NCDOT contract C205138 bid tabulation
GRADING, DRAINAGE, AND PAVING. I-77 RAMPS AT US-21, NC-73, NC-24, SR-1109, AND SR-2158. Let by North Carolina DOT on May 19, 2026, Mecklenburg, Iredell. 4 bids received; low bid $5,181,573 by King Asphalt Inc.
- Owner
- North Carolina DOT
- Letting
- 19 MAY 2026
- Pay items
- 73
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | King Asphalt Inc | $5,181,573 | Low |
| 2 | Blythe Brothers Asphalt Co LLC | $5,208,588 | +1.0% |
| 3 | Blythe Construction Inc | $5,797,086 | +12% |
| 4 | NJR Group Inc | $7,610,343 | +47% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. King Asphalt Inc | 2. Blythe Brothers Asphalt Co LLC | 3. Blythe Construction Inc | 4. NJR Group Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $258,500 | $255,000 | $290,000 | $380,500 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $16,000 | $30,000 | $70,000 | $95,000 |
| 0003 | Grading (0043000000-N) | LS | 1 | $706,250 | $530,000 | $697,000 | $1,365,000 |
| 0004 | Aggregate base course (1121000000-E) | TON | 4,219 | $50.25 | $65.00 | $60.00 | $65.00 |
| 0005 | Incidental stone base (1220000000-E) | TON | 430 | $80.70 | $60.00 | $65.00 | $75.00 |
| 0006 | Shoulder reconstruction (1245000000-E) | SMI | 5.93 | $14,110 | $7,000.00 | $10,000 | $10,500 |
| 0007 | Aggregate shoulder borrow (1260000000-E) | TON | 1,879 | $53.00 | $60.00 | $50.00 | $65.00 |
| 0008 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 21,830 | $4.80 | $6.00 | $8.50 | $8.00 |
| 0009 | Mill asp PVMT *****" DTH - (2-1/2") (1297000000-E) | SY | 2,760 | $8.40 | $7.00 | $10.50 | $10.00 |
| 0010 | Mill asp PVMT *****" DTH - (3") (1297000000-E) | SY | 28,330 | $9.50 | $8.00 | $11.00 | $14.00 |
| 0011 | Incidental milling (1330000000-E) | SY | 2,670 | $19.00 | $18.00 | $15.00 | $18.00 |
| 0012 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 5,610 | $60.40 | $105.00 | $90.00 | $119.77 |
| 0013 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 5,370 | $108.25 | $110.00 | $105.00 | $144.10 |
| 0014 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 3,860 | $122.00 | $115.00 | $135.00 | $128.10 |
| 0015 | Asphalt conc surface course, type S9.5D (1524200000-E) | TON | 4,510 | $112.00 | $125.00 | $140.00 | $155.73 |
| 0016 | Asphalt binder for plant mix (1575000000-E) | TON | 760 | $748.00 | $700.00 | $850.00 | $875.00 |
| 0017 | Polymer modified asphalt binder for plant mix (1577000000-E) | TON | 265 | $861.40 | $860.00 | $1,000.00 | $1,050.00 |
| 0018 | Patching existing pavement (1704000000-E) | TON | 523 | $446.00 | $300.00 | $420.00 | $275.00 |
| 0019 | Generic paving item (LF) 665 - milled rumble strips (asphalt concrete), (16") (1841000000-E) | LF | 6,245 | $2.60 | $1.50 | $2.00 | $2.00 |
| 0020 | Geotextile for drainage (3656000000-E) | SY | 190 | $12.40 | $6.00 | $6.00 | $8.00 |
| 0021 | Sign erect, reloc ** GRD MTD - (D) (4116100000-N) | EACH | 4 | $250.00 | $200.00 | $250.00 | $230.00 |
| 0022 | Sign erect, reloc ** GRD MTD - (E) (4116100000-N) | EACH | 2 | $250.00 | $200.00 | $250.00 | $178.25 |
| 0023 | Work zone signs (stationary) (4400000000-E) | SF | 1,188 | $7.50 | $12.00 | $8.00 | $8.05 |
| 0024 | Work zone signs (portable) (4405000000-E) | SF | 32 | $12.00 | $15.00 | $13.00 | $27.60 |
| 0025 | Work zone signs (barricade mounted) (4410000000-E) | SF | 36 | $7.00 | $15.00 | $8.00 | $9.20 |
| 0026 | Work zone advance/general warning signing (4413000000-E) | SF | 96 | $7.50 | $10.00 | $8.00 | $9.20 |
| 0027 | Flashing arrow board (4415000000-N) | EACH | 2 | $1,000.00 | $2,000.00 | $1,200.00 | $5,750.00 |
| 0028 | Portable changeable message sign (4420000000-N) | EACH | 6 | $4,000.00 | $1,500.00 | $4,000.00 | $21,275 |
| 0029 | Drums (4430000000-N) | EACH | 31 | $35.00 | $75.00 | $40.00 | $74.75 |
| 0030 | Barricades (type III) (4445000000-E) | LF | 40 | $27.00 | $50.00 | $35.00 | $25.30 |
| 0031 | Temporary crash cushions (4465000000-N) | EACH | 1 | $6,000.00 | $1,800.00 | $6,500.00 | $12,450 |
| 0032 | Remove & reset temporary crash cushion (4470000000-N) | EACH | 1 | $2,500.00 | $5,000.00 | $2,750.00 | $3,250.00 |
| 0033 | TMA (4480000000-N) | EACH | 1 | $2,400.00 | $8,000.00 | $10,000 | $75,000 |
| 0034 | Portable concrete barrier (4485000000-E) | LF | 460 | $29.00 | $80.00 | $32.00 | $55.62 |
| 0035 | Remove and reset portable concrete barrier (4500000000-E) | LF | 460 | $20.00 | $30.00 | $23.00 | $16.23 |
| 0036 | Law enforcement (4510000000-N) | HR | 150 | $79.00 | $100.00 | $75.00 | $125.00 |
| 0037 | Generic traffic control item (EA) - connected lane closure system (4600000000-N) | EACH | 1 | $975.00 | $5,000.00 | $1,100.00 | $5,750.00 |
| 0038 | Thermoplastic pavement marking lines (6", 90 mils) (4688000000-E) | LF | 38,307 | $0.87 | $1.00 | $1.15 | $0.70 |
| 0039 | Thermoplastic pavement marking lines (8", 90 mils) (4695000000-E) | LF | 80 | $11.25 | $2.00 | $2.30 | $14.38 |
| 0040 | Thermoplastic pavement marking lines (12", 90 mils) (4700000000-E) | LF | 5,525 | $3.00 | $3.00 | $3.50 | $1.39 |
| 0041 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 36 | $23.00 | $18.00 | $20.00 | $46.00 |
| 0042 | Heated-in-place thermoplastic pavement marking character (120 mils) (4726100000-E) | EACH | 12 | $202.00 | $130.00 | $150.00 | $586.50 |
| 0043 | Heated-in-place thermoplastic pavement marking symbol (90 mils) (4726110000-E) | EACH | 32 | $433.00 | $185.00 | $200.00 | $989.00 |
| 0044 | Paint pavement marking lines (6") (4815000000-E) | LF | 43,913 | $1.15 | $0.50 | $0.55 | $0.49 |
| 0045 | Paint pavement marking lines (8") (4820000000-E) | LF | 80 | $4.55 | $0.55 | $0.60 | $0.66 |
| 0046 | Paint pavement marking lines (12") (4825000000-E) | LF | 5,525 | $0.90 | $0.70 | $0.80 | $0.98 |
| 0047 | Paint pavement marking lines (24") (4835000000-E) | LF | 36 | $10.25 | $4.50 | $5.00 | $1.96 |
| 0048 | Paint pavement marking character (4840000000-N) | EACH | 12 | $72.00 | $50.00 | $55.00 | $23.00 |
| 0049 | Paint pavement marking symbol (4845000000-N) | EACH | 52 | $93.00 | $50.00 | $55.00 | $23.00 |
| 0050 | Generic pavement marking item (LF) - yield line thermoplastic pavement marking (24", 90 mils) (4890000000-E) | LF | 40 | $54.00 | $15.00 | $17.00 | $34.50 |
| 0051 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 395 | $80.00 | $86.00 | $90.00 | $64.40 |
| 0052 | Portable lighting (5255000000-N) | LS | 1 | $29,275 | $35,000 | $25,000 | $355,000 |
| 0053 | Temporary silt fence (6000000000-E) | LF | 510 | $3.00 | $3.00 | $3.50 | $5.75 |
| 0054 | Stone for erosion control, class A (6006000000-E) | TON | 100 | $91.00 | $80.00 | $60.00 | $70.00 |
| 0055 | Stone for erosion control, class B (6009000000-E) | TON | 110 | $92.00 | $80.00 | $60.00 | $70.00 |
| 0056 | Sediment control stone (6012000000-E) | TON | 65 | $108.00 | $70.00 | $55.00 | $70.00 |
| 0057 | Temporary mulching (6015000000-E) | ACRE | 1 | $1,800.00 | $1,800.00 | $1,900.00 | $1,955.00 |
| 0058 | Seed for temporary seeding (6018000000-E) | LB | 100 | $3.00 | $3.00 | $3.50 | $6.90 |
| 0059 | Fertilizer for temporary seeding (6021000000-E) | TON | 1 | $1,350.00 | $1,350.00 | $1,450.00 | $2,185.00 |
| 0060 | Temporary slope drains (6024000000-E) | LF | 200 | $53.00 | $25.00 | $7.00 | $30.00 |
| 0061 | Safety fence (6029000000-E) | LF | 120 | $2.00 | $30.00 | $2.50 | $5.00 |
| 0062 | Silt excavation (6030000000-E) | CY | 120 | $62.00 | $25.00 | $10.00 | $25.00 |
| 0063 | 1/4" hardware cloth (6042000000-E) | LF | 75 | $6.00 | $6.00 | $7.00 | $15.00 |
| 0064 | Wattle barrier (6071013000-E) | LF | 50 | $11.00 | $11.00 | $11.00 | $95.00 |
| 0065 | Seeding and mulching (6084000000-E) | ACRE | 3 | $2,650.00 | $2,650.00 | $3,000.00 | $2,990.00 |
| 0066 | Mowing (6087000000-E) | ACRE | 3 | $185.00 | $185.00 | $200.00 | $345.00 |
| 0067 | Seed for repair seeding (6090000000-E) | LB | 50 | $8.00 | $8.00 | $9.00 | $8.05 |
| 0068 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $1,900.00 | $1,900.00 | $2,000.00 | $2,530.00 |
| 0069 | Seed for supplemental seeding (6096000000-E) | LB | 50 | $8.00 | $8.00 | $9.00 | $6.90 |
| 0070 | Fertilizer topdressing (6108000000-E) | TON | 0.75 | $1,700.00 | $1,700.00 | $1,800.00 | $2,415.00 |
| 0071 | Specialized hand mowing (6114500000-N) | MHR | 10 | $90.00 | $90.00 | $100.00 | $86.25 |
| 0072 | Response for erosion control (6117000000-N) | EACH | 13 | $275.00 | $275.00 | $325.00 | $287.50 |
| 0073 | Inductive loop sawcut (7444000000-E) | LF | 3,316 | $10.00 | $19.00 | $20.00 | $11.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of May 19, 2026. Compiled by Mirage Metrics.