hydrant (5815500000-N) | EACH | 2 | $1,350.00 | $500.00 | $2,910.00 | $1,900.00 |
| 0119 | Remove utility manhole (5828000000-N) | EACH | 4 | $4,365.00 | $5,000.00 | $1,560.00 | $2,460.00 |
| 0120 | 12" encasement pipe (5835600000-E) | LF | 116 | $160.00 | $125.00 | $279.00 | $181.00 |
| 0121 | 16" encasement pipe (5835700000-E) | LF | 211 | $160.00 | $135.00 | $291.00 | $230.00 |
| 0122 | 24" encasement pipe (5836000000-E) | LF | 130 | $300.00 | $175.00 | $407.00 | $372.00 |
| 0123 | Bore & jack **" - (12") (5872500000-E) | LF | 116 | $533.00 | $310.00 | $1,280.00 | $1,225.00 |
| 0124 | Bore & jack **" - (16") (5872500000-E) | LF | 211 | $840.00 | $352.00 | $2,090.00 | $1,300.00 |
| 0125 | Bore & jack **" - (24") (5872500000-E) | LF | 130 | $910.00 | $475.00 | $2,910.00 | $1,628.00 |
| 0126 | Direct drill **" - (16") (5872600000-E) | LF | 140 | $322.50 | $350.00 | $1,450.00 | $3,254.00 |
| 0127 | Temporary silt fence (6000000000-E) | LF | 6,160 | $3.50 | $2.50 | $3.25 | $3.05 |
| 0128 | Stone for erosion control, class A (6006000000-E) | TON | 1,220 | $96.00 | $40.00 | $120.00 | $69.00 |
| 0129 | Stone for erosion control, class B (6009000000-E) | TON | 730 | $99.00 | $40.00 | $133.00 | $74.00 |
| 0130 | Sediment control stone (6012000000-E) | TON | 1,060 | $85.00 | $40.00 | $129.00 | $56.25 |
| 0131 | Temporary mulching (6015000000-E) | ACRE | 51.50 | $1,612.00 | $1,200.00 | $2,040.00 | $1,654.00 |
| 0132 | Seed for temporary seeding (6018000000-E) | LB | 2,500 | $1.25 | $5.00 | $2.25 | $1.30 |
| 0133 | Fertilizer for temporary seeding (6021000000-E) | TON | 13.50 | $124.00 | $1,200.00 | $1,020.00 | $127.00 |
| 0134 | Temporary slope drains (6024000000-E) | LF | 200 | $39.50 | $40.00 | $70.00 | $21.00 |
| 0135 | Safety fence (6029000000-E) | LF | 120 | $4.00 | $1.85 | $3.25 | $4.15 |
| 0136 | Silt excavation (6030000000-E) | CY | 5,070 | $52.50 | $1.00 | $14.75 | $16.00 |
| 0137 | Matting for erosion control (6036000000-E) | SY | 20,700 | $2.20 | $1.75 | $1.75 | $2.25 |
| 0138 | Coir fiber mat (6037000000-E) | SY | 75 | $24.80 | $6.00 | $6.75 | $26.00 |
| 0139 | 1/4" hardware cloth (6042000000-E) | LF | 1,260 | $4.35 | $10.00 | $5.75 | $4.50 |
| 0140 | Low permeability geotextile (6043000000-E) | SY | 200 | $9.25 | $10.00 | $6.00 | $2.25 |
| 0141 | Special stilling basins (6070000000-N) | EACH | 1 | $3,420.00 | $500.00 | $1,320.00 | $500.00 |
| 0142 | Flocculant (6071002000-E) | LB | 265 | $1.25 | $10.00 | $5.75 | $18.00 |
| 0143 | Coir fiber wattle (6071012000-E) | LF | 2,020 | $10.00 | $10.00 | $10.50 | $10.50 |
| 0144 | Coir fiber baffle (6071030000-E) | LF | 660 | $10.00 | $6.50 | $9.25 | $10.50 |
| 0145 | **" skimmer - (1-1/2") (6071050000-E) | EACH | 6 | $2,357.00 | $2,000.00 | $3,900.00 | $9,500.00 |
| 0146 | Seeding and mulching (6084000000-E) | ACRE | 36.30 | $3,340.00 | $2,000.00 | $2,950.00 | $3,750.00 |
| 0147 | Mowing (6087000000-E) | ACRE | 33 | $248.00 | $250.00 | $340.00 | $250.00 |
| 0148 | Seed for repair seeding (6090000000-E) | LB | 550 | $6.20 | $6.00 | $5.00 | $6.50 |
| 0149 | Fertilizer for repair seeding (6093000000-E) | TON | 1.50 | $992.00 | $1,750.00 | $1,250.00 | $1,018.00 |
| 0150 | Seed for supplemental seeding (6096000000-E) | LB | 825 | $1.25 | $6.00 | $5.00 | $1.30 |
| 0151 | Fertilizer topdressing (6108000000-E) | TON | 24.50 | $992.00 | $1,300.00 | $1,020.00 | $1,018.00 |
| 0152 | Specialized hand mowing (6114500000-N) | MHR | 10 | $310.00 | $85.00 | $198.00 | $97.00 |
| 0153 | Manual litter removal (6114800000-N) | MHR | 19 | $67.00 | $65.00 | $202.00 | $41.00 |
| 0154 | Litter disposal (6114900000-E) | TON | 1 | $100.00 | $450.00 | $231.00 | $54.00 |
| 0155 | Response for erosion control (6117000000-N) | EACH | 100 | $1.25 | $200.00 | $289.00 | $1.00 |
| 0156 | Concrete washout structure (6117500000-N) | EACH | 2 | $2,485.00 | $1,500.00 | $1,200.00 | $950.00 |
| 0157 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 150 | $155.00 | $300.00 | $278.00 | $34.00 |
| 0158 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 50 | $155.00 | $200.00 | $278.00 | $75.00 |
| 0159 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 12 | $1,230.00 | $1,000.00 | $1,200.00 | $890.00 |
| 0160 | Signal cable (7060000000-E) | LF | 3,960 | $5.00 | $4.00 | $4.50 | $5.10 |
| 0161 | Vehicle signal head (12", 3 section) (7120000000-E) | EACH | 27 | $1,700.00 | $1,365.00 | $1,530.00 | $1,736.25 |
| 0162 | Vehicle signal head (12", 4 section) (7132000000-E) | EACH | 6 | $1,980.00 | $1,594.00 | $1,790.00 | $2,027.59 |
| 0163 | Vehicle signal head (12", 5 section) (7144000000-E) | EACH | 1 | $2,680.00 | $2,159.00 | $2,420.00 | $2,746.00 |
| 0164 | Messenger cable (3/8") (7264000000-E) | LF | 390 | $13.65 | $11.00 | $12.25 | $14.00 |
| 0165 | Tracer wire (7279000000-E) | LF | 2,027 | $1.25 | $1.00 | $1.00 | $1.30 |
| 0166 | Paved trench (***********) - (1, 2") (7288000000-E) | LF | 100 | $80.00 | $64.00 | $72.00 | $81.40 |
| 0167 | Unpaved trench (***********) - (1, 2") (7300000000-E) | LF | 2,230 | $20.00 | $16.00 | $18.00 | $20.35 |
| 0168 | Unpaved trench (***********) - (4, 2") (7300000000-E) | LF | 60 | $37.00 | $30.00 | $33.75 | $38.15 |
| 0169 | Direct drill (***********) - (1, 2") (7301000000-E) | LF | 555 | $67.00 | $54.00 | $61.00 | $69.00 |
| 0170 | Junction box (standard size) (7324000000-N) | EACH | 27 | $1,035.00 | $835.00 | $937.00 | $1,062.00 |
| 0171 | Junction box (over-sized, heavy duty) (7348000000-N) | EACH | 4 | $1,945.00 | $1,568.00 | $1,760.00 | $1,995.00 |
| 0172 | Wood pole (7360000000-N) | EACH | 2 | $3,105.00 | $2,504.00 | $2,810.00 | $3,185.00 |
| 0173 | Guy assembly (7372000000-N) | EACH | 6 | $1,285.00 | $1,034.00 | $1,160.00 | $1,315.25 |
| 0174 | 1" riser with weatherhead (7408000000-E) | EACH | 2 | $790.00 | $634.00 | $711.00 | $807.00 |
| 0175 | 2" riser with weatherhead (7420000000-E) | EACH | 4 | $1,375.00 | $1,109.00 | $1,240.00 | $1,411.00 |
| 0176 | Inductive loop sawcut (7444000000-E) | LF | 2,035 | $27.25 | $22.00 | $24.75 | $28.00 |
| 0177 | Lead-in cable (14-2) (7456100000-E) | LF | 5,575 | $3.75 | $3.00 | $3.25 | $4.00 |
| 0178 | Site survey (7481000000-N) | EACH | 1 | $1,690.00 | $1,363.00 | $1,530.00 | $1,734.00 |
| 0179 | Camera without internal loop emulator processing unit (7481240000-N) | EACH | 6 | $3,100.00 | $2,501.00 | $2,810.00 | $3,181.25 |
| 0180 | External loop emulator processing unit (7481260000-N) | EACH | 2 | $20,440 | $16,484 | $18,500 | $20,968 |
| 0181 | 900MHZ serial spread spectrum radio (7575142000-N) | EACH | 4 | $6,410.00 | $5,169.00 | $5,800.00 | $6,575.00 |
| 0182 | Metal pole with single mast arm (7588000000-N) | EACH | 4 | $47,265 | $38,116 | $42,800 | $48,483 |
| 0183 | Soil test (7613000000-N) | EACH | 4 | $2,200.00 | $1,772.00 | $1,990.00 | $2,254.00 |
| 0184 | Drilled pier foundation (7614100000-E) | CY | 32 | $3,380.00 | $2,726.00 | $3,060.00 | $3,467.50 |
| 0185 | Sign for signals (7636000000-N) | EACH | 8 | $1,030.00 | $832.00 | $934.00 | $1,059.00 |
| 0186 | Type II pedestal with foundation (7642200000-N) | EACH | 13 | $4,760.00 | $3,840.00 | $4,310.00 | $4,885.00 |
| 0187 | Signal cabinet foundation (7684000000-N) | EACH | 4 | $3,900.00 | $3,146.00 | $3,530.00 | $4,002.00 |
| 0188 | Contlrs with CBNT (**************) - (type 2070LX, base mounted) (7696000000-N) | EACH | 4 | $37,190 | $29,989 | $33,700 | $38,146 |
| 0189 | Detector card (type 170) (7744000000-N) | EACH | 10 | $335.00 | $270.00 | $303.00 | $344.00 |
| 0190 | Cabinet base extender (7901000000-N) | EACH | 4 | $975.00 | $786.00 | $882.00 | $1,000.00 |
| 0191 | Generic signal item (EA) - ethernet edge switch (7980000000-N) | EACH | 4 | $2,240.00 | $1,806.00 | $2,030.00 | $2,298.00 |
| 0192 | Generic signal item (EA) - relocate temporary camera sensor unit (7980000000-N) | EACH | 2 | $515.00 | $415.00 | $466.00 | $528.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of October 21, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.