King Asphalt Inc: NCDOT bid record
King Asphalt Inc submitted 16 bids on North Carolina DOT contracts in the data, from 18 JUN 2024 to 20 OCT 2026, and was the low bidder on 1 of them (6%). When it was not low, its total sat a median +10% above the low bid.
- Owner
- North Carolina DOT
- Low bid volume
- $5,181,573
- Latest bid
- 20 OCT 2026
- Data through
- 20 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2024 | 1 | 0 | 0% |
| 2025 | 4 | 0 | 0% |
| 2026 | 11 | 1 | 9% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Mecklenburg | 5 | 0 | 0% |
| Brunswick | 3 | 0 | 0% |
| Pender | 2 | 0 | 0% |
| Cabarrus | 1 | 0 | 0% |
| Rowan | 1 | 0 | 0% |
| Onslow | 1 | 0 | 0% |
| Mecklenburg, Iredell | 1 | 1 | 100% |
| New Hanover | 1 | 0 | 0% |
| Union | 1 | 0 | 0% |
Pay items where it is most often lowest
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Blythe Construction Inc | 8 | 5 of 8 |
| S T Wooten Corporation | 7 | 6 of 7 |
| Barnhill Contracting Company | 7 | 6 of 7 |
| NJR Group Inc | 5 | 3 of 5 |
| Highland Paving Co LLC | 5 | 2 of 5 |
| Blythe Development Co. | 4 | 3 of 4 |
| Sealand Contractors Corp | 3 | 3 of 3 |
| Blythe Brothers Asphalt Co LLC | 3 | 1 of 3 |
| Kemp Sigmon Construction Co Inc | 2 | 2 of 2 |
| Truerock Construction LLC | 2 | 2 of 2 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 20 OCT 2026 | C205236 | Union | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 2 SECTIONS OF US-74 EAST, 1 SECTION OF NC-84, AND 15 SECTIONS OF SECONDARY ROADS | 2 of 3 | $7,481,156 | +8.0% |
| 16 JUN 2026 | C205213 | New Hanover | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 5 SECTIONS OF US-117, 3 SECTIONS OF NC-133, AND 46 SECTIONS OF SECONDARY ROADS | 2 of 3 | $5,461,927 | +2.0% |
| 16 JUN 2026 | C205212 | Pender | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF US-421, 9 SECTIONS OF SECONDARY ROADS, AND 6 SECTIONS OF TOWN ROADS | 3 of 4 | $4,465,311 | +10% |
| 16 JUN 2026 | C204970 | Brunswick | GRADING, DRAINAGE, PAVING, AND SIGNALS. NEW ROUTE FROM 0.5 MILES EAST OF BRUNSWICK COUNTY LINE TO 1.5 MILES EAST OF BRUNSWICK COUNTY LINE ON | 7 of 7 | $9,624,333 | +22% |
| 19 MAY 2026 | C205199 | Brunswick | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 3 SECTIONS OF NC-133, AND 19 SECTIONS OF SECONDARY ROADS | 4 of 4 | $5,424,584 | +6.0% |
| 19 MAY 2026 | C205138 | Mecklenburg, Iredell | GRADING, DRAINAGE, AND PAVING. I-77 RAMPS AT US-21, NC-73, NC-24, SR-1109, AND SR-2158 | 1 of 4 | $5,181,573 | Low, 1.0% under the second |
| 17 MAR 2026 | C205175 | Onslow | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 3 SECTIONS OF NC-111, 2 SECTIONS OF US-258, AND 6 SECTIONS OF SECONDARY ROADS | 4 of 4 | $6,849,702 | +10% |
| 17 FEB 2026 | C205170 | Rowan | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF US-29 S,1 SECTION US-29 N, AND 13 SECTIONS OF SECONDARY ROADS | 3 of 3 | $9,127,281 | +27% |
| 17 FEB 2026 | C205168 | Mecklenburg | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 2 SECTIONS OF US-21, 1 SECTION OF NC-24, & 1 SECTION OF NC-51, AND 14 SECTIONS OF SECONDA | 2 of 3 | $4,863,867 | +2.0% |
| 17 FEB 2026 | C205095 | Mecklenburg | GRADING, DRAINAGE, PAVING, SIGNALS, AND CULVERTS. SR-2415 (BAILEY RD) FROM POOLE PLACE DR TO US-21 (STATESVILLE RD) | 6 of 10 | $8,991,316 | +15% |
| 20 JAN 2026 | C205117 | Cabarrus | GRADING, DRAINAGE, PAVING, AND SIGNALS. US-29 FROM 0.6 MILES WEST OF SR-1414 (ROCK HILL CHURCH RD) TO JUST EAST OF SR-1414 (ROCK HILL CHURCH | 4 of 5 | $15,510,468 | +11% |
| 16 DEC 2025 | C205149 | Mecklenburg | MILLING AND RESURFACING. 4 SECTIONS OF NC-49 | 2 of 3 | $6,574,666 | +9.0% |
| 18 NOV 2025 | C205118 | Mecklenburg | GRADING, DRAINAGE, AND PAVING. SR-2042 (OAKDALE RD), SR-2108 (SUNSET RD), SR-2025 (MIRANDA RD), AND SR-2040 (LAWING RD) | 6 of 6 | $9,447,290 | +38% |
| 17 JUN 2025 | C205101 | Pender | GRADING, MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF US-421, AND 2 SECTIONS OF SECONDARY ROADS | 3 of 4 | $5,264,650 | +14% |
| 17 JUN 2025 | C205109 | Brunswick | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF NC-87, 1 SECTION OF NC-133, AND 3 SECTIONS OF SECONDARY ROADS | 2 of 4 | $5,464,350 | +5.0% |
| 18 JUN 2024 | C204501 | Mecklenburg | GRADING, DRAINAGE, PAVING, AND STRUCTURES. SR-2316 (NORTHCROSS DR) FROM NORTH OF NC-73 (SAM FURR RD) TO SR-2147 (WESTMORELAND RD) | 6 of 9 | $22,855,739 | +10% |
How this record was read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; NCDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.