NCDOT contract C205194 bid tabulation
GRADING, DRAINAGE, PAVING, AND STRUCTURE. BRIDGE #780177 OVER MATRIMONY CREEK ON SR-1535 (PRICE RD). Let by North Carolina DOT on July 21, 2026, Rockingham. 5 bids received; low bid $3,486,174 by Smith-Rowe, LLC.
- Owner
- North Carolina DOT
- Letting
- 21 JUL 2026
- Pay items
- 125
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Smith-Rowe, LLC | $3,486,174 | Low |
| 2 | United Infrastructure Group Inc | $3,871,218 | +11% |
| 3 | Haymes Brothers, Inc. | $4,649,378 | +33% |
| 4 | W C English Incorporated | $4,799,847 | +38% |
| 5 | Caton Construction Group Inc | $4,934,277 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Smith-Rowe, LLC | 2. United Infrastructure Group Inc | 3. Haymes Brothers, Inc. | 4. W C English Incorporated | 5. Caton Construction Group Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $174,300 | $193,561 | $218,000 | $240,000 | $246,500 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $16,500 | $100,000 | $50,000 | $50,387 | $28,000 |
| 0003 | Undercut excavation (0036000000-E) | CY | 350 | $0.01 | $23.00 | $12.00 | $40.00 | $94.76 |
| 0004 | Grading (0043000000-N) | LS | 1 | $376,000 | $453,310 | $370,000 | $532,575 | $294,924 |
| 0005 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $0.01 | $0.01 | $5,000.00 | $0.01 | $9,000.00 |
| 0006 | Select granular material (0195000000-E) | CY | 300 | $0.01 | $0.01 | $48.00 | $65.00 | $136.76 |
| 0007 | Geotextile for soil stabilization (0196000000-E) | SY | 300 | $5.25 | $3.85 | $3.50 | $4.50 | $8.65 |
| 0008 | Rock plating (0223000000-E) | SY | 80 | $82.00 | $150.00 | $140.00 | $120.00 | $142.12 |
| 0009 | Generic grading item (LS) - type 1 bridge approach fill, station 22+25.00 -L- (0248000000-N) | LS | 1 | $57,425 | $50,000 | $42,000 | $34,000 | $32,000 |
| 0010 | Foundation conditioning material, minor structures (0318000000-E) | TON | 60 | $44.20 | $48.00 | $36.00 | $52.75 | $78.68 |
| 0011 | FND condit geotextile (4A) (0321000000-E) | SY | 160 | $6.10 | $3.00 | $8.00 | $4.70 | $8.65 |
| 0012 | 15" drainage pipe (0335200000-E) | LF | 120 | $73.78 | $100.00 | $150.00 | $139.15 | $179.46 |
| 0013 | **" drainage pipe elbow - (15") (0335850000-E) | EACH | 2 | $678.43 | $1,500.00 | $600.00 | $640.34 | $1,283.33 |
| 0014 | 15" RC pipe culverts, class III (0366000000-E) | LF | 292 | $90.11 | $125.00 | $100.00 | $136.45 | $194.70 |
| 0015 | 24" CS pipe culverts, 0.064" thick (0594000000-E) | LF | 68 | $133.15 | $125.00 | $270.00 | $230.72 | $204.63 |
| 0016 | **" CS elbow *****" thick - (24", 0.064") (0636000000-E) | EACH | 2 | $1,160.70 | $1,000.00 | $750.00 | $1,153.94 | $2,157.68 |
| 0017 | Pipe removal (0995000000-E) | LF | 43 | $62.03 | $40.00 | $60.00 | $20.95 | $166.68 |
| 0018 | Shallow undercut (1099500000-E) | CY | 100 | $26.85 | $29.00 | $16.00 | $36.85 | $114.88 |
| 0019 | Class IV subgrade stabilization (1099700000-E) | TON | 827 | $22.00 | $36.00 | $38.00 | $47.95 | $76.68 |
| 0020 | Geotextile for subgrade stabilization (1112000000-E) | SY | 1,261 | $3.00 | $4.00 | $3.50 | $6.45 | $8.19 |
| 0021 | Aggregate base course (1121000000-E) | TON | 187 | $48.15 | $55.00 | $85.00 | $52.20 | $117.28 |
| 0022 | Incidental stone base (1220000000-E) | TON | 100 | $49.65 | $45.00 | $30.00 | $54.20 | $115.56 |
| 0023 | Incidental milling (1330000000-E) | SY | 500 | $23.35 | $25.00 | $32.00 | $90.00 | $26.14 |
| 0024 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 500 | $135.00 | $135.00 | $150.00 | $162.00 | $266.65 |
| 0025 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 500 | $135.00 | $135.00 | $150.00 | $162.00 | $266.65 |
| 0026 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 520 | $135.00 | $135.00 | $150.00 | $162.00 | $277.11 |
| 0027 | Asphalt binder for plant mix (1575000000-E) | TON | 85 | $960.00 | $960.00 | $1,050.00 | $1,152.00 | $277.11 |
| 0028 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 121 | $40.75 | $150.00 | $150.00 | $210.00 | $298.02 |
| 0029 | Subdrain excavation (2022000000-E) | CY | 44.80 | $10.00 | $40.00 | $100.00 | $50.35 | $145.33 |
| 0030 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $1.15 | $1.40 | $3.25 | $4.65 | $16.73 |
| 0031 | Subdrain coarse aggregate (2036000000-E) | CY | 33.60 | $25.00 | $115.00 | $56.00 | $81.15 | $185.37 |
| 0032 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $1.10 | $4.00 | $17.00 | $18.85 | $32.95 |
| 0033 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $125.00 | $300.00 | $500.00 | $420.00 | $2,065.52 |
| 0034 | 6" outlet pipe (2077000000-E) | LF | 6 | $61.85 | $10.00 | $50.00 | $65.00 | $209.35 |
| 0035 | Masonry drainage structures (2286000000-N) | EACH | 6 | $4,602.13 | $6,500.00 | $4,000.00 | $6,372.81 | $15,906 |
| 0036 | Masonry drainage structures (2308000000-E) | LF | 1.10 | $601.86 | $175.00 | $2,800.00 | $750.00 | $2,943.47 |
| 0037 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 2 | $1,297.44 | $2,000.00 | $900.00 | $1,672.60 | $1,961.38 |
| 0038 | Frame-GRT-HD 840.03 ** - (E) (2374000000-N) | EACH | 1 | $1,459.28 | $2,000.00 | $1,200.00 | $1,292.00 | $2,059.03 |
| 0039 | Frame-GRT-HD 840.03 ** - (F) (2374000000-N) | EACH | 2 | $1,459.28 | $2,000.00 | $1,000.00 | $1,292.00 | $2,378.73 |
| 0040 | Frame-GRT-HD 840.03 ** - (G) (2374000000-N) | EACH | 1 | $1,459.28 | $2,000.00 | $1,000.00 | $1,292.00 | $2,378.75 |
| 0041 | 2'-6" concrete curb & gutter (2549000000-E) | LF | 220 | $47.25 | $55.00 | $70.00 | $57.15 | $42.25 |
| 0042 | Shoulder berm gutter (2556000000-E) | LF | 60 | $57.25 | $80.00 | $70.00 | $69.15 | $52.25 |
| 0043 | 4" concrete sidewalk (2591000000-E) | SY | 120 | $113.31 | $100.00 | $135.00 | $94.50 | $73.35 |
| 0044 | Concrete curb ramps (2605000000-N) | EACH | 1 | $4,648.18 | $3,500.00 | $550.00 | $3,180.00 | $2,650.00 |
| 0045 | Adjustment of manholes (2830000000-N) | EACH | 1 | $3,168.80 | $1,000.00 | $3,400.00 | $2,079.52 | $2,476.80 |
| 0046 | Steel beam guardrail (3030000000-E) | LF | 487.50 | $24.50 | $24.50 | $26.00 | $29.40 | $24.50 |
| 0047 | Additional guardrail posts (3150000000-N) | EACH | 5 | $1.00 | $1.00 | $1.00 | $1.20 | $1.00 |
| 0048 | Guardrail anchor units, type III (3215000000-N) | EACH | 4 | $2,400.00 | $2,400.00 | $2,600.00 | $2,880.00 | $2,400.00 |
| 0049 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 6 | $3,200.00 | $3,200.00 | $3,500.00 | $3,840.00 | $3,200.00 |
| 0050 | Remove existing guardrail (3360000000-E) | LF | 208 | $1.00 | $1.00 | $1.20 | $1.20 | $1.00 |
| 0051 | Generic fencing item (EA) - bollards (3578000000-N) | EACH | 3 | $2,000.00 | $2,000.00 | $2,200.00 | $2,400.00 | $2,000.00 |
| 0052 | Rip rap, class II (3635000000-E) | TON | 41 | $82.00 | $85.00 | $60.00 | $71.20 | $98.75 |
| 0053 | Rip rap, class B (3649000000-E) | TON | 10 | $99.30 | $85.00 | $75.00 | $93.10 | $134.58 |
| 0054 | Geotextile for drainage (3656000000-E) | SY | 650 | $5.30 | $3.00 | $2.50 | $3.45 | $8.27 |
| 0055 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 40 | $14.00 | $7.65 | $12.00 | $9.20 | $7.65 |
| 0056 | Sign erection, type E (4102000000-N) | EACH | 3 | $200.00 | $190.00 | $190.00 | $228.00 | $190.00 |
| 0057 | Sign erect, reloc ** GRD MTD - (E) (4116100000-N) | EACH | 1 | $250.00 | $175.00 | $142.00 | $210.00 | $175.00 |
| 0058 | Disposal of sign system, U-channel (4155000000-N) | EACH | 7 | $5.00 | $5.00 | $5.50 | $6.00 | $5.00 |
| 0059 | Disposal of support, U-channel (4192000000-N) | EACH | 1 | $5.00 | $5.00 | $5.50 | $6.00 | $5.00 |
| 0060 | Work zone signs (stationary) (4400000000-E) | SF | 670 | $9.00 | $6.50 | $8.10 | $7.80 | $6.50 |
| 0061 | Work zone signs (barricade mounted) (4410000000-E) | SF | 184 | $8.50 | $6.25 | $8.25 | $7.50 | $6.25 |
| 0062 | Barricades (type III) (4445000000-E) | LF | 96 | $25.00 | $18.00 | $19.50 | $21.60 | $18.00 |
| 0063 | Pedestrian channelizing devices (4447000000-E) | LF | 16 | $50.00 | $36.00 | $16.00 | $43.20 | $36.00 |
| 0064 | Generic PVMT marking item (LF) 1205 - integrated multipolymer pavement marking lines (4", 90 mils) (4891000000-E) | LF | 4,021 | $3.00 | $3.00 | $3.30 | $3.60 | $3.00 |
| 0065 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 21 | $225.00 | $225.00 | $250.00 | $270.00 | $225.00 |
| 0066 | Permanent raised pavement markers (4900000000-N) | EACH | 3 | $25.00 | $25.00 | $28.00 | $30.00 | $25.00 |
| 0067 | 6" water line (5325600000-E) | LF | 306 | $160.86 | $145.00 | $115.00 | $148.35 | $242.64 |
| 0068 | DI H2O pipe fittings (5329000000-E) | LB | 750 | $25.46 | $12.00 | $8.50 | $16.60 | $18.81 |
| 0069 | 6" valve (5540000000-E) | EACH | 1 | $4,545.52 | $4,500.00 | $4,000.00 | $4,907.10 | $8,007.57 |
| 0070 | Utility vault (5773000000-N) | EACH | 1 | $59,904 | $22,000 | $78,000 | $57,455 | $42,000 |
| 0071 | Abandon 6" utility pipe (5800000000-E) | LF | 302 | $20.84 | $32.00 | $16.00 | $26.05 | $20.29 |
| 0072 | Remove utility manhole (5828000000-N) | EACH | 1 | $1,376.10 | $7,000.00 | $2,500.00 | $3,340.00 | $2,582.20 |
| 0073 | Temporary silt fence (6000000000-E) | LF | 1,275 | $3.00 | $3.00 | $3.50 | $3.35 | $2.80 |
| 0074 | Stone for erosion control, class A (6006000000-E) | TON | 115 | $0.01 | $60.00 | $100.00 | $54.60 | $109.50 |
| 0075 | Stone for erosion control, class B (6009000000-E) | TON | 345 | $71.50 | $65.00 | $100.00 | $55.80 | $100.37 |
| 0076 | Sediment control stone (6012000000-E) | TON | 280 | $67.15 | $55.00 | $85.00 | $56.00 | $91.74 |
| 0077 | Temporary mulching (6015000000-E) | ACRE | 1.50 | $800.00 | $800.00 | $2,000.00 | $2,160.00 | $1,800.00 |
| 0078 | Seed for temporary seeding (6018000000-E) | LB | 100 | $2.00 | $2.00 | $2.20 | $2.40 | $2.00 |
| 0079 | Fertilizer for temporary seeding (6021000000-E) | TON | 0.50 | $800.00 | $800.00 | $1,100.00 | $1,200.00 | $1,000.00 |
| 0080 | Temporary slope drains (6024000000-E) | LF | 215 | $22.30 | $15.00 | $24.00 | $16.30 | $60.20 |
| 0081 | Safety fence (6029000000-E) | LF | 260 | $3.00 | $3.00 | $3.50 | $3.35 | $2.80 |
| 0082 | Silt excavation (6030000000-E) | CY | 470 | $0.01 | $0.01 | $5.00 | $0.01 | $5.00 |
| 0083 | Matting for erosion control (6036000000-E) | SY | 4,325 | $1.75 | $1.75 | $1.90 | $2.05 | $1.70 |
| 0084 | Coir fiber mat (6037000000-E) | SY | 100 | $22.00 | $12.00 | $8.80 | $9.60 | $8.00 |
| 0085 | 1/4" hardware cloth (6042000000-E) | LF | 350 | $4.00 | $4.00 | $6.50 | $7.20 | $6.00 |
| 0086 | Special stilling basins (6070000000-N) | EACH | 6 | $0.01 | $1,500.00 | $375.00 | $1,721.50 | $1,602.04 |
| 0087 | Flocculant (6071002000-E) | LB | 30 | $1.00 | $1.00 | $5.50 | $6.00 | $5.00 |
| 0088 | Coir fiber wattle (6071012000-E) | LF | 30 | $30.00 | $20.00 | $9.90 | $10.80 | $9.00 |
| 0089 | Seeding and mulching (6084000000-E) | ACRE | 1.60 | $2,350.00 | $2,350.00 | $3,050.00 | $3,360.00 | $2,800.00 |
| 0090 | Mowing (6087000000-E) | ACRE | 0.80 | $15.00 | $15.00 | $280.00 | $300.00 | $250.00 |
| 0091 | Seed for repair seeding (6090000000-E) | LB | 50 | $3.00 | $3.00 | $5.00 | $5.40 | $4.50 |
| 0092 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $800.00 | $800.00 | $1,285.00 | $1,440.00 | $1,200.00 |
| 0093 | Seed for supplemental seeding (6096000000-E) | LB | 50 | $3.00 | $3.00 | $5.00 | $5.40 | $4.50 |
| 0094 | Fertilizer topdressing (6108000000-E) | TON | 1 | $800.00 | $800.00 | $1,100.00 | $1,200.00 | $1,000.00 |
| 0095 | Specialized hand mowing (6114500000-N) | MHR | 10 | $95.00 | $95.00 | $170.00 | $192.00 | $160.00 |
| 0096 | Response for erosion control (6117000000-N) | EACH | 13 | $10.00 | $10.00 | $275.00 | $300.00 | $250.00 |
| 0097 | Concrete washout structure (6117500000-N) | EACH | 1 | $1,000.00 | $1,000.00 | $3,500.00 | $3,635.00 | $750.00 |
| 0098 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 3 | $643.00 | $750.00 | $2,800.00 | $333.85 | $2,280.67 |
| 0099 | Generic erosion control item (SY) - permanent soil reinforcement mat, type 3 (6141000000-E) | SY | 35 | $20.00 | $25.00 | $11.00 | $12.00 | $10.00 |
| 0100 | CM&R temp access *********** - (22+25.00 -L-) (8017000000-N) | LS | 1 | $7,850.00 | $176,000 | $110,000 | $478,000 | $80,000 |
| 0101 | Remv exist STR ****** BRG (402) - (22+25.00 -L-) (8035000000-N) | LS | 1 | $244,598 | $425,000 | $500,000 | $517,000 | $150,000 |
| 0102 | Asbestos assessment (8065000000-N) | LS | 1 | $1,395.65 | $1,500.00 | $4,000.00 | $1,680.00 | $1,400.00 |
| 0103 | Pile excavation in soil (8096000000-E) | LF | 45 | $298.90 | $500.00 | $1,600.00 | $540.00 | $331.65 |
| 0104 | Pile excavation not in soil (8097000000-E) | LF | 54 | $523.55 | $500.00 | $1,600.00 | $540.00 | $331.65 |
| 0105 | 4'-0" dia drilled piers in soil (8105560000-E) | LF | 12 | $2,749.81 | $900.00 | $4,200.00 | $2,220.00 | $1,530.68 |
| 0106 | 4'-0" dia drilled piers not in soil (8105660000-E) | LF | 33 | $2,749.81 | $1,560.00 | $4,200.00 | $2,220.00 | $3,394.44 |
| 0107 | Permanent steel casing for 4'-0" dia drilled pier (8111600000-E) | LF | 15 | $554.88 | $445.00 | $400.00 | $380.00 | $311.24 |
| 0108 | Sid inspections (8113000000-N) | EACH | 1 | $1,125.00 | $1,000.00 | $5,500.00 | $1,250.00 | $1,020.45 |
| 0109 | CSL testing (8115000000-N) | EACH | 1 | $1,715.00 | $2,700.00 | $5,200.00 | $1,250.00 | $7,114.22 |
| 0110 | Uncl STR excav sta ***** - (22+25.00 -L-) (8121000000-N) | LS | 1 | $12,500 | $40,000 | $40,000 | $28,500 | $48,488 |
| 0111 | Reinforced concrete deck slab (8147000000-E) | SF | 9,188 | $59.36 | $58.00 | $65.00 | $65.00 | $105.64 |
| 0112 | Grooving bridge floors (8161000000-E) | SF | 7,450 | $1.42 | $1.00 | $1.00 | $1.12 | $1.00 |
| 0113 | Class A concrete (bridge) (8182000000-E) | CY | 117.60 | $1,298.87 | $1,650.00 | $2,000.00 | $2,054.00 | $2,523.71 |
| 0114 | BRG appr slab *********** - (22+25.00 -L-) (8210000000-N) | LS | 1 | $47,500 | $50,000 | $50,000 | $46,000 | $59,713 |
| 0115 | Reinforcing steel (bridge) (8217000000-E) | LB | 22,583 | $1.78 | $1.50 | $1.25 | $1.41 | $2.90 |
| 0116 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 2,986 | $3.81 | $3.50 | $2.50 | $2.79 | $6.01 |
| 0117 | Fib **" prestr conc girdr - (63") (8278000000-E) | LF | 871.33 | $654.09 | $500.00 | $950.00 | $590.00 | $878.16 |
| 0118 | Pile DRV equip setup ** steel piles - (HP 12 X 53) (8328200000-E) | EACH | 9 | $997.60 | $2,500.00 | $750.00 | $930.00 | $2,073.51 |
| 0119 | HP 12 X 53 steel piles (8364000000-E) | LF | 360 | $76.86 | $85.00 | $88.00 | $90.00 | $220.81 |
| 0120 | Two bar metal rail (8475000000-E) | LF | 421.67 | $212.48 | $175.00 | $210.00 | $268.00 | $186.00 |
| 0121 | 1'-**"X*****"conc parapet - (1'-2" X 2'-6") (8517000000-E) | LF | 218.33 | $225.78 | $127.00 | $162.00 | $209.00 | $191.59 |
| 0122 | 1'-**"X*****"conc parapet - (1'-2" X 3'-3") (8517000000-E) | LF | 218.33 | $248.58 | $133.00 | $185.00 | $225.00 | $221.58 |
| 0123 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 355 | $62.34 | $72.00 | $115.00 | $58.00 | $119.14 |
| 0124 | Geotextile for drainage (8622000000-E) | SY | 396 | $5.10 | $3.00 | $4.50 | $3.70 | $25.44 |
| 0125 | Elastomeric bearings (8657000000-N) | LS | 1 | $7,875.00 | $25,000 | $10,000 | $20,000 | $32,730 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of July 21, 2026. Compiled by Mirage Metrics.