ODOT contract 250055 bid tabulation

LOR-IR 90-20.20 (LIGHTING). Let by Ohio DOT on January 30, 2025, LOR. 4 bids received; low bid $298,474 by Cornerstone Electric Inc, -19% against the engineer's estimate of $370,000.

Owner
Ohio DOT
Letting
30 JAN 2025
Pay items
36
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Cornerstone Electric Inc$298,474Low-19%
2Miller Cable Company$303,500+2.0%-18%
3Perram Electric Inc$334,034+12%-10%
4Greenwich Electric Inc$353,247+18%-5.0%
ODOT contract 250055: bids by rank

Engineer's estimate: $370,000.

Bid tabulation

LinePay itemUnitQuantity1. Cornerstone Electric Inc2. Miller Cable Company3. Perram Electric Inc4. Greenwich Electric Inc
1Preconstruction survey monument verification and report (623E50000)LS1$500.00$5,000.00$1,400.00$2,400.00
2Erosion control (832E30000)EACH1,000$1.00$1.00$1.00$1.00
34" conduit, type E, as per plan (611E00401)FT260$4.50$1.90$6.75$9.75
4Connection, fused pull apart (625E00450)EACH36$150.00$100.00$183.50$130.00
5Connection, unfused permanent (625E00480)EACH78$100.00$100.00$128.50$115.00
6Light pole, conventional, AT12B35 (625E10490)EACH5$3,250.00$3,200.00$2,820.00$3,050.00
7Light pole, conventional, AT15B35 (625E10490)EACH9$3,500.00$3,300.00$2,880.00$3,115.00
8Light pole foundation, 24" X 6' deep (625E14000)EACH14$1,250.00$1,550.00$1,435.00$1,450.00
9No. 4 AWG 2400 volt distribution cable (625E23200)FT4,092$2.68$3.00$2.95$3.60
10No. 10 AWG pole and bracket cable (625E23400)FT2,655$1.20$2.00$0.92$1.50
111-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT5,461$9.00$13.00$11.08$11.20
12Conduit, 3", 725.04 (625E25500)FT8$35.00$30.00$42.40$32.00
13Conduit, jacked or drilled, 725.04, 3" (625E25902)FT386$62.00$42.00$73.45$62.00
14Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH18$325.00$375.00$447.00$330.00
15Trench (625E29000)FT5,173$9.00$5.00$7.81$8.90
16Pull box, 725.08, 18" (625E30700)EACH8$1,200.00$850.00$1,270.00$1,050.00
17Pull box, 725.08, 24" (625E30706)EACH5$1,400.00$1,100.00$1,445.00$1,250.00
18Pull box removed (625E31510)EACH10$250.00$150.00$187.00$210.00
19Ground rod (625E32000)EACH15$200.00$225.00$312.00$290.00
20Power service, as per plan (625E34001)EACH1$6,500.00$6,800.00$9,400.00$9,545.00
21Underground warning marking tape (625E36010)FT5,173$1.40$2.00$1.43$2.00
22Special - maintain existing lighting (625E40000)LS1$2,000.00$100.00$750.00$1,500.00
23Light pole removed, as per plan (625E75401)EACH14$500.00$200.00$455.00$325.00
24Light pole foundation removed (625E75500)EACH14$250.00$200.00$560.00$425.00
25Luminaire removed for storage (625E75504)EACH18$100.00$50.00$95.00$50.00
26Power service removed (625E75510)EACH2$500.00$500.00$750.00$700.00
27Distribution cable removed (625E75550)FT5,191$1.00$0.10$0.36$0.95
28Arc flash calculations and label, power service (625E76000)EACH1$500.00$2,600.00$1,800.00$3,500.00
29Conduit riser, 2" diameter (632E70400)EACH1$500.00$500.00$645.00$660.00
30Controller work pad (633E67200)EACH1$1,200.00$400.00$260.00$750.00
31Law enforcement officer with patrol car for assistance (614E11110)HR40$65.00$80.00$55.00$80.00
32Premium for contract performance bond and for payment bond (103E05000)LS1$2,800.00$3,419.90$5,583.94$9,500.00
33Maintaining traffic (614E11000)LS1$2,500.00$6,500.00$4,500.00$8,800.00
34Field office, type B (619E16010)MNTH4$500.00$850.00$3,280.00$2,400.00
35Construction layout stakes and surveying (623E10000)LS1$4,000.00$8,100.00$2,100.00$5,800.00
36Mobilization (624E10000)LS1$5,000.00$10,000$10,000$12,000
ODOT contract 250055: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy