NCDOT contract C205225 bid tabulation
GRADING, DRAINAGE, AND PAVING., GRADING, DRAINAGE, PAVING, AND RETAINING WALLS. SITES 936-940, 942-944, 314, 316-321, 941: US-176 FROM 0.1 M N OF THOMPSON RD TO 0.8 M EAST OF BEAR CREEK LN. W03293. Let by North Carolina DOT on July 21, 2026, Polk. 3 bids received; low bid $32,021,844 by Blythe Construction Inc.
- Owner
- North Carolina DOT
- Letting
- 21 JUL 2026
- Pay items
- 142
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blythe Construction Inc | $32,021,844 | Low |
| 2 | Precision Pipeline LLC | $35,490,939 | +11% |
| 3 | Zachry Construction Corporation | $36,504,473 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blythe Construction Inc | 2. Precision Pipeline LLC | 3. Zachry Construction Corporation |
|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $1,600,000 | $6,000,000 | $1,825,224 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $180,000 | $300,000 | $500,000 |
| 0003 | Grading (0043000000-N) | LS | 1 | $6,346,001 | $9,557,307 | $1,500,000 |
| 0004 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 2 | $25,000 | $17,500 | $26,242 |
| 0005 | Undercut excavation (0057000000-E) | CY | 3,000 | $23.00 | $30.00 | $23.24 |
| 0006 | Select granular material (0195000000-E) | CY | 3,000 | $84.83 | $60.00 | $51.37 |
| 0007 | Geotextile for soil stabilization (0196000000-E) | SY | 3,000 | $7.17 | $3.00 | $3.12 |
| 0008 | Temporary shoring (0199000000-E) | SF | 2,238 | $110.00 | $28.00 | $64.13 |
| 0009 | Rock embankments (0220000000-E) | TON | 9,240 | $79.25 | $60.00 | $125.00 |
| 0010 | Geotextile for rock embankments (0222000000-E) | SY | 3,725 | $7.00 | $4.00 | $3.31 |
| 0011 | Rock plating (0223000000-E) | SY | 3,675 | $85.00 | $100.00 | $109.32 |
| 0012 | Generic grading item (CY) - borrow for wire form embankment (0234000000-E) | CY | 4,900 | $100.00 | $60.00 | $62.04 |
| 0013 | Generic grading item (SY) - geotextile for wire form embankment, type 5A (0241000000-E) | SY | 19,200 | $5.00 | $3.00 | $4.08 |
| 0014 | Generic grading item (TON) - shot rock plating (0255000000-E) | TON | 4,650 | $82.00 | $50.00 | $70.63 |
| 0015 | Generic grading item (EA) - wire basket forms (0262000000-N) | EACH | 400 | $85.00 | $81.00 | $104.96 |
| 0016 | Foundation conditioning material, minor structures (0318000000-E) | TON | 245.50 | $60.00 | $40.00 | $54.76 |
| 0017 | FND condit geotextile (4A) (0321000000-E) | SY | 772 | $7.15 | $2.00 | $17.96 |
| 0018 | ***" RCP culv class IV - (54") (0448000000-E) | LF | 48 | $500.00 | $398.00 | $585.88 |
| 0019 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 140 | $110.00 | $57.00 | $97.25 |
| 0020 | 24" RC pipe culverts, class IV (0448400000-E) | LF | 272 | $155.00 | $114.00 | $143.29 |
| 0021 | 30" RC pipe culverts, class IV (0448500000-E) | LF | 844 | $175.00 | $162.00 | $201.67 |
| 0022 | 42" RC pipe culverts, class IV (0448700000-E) | LF | 372 | $280.00 | $323.00 | $331.06 |
| 0023 | **" CS pipe culv *****" - (48", 0.109") (0576000000-E) | LF | 44 | $425.00 | $312.00 | $331.69 |
| 0024 | **" CS pipe culv *****" - (54", 0.109") (0576000000-E) | LF | 56 | $315.00 | $277.00 | $399.27 |
| 0025 | 15" CS pipe culverts, 0.064" thick (0582000000-E) | LF | 48 | $135.00 | $56.00 | $198.01 |
| 0026 | 18" CS pipe culverts, 0.064" thick inlet used based on county (0588000000-E) | LF | 132 | $115.00 | $57.00 | $151.68 |
| 0027 | 24" CS pipe culverts, 0.064" thick (0594000000-E) | LF | 308 | $130.00 | $70.00 | $177.42 |
| 0028 | 30" CS pipe culverts, 0.079" thick (0600000000-E) | LF | 52 | $185.00 | $122.00 | $203.52 |
| 0029 | **" CS elbow *****" thick - (15", 0.064") (0636000000-E) | EACH | 2 | $365.00 | $713.00 | $1,042.10 |
| 0030 | **" CS elbow *****" thick - (24", 0.064") (0636000000-E) | EACH | 8 | $650.00 | $980.00 | $1,246.83 |
| 0031 | **" CS elbow *****" thick - (30", 0.079") (0636000000-E) | EACH | 2 | $850.00 | $1,541.00 | $1,406.82 |
| 0032 | **" CS elbow *****" thick - (54", 0.109") (0636000000-E) | EACH | 2 | $2,300.00 | $3,810.00 | $2,386.25 |
| 0033 | Pipe removal (0995000000-E) | LF | 566 | $45.00 | $126.00 | $29.85 |
| 0034 | Pipe clean out (0996000000-N) | EACH | 1 | $12,000 | $148.00 | $8,480.73 |
| 0035 | Shallow undercut (1099500000-E) | CY | 750 | $25.00 | $186.00 | $24.71 |
| 0036 | Class IV subgrade stabilization (1099700000-E) | TON | 1,500 | $40.00 | $50.00 | $39.79 |
| 0037 | Geotextile for subgrade stabilization (1112000000-E) | SY | 2,250 | $4.12 | $3.00 | $5.31 |
| 0038 | Incidental stone base (1220000000-E) | TON | 750 | $55.00 | $40.00 | $35.86 |
| 0039 | Shoulder reconstruction (1245000000-E) | SMI | 0.10 | $41,650 | $492.00 | $27,416 |
| 0040 | Aggregate shoulder borrow (1260000000-E) | TON | 10 | $50.00 | $29.00 | $232.34 |
| 0041 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 850 | $30.00 | $13.00 | $13.64 |
| 0042 | Incidental milling (1330000000-E) | SY | 1,500 | $25.00 | $29.00 | $17.05 |
| 0043 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 2,370 | $196.00 | $158.00 | $157.45 |
| 0044 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 1,490 | $250.00 | $173.00 | $159.55 |
| 0045 | Asphalt binder for plant mix (1575000000-E) | TON | 235 | $770.00 | $1,155.00 | $968.85 |
| 0046 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 180 | $355.00 | $183.00 | $418.85 |
| 0047 | Subdrain excavation (2022000000-E) | CY | 336 | $35.00 | $8.00 | $12.80 |
| 0048 | Geotextile for subsurface drains (2026000000-E) | SY | 1,500 | $12.00 | $1.00 | $2.58 |
| 0049 | Subdrain coarse aggregate (2036000000-E) | CY | 252 | $85.00 | $50.00 | $52.05 |
| 0050 | 6" perforated subdrain pipe (2044000000-E) | LF | 1,500 | $18.00 | $2.00 | $21.62 |
| 0051 | Subdrain pipe outlet (2070000000-N) | EACH | 4 | $400.00 | $18.00 | $393.11 |
| 0052 | 6" outlet pipe (2077000000-E) | LF | 24 | $40.00 | $13.00 | $27.12 |
| 0053 | Endwalls (2209000000-E) | CY | 9.80 | $1,500.00 | $1,650.00 | $2,164.07 |
| 0054 | Flowable fill (2275000000-E) | CY | 3 | $1,000.00 | $339.00 | $438.76 |
| 0055 | Masonry drainage structures (2286000000-N) | EACH | 21 | $3,500.00 | $1,388.00 | $4,924.96 |
| 0056 | Masonry drainage structures (2297000000-E) | CY | 12.10 | $1,800.00 | $1,650.00 | $2,910.34 |
| 0057 | Masonry drainage structures (2308000000-E) | LF | 8.20 | $500.00 | $375.00 | $856.51 |
| 0058 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 5 | $1,650.00 | $3,026.00 | $1,068.47 |
| 0059 | Steel frame with two grates, STD 840.37 (2407000000-N) | EACH | 18 | $3,200.00 | $7,766.00 | $2,877.81 |
| 0060 | **"X**" concrete curb - (8" X 12") (2535000000-E) | LF | 545 | $50.00 | $50.00 | $39.23 |
| 0061 | Shoulder berm gutter (2556000000-E) | LF | 3,180 | $60.00 | $78.00 | $47.97 |
| 0062 | 4" concrete paved ditch (2619000000-E) | SY | 70 | $300.00 | $253.00 | $132.16 |
| 0063 | Steel beam guardrail (3030000000-E) | LF | 4,675 | $23.50 | $29.00 | $24.43 |
| 0064 | Additional guardrail posts (3150000000-N) | EACH | 30 | $44.00 | $1,500.00 | $45.73 |
| 0065 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 7 | $3,200.00 | $3,840.00 | $3,326.01 |
| 0066 | Remove & reset existing guardrail (3345000000-E) | LF | 100 | $7.00 | $30.00 | $7.28 |
| 0067 | Remove existing guardrail (3360000000-E) | LF | 3,061 | $1.00 | $1,750.00 | $1.04 |
| 0068 | Rip rap, class I (3628000000-E) | TON | 114 | $95.00 | $60.00 | $67.34 |
| 0069 | Geotextile for drainage (3656000000-E) | SY | 1,781 | $6.00 | $1.00 | $4.04 |
| 0070 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 227 | $9.00 | $11.00 | $9.45 |
| 0071 | Sign erection, type E (4102000000-N) | EACH | 16 | $100.00 | $222.00 | $194.19 |
| 0072 | Sign erection, type F (4108000000-N) | EACH | 1 | $150.00 | $120.00 | $104.97 |
| 0073 | Sign erect, reloc ** GRD MTD - (E) (4116100000-N) | EACH | 2 | $125.00 | $222.00 | $194.19 |
| 0074 | Disposal of sign system, U-channel (4155000000-N) | EACH | 12 | $25.00 | $1,120.00 | $26.24 |
| 0075 | Disposal of support, U-channel (4192000000-N) | EACH | 2 | $25.00 | $1,052.00 | $26.24 |
| 0076 | Disposal of sign, D, E or F (4238000000-N) | EACH | 2 | $25.00 | $1,383.00 | $26.24 |
| 0077 | Work zone signs (stationary) (4400000000-E) | SF | 1,062 | $8.27 | $11.00 | $9.45 |
| 0078 | Work zone signs (portable) (4405000000-E) | SF | 472 | $16.55 | $26.00 | $23.09 |
| 0079 | Work zone signs (barricade mounted) (4410000000-E) | SF | 210 | $9.31 | $11.00 | $9.45 |
| 0080 | Portable changeable message sign (4420000000-N) | EACH | 3 | $9,308.36 | $19,200 | $16,795 |
| 0081 | Temporary portable traffic signal system (4424500000-N) | EACH | 5 | $88,016 | $45,844 | $19,419 |
| 0082 | Drums (4430000000-N) | EACH | 203 | $46.54 | $60.00 | $60.88 |
| 0083 | Cones (4435000000-N) | EACH | 70 | $28.96 | $33.00 | $26.24 |
| 0084 | Barricades (type III) (4445000000-E) | LF | 216 | $36.20 | $41.00 | $25.19 |
| 0085 | Flagger (4455000000-N) | DAY | 84 | $600.00 | $124.00 | $359.61 |
| 0086 | Temporary crash cushions (4465000000-N) | EACH | 12 | $11,377 | $5,859.00 | $9,210.34 |
| 0087 | Remove & reset temporary crash cushion (4470000000-N) | EACH | 4 | $5,688.44 | $116.00 | $3,344.54 |
| 0088 | Portable concrete barrier (4485000000-E) | LF | 2,270 | $33.10 | $46.00 | $68.93 |
| 0089 | Portable concrete barrier (anchored) (4490000000-E) | LF | 220 | $48.61 | $70.00 | $87.05 |
| 0090 | Remove and reset portable concrete barrier (4500000000-E) | LF | 410 | $20.69 | $228.00 | $28.14 |
| 0091 | Remove & reset portable concrete barrier (anchored) (4505000000-E) | LF | 220 | $41.37 | $1,269.00 | $40.69 |
| 0092 | Skinny drum (4516000000-N) | EACH | 35 | $35.16 | $51.00 | $41.99 |
| 0093 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 20,782 | $1.07 | $1.00 | $0.68 |
| 0094 | 4" cold appl plstic lines type ** - (IV) (4770000000-E) | LF | 820 | $16.49 | $12.00 | $9.45 |
| 0095 | Paint pavement marking lines (4") (4810000000-E) | LF | 16,076 | $0.41 | $0.50 | $0.26 |
| 0096 | Paint pavement marking lines (24") (4835000000-E) | LF | 132 | $8.25 | $7.00 | $6.30 |
| 0097 | Removal of pavement marking lines (4") (4850000000-E) | LF | 2,810 | $2.47 | $2.00 | $2.10 |
| 0098 | Removal of pavement marking lines (24") (4870000000-E) | LF | 132 | $24.74 | $18.00 | $5.25 |
| 0099 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 178 | $112.46 | $82.00 | $94.47 |
| 0100 | Generic utility item (LF) - install conduit (6") (5888000000-E) | LF | 4,000 | $8.00 | $22.00 | $12.07 |
| 0101 | Temporary silt fence (6000000000-E) | LF | 3,660 | $4.00 | $2.00 | $4.20 |
| 0102 | Stone for erosion control, class A (6006000000-E) | TON | 805 | $80.00 | $50.00 | $60.28 |
| 0103 | Stone for erosion control, class B (6009000000-E) | TON | 1,100 | $80.00 | $50.00 | $60.28 |
| 0104 | Sediment control stone (6012000000-E) | TON | 630 | $75.00 | $45.00 | $54.86 |
| 0105 | Temporary mulching (6015000000-E) | ACRE | 8.50 | $2,000.00 | $2,250.00 | $2,099.34 |
| 0106 | Seed for temporary seeding (6018000000-E) | LB | 590 | $2.00 | $2.00 | $2.10 |
| 0107 | Fertilizer for temporary seeding (6021000000-E) | TON | 3 | $1,200.00 | $1,316.00 | $1,259.60 |
| 0108 | Temporary slope drains (6024000000-E) | LF | 390 | $53.13 | $81.00 | $25.32 |
| 0109 | Safety fence (6029000000-E) | LF | 4,690 | $3.20 | $24.00 | $3.36 |
| 0110 | Silt excavation (6030000000-E) | CY | 1,980 | $25.00 | $182.00 | $15.27 |
| 0111 | Matting for erosion control (6036000000-E) | SY | 24,560 | $1.70 | $1.00 | $1.78 |
| 0112 | Coir fiber mat (6037000000-E) | SY | 350 | $8.00 | $0.50 | $8.40 |
| 0113 | 1/4" hardware cloth (6042000000-E) | LF | 1,070 | $6.00 | $3.00 | $6.30 |
| 0114 | Special stilling basins (6070000000-N) | EACH | 23 | $500.00 | $608.00 | $990.70 |
| 0115 | Flocculant (6071002000-E) | LB | 150 | $5.00 | $40.00 | $5.25 |
| 0116 | Coir fiber wattle (6071012000-E) | LF | 60 | $9.00 | $8.00 | $9.45 |
| 0117 | Coir fiber baffle (6071030000-E) | LF | 95 | $10.00 | $14.00 | $10.50 |
| 0118 | Seeding and mulching (6084000000-E) | ACRE | 8.50 | $2,900.00 | $3,300.00 | $3,044.04 |
| 0119 | Mowing (6087000000-E) | ACRE | 4.25 | $300.00 | $203.00 | $314.90 |
| 0120 | Seed for repair seeding (6090000000-E) | LB | 150 | $4.50 | $13.00 | $4.72 |
| 0121 | Fertilizer for repair seeding (6093000000-E) | TON | 0.50 | $1,200.00 | $1,316.00 | $1,259.60 |
| 0122 | Seed for supplemental seeding (6096000000-E) | LB | 225 | $4.50 | $13.00 | $4.72 |
| 0123 | Fertilizer topdressing (6108000000-E) | TON | 6.50 | $1,000.00 | $1,316.00 | $1,049.67 |
| 0124 | Impervious dike (6111000000-E) | LF | 720 | $150.00 | $158.00 | $400.00 |
| 0125 | Specialized hand mowing (6114500000-N) | MHR | 20 | $175.00 | $9.00 | $183.69 |
| 0126 | Manual litter removal (6114800000-N) | MHR | 3 | $175.00 | $17.00 | $183.69 |
| 0127 | Litter disposal (6114900000-E) | TON | 2 | $200.00 | $10.00 | $209.93 |
| 0128 | Response for erosion control (6117000000-N) | EACH | 50 | $300.00 | $1,863.00 | $314.90 |
| 0129 | Concrete washout structure (6117500000-N) | EACH | 5 | $1,000.00 | $1,800.00 | $959.28 |
| 0130 | Reforestation (6123000000-E) | ACRE | 1 | $3,500.00 | $3,750.00 | $3,673.85 |
| 0131 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 105 | $350.00 | $36.00 | $155.50 |
| 0132 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 35 | $350.00 | $293.00 | $400.19 |
| 0133 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 23 | $600.00 | $3,881.00 | $711.18 |
| 0134 | Soil nail retaining walls (8802010000-E) | SF | 4,210 | $180.00 | $250.00 | $186.76 |
| 0135 | Generic ret wall item (LS) - retaining walls, site #936 (8832000000-N) | LS | 1 | $2,400,000 | $921,827 | $4,000,000 |
| 0136 | Generic ret wall item (LS) - retaining walls, site #937 (8832000000-N) | LS | 1 | $3,350,000 | $1,393,443 | $5,800,000 |
| 0137 | Generic ret wall item (LS) - retaining walls, site #938 (8832000000-N) | LS | 1 | $1,800,000 | $464,121 | $2,000,000 |
| 0138 | Generic ret wall item (LS) - retaining walls, site #939 (8832000000-N) | LS | 1 | $1,400,000 | $552,451 | $2,000,000 |
| 0139 | Generic ret wall item (LS) - retaining walls, site #942 (8832000000-N) | LS | 1 | $2,900,000 | $1,240,821 | $4,800,000 |
| 0140 | Generic ret wall item (LS) - retaining walls, site #943 (8832000000-N) | LS | 1 | $700,000 | $39,449 | $400,000 |
| 0141 | Generic ret wall item (LS) - retaining walls, site #944 (8832000000-N) | LS | 1 | $2,924,705 | $1,900,240 | $4,900,000 |
| 0142 | Generic ret wall item (LF) - micropile grade beam (8839000000-E) | LF | 730 | $1,300.00 | $185.00 | $2,191.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of July 21, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.