ODOT contract 250135 bid tabulation

WAR-S River & S Main NS (RR CROSSING PROTECTION (RRP)). Let by Ohio DOT on February 27, 2025, WAR. 3 bids received; low bid $624,129 by Bansal Construction Inc, +3.0% against the engineer's estimate of $606,000.

Owner
Ohio DOT
Letting
27 FEB 2025
Pay items
82
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Bansal Construction Inc$624,129Low+3.0%
2Complete General Construction Company$696,472+12%+15%
3Sunesis Construction Co$801,924+28%+32%
ODOT contract 250135: bids by rank

Engineer's estimate: $606,000.

Bid tabulation

LinePay itemUnitQuantity1. Bansal Construction Inc2. Complete General Construction Company3. Sunesis Construction Co
1Clearing and grubbing (201E11000)LS1$4,500.00$3,000.00$2,577.90
2Pavement removed (202E23000)SY7$205.00$75.00$344.82
3Walk removed (202E30000)SF832$9.25$10.00$4.17
4Curb removed (202E32000)FT83$28.00$10.00$28.71
5Curb removed, as per plan (202E32001)FT2$300.00$95.00$316.45
6Excavation (203E10000)CY5$275.00$1,250.00$574.79
7Embankment (203E20000)CY5$200.00$90.00$359.99
84" concrete walk (608E10000)SF399$12.25$14.25$50.66
9Curb ramp, as per plan (608E52001)SF515$33.25$17.00$65.01
10Detectable warning (608E53020)SF10$125.00$78.00$821.47
11Crushed aggregate slope protection, as per plan (601E20001)SY9$165.00$97.00$290.46
12Topsoil (659E00300)CY4$200.00$84.00$876.04
13Seeding and mulching (659E10000)SY30$50.00$49.50$78.43
14Repair seeding and mulching (659E14000)SY2$45.00$15.00$50.00
15Inter-seeding (659E15000)SY2$45.00$1.00$50.00
16Commercial fertilizer (659E20000)TON0.01$550.00$1,500.00$10,000
17Lime (659E31000)ACRE0.01$75.00$200.00$10,000
18Water (659E35000)MGAL1$245.00$1.00$100.00
19Erosion control (832E30000)EACH5,000$1.00$1.00$1.00
204" non-reinforced concrete pavement, class QC 1P (452E09010)SY5$185.00$450.00$718.04
21Curb, type 4-C (609E24510)FT54$40.00$85.00$241.03
22Curb, type 6 (609E26000)FT20$40.00$103.00$461.31
23Ground mounted support, no. 3 post (630E03100)FT53$23.14$35.00$23.14
24Sign hanger assembly, mast arm, as per plan (630E79101)EACH7$440.97$343.56$440.97
25Sign, flat sheet (630E80100)SF35$25.20$39.00$25.20
26Removal of ground mounted sign and disposal (630E84900)EACH18$16.55$15.00$16.55
27Removal of ground mounted post support and disposal (630E86002)EACH10$22.07$20.00$22.07
28Internally illuminated fixed message sign, as per plan (631E90501)EACH7$2,800.00$3,100.00$2,919.20
29Removal of pavement marking (642E30000)FT873$2.35$2.35$4.88
30Removal of pavement marking (642E30020)EACH5$255.00$150.00$255.00
31Edge line, 4" (644E00100)MI0.01$7,610.00$10,000$7,610.00
32Edge line, 6" (644E00104)MI0.03$9,555.00$7,500.00$9,555.00
33Center line (644E00300)MI0.13$11,595$10,000$28,278
34Stop line (644E00500)FT63$7.50$8.00$7.50
35Crosswalk line, 12" (644E00620)FT345$6.50$4.00$6.50
36Railroad symbol marking (644E01000)EACH2$450.00$751.00$450.00
37Lane arrow (644E01300)EACH4$175.00$334.00$175.00
38Dotted line, 6" (644E01510)FT114$2.50$2.50$2.50
394" conduit, type E (611E00400)FT100$12.15$16.50$12.67
40Conduit, 4", 725.051 (625E25604)FT113$12.15$28.00$12.67
41Conduit, jacked or drilled, 725.052, 4" (625E25908)FT275$95.00$205.00$99.04
42Trench (625E29000)FT82$12.50$15.00$13.03
43Pull box, 725.08, 24" (625E30706)EACH8$1,450.00$1,650.00$1,511.73
44Ground rod (625E32000)EACH9$485.00$350.00$505.65
45Underground warning marking tape (625E36010)FT82$1.70$2.00$1.77
46Arc flash calculations and label - (signal control (625E76000)EACH2$600.00$2,300.00$625.55
47Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH11$1,225.00$1,000.00$1,277.15
48Vehicular signal head, (LED), 4-section, 12" lens, 1-way, polycarbonate (632E05064)EACH2$1,530.00$1,225.00$1,595.14
49Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH11$615.00$825.00$641.18
50Accessible pedestrian pushbutton (632E20750)EACH6$990.00$1,225.00$1,032.15
51Covering of vehicular signal head (632E25000)EACH14$80.00$40.00$83.41
52Covering of pedestrian signal head (632E25010)EACH12$80.00$35.00$83.41
53Signal cable, 5 conductor, no. 14 AWG (632E40500)FT1,873$2.30$2.75$2.40
54Signal cable, 7 conductor, no. 14 AWG (632E40700)FT1,595$2.55$3.25$2.66
55Signal support foundation (632E64010)EACH4$7,350.00$9,800.00$7,662.90
56Pedestal foundation (632E64020)EACH4$1,465.00$1,950.00$1,527.37
57Loop detector lead-in cable, 2 conductor, no. 14 AWG (632E65300)FT893$2.05$2.50$2.14
58Power cable, 2 conductor, no. 4 AWG (632E69200)FT59$5.50$6.75$5.73
59Service cable, 3 conductor, no. 4 AWG (632E69900)FT180$8.25$7.50$8.60
60Power service (632E70000)EACH2$5,975.00$3,000.00$6,229.36
61Signal support, type TC-12.31, design 6, as per plan (632E71101)EACH2$25,360$25,000$375.33
63Signal support, type TC-81.22, design 4, as per plan (632E72111)EACH4$15,500$18,750$521.29
64Pedestal, 11', transformer base, as per plan (632E90001)EACH5$1,295.00$2,000.00$1,350.13
65Removal of traffic signal installation (632E90100)EACH1$4,925.00$3,300.00$5,134.66
66Cabinet, type TS-2, as per plan (633E65511)EACH2$21,850$21,000$22,780
67Cabinet foundation, as per plan (633E67101)EACH2$1,950.00$5,100.00$2,033.02
68Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH2$8,575.00$8,000.00$8,940.05
69Ethernet cable, outdoor-rated (809E64550)FT120$3.05$2.50$3.18
70ITS device, misc.: high-speed ethernet radio (809E65990)EACH2$10,650$9,475.00$11,103
71Stop line radar detection, as per plan (809E69101)EACH6$9,725.00$8,700.00$10,139
72Atc controller, as per plan (809E69123)EACH2$5,725.00$5,400.00$5,968.72
73Railroad preemption interface, (locate on prop. SI (819E10000)EACH2$10,525$13,680$10,973
74LED blankout sign, ("no left turn -train", 30"X24" (828E00100)EACH1$4,125.00$3,925.00$4,300.60
75LED blankout sign, ("no right turn -train", 30"X24 (828E00100)EACH3$4,125.00$3,925.00$4,300.60
76Law enforcement officer with patrol car for assistance (614E11110)HR48$75.00$100.00$100.00
77Water (616E10000)MGAL1$245.00$1.00$69.10
78Railroad flagging services (900E00100)EACH5,000$1.00$1.00$1.00
79Premium on railroads' protective public liability and property damage liability insurance (100E00300)LS1$5,150.00$3,100.00$5,737.14
80Premium for contract performance bond and for payment bond (103E05000)LS1$4,257.52$5,400.00$5,121.67
81Maintaining traffic (614E11000)LS1$10,000$30,000$54,985
82Construction layout stakes and surveying (623E10000)LS1$10,000$6,000.00$3,700.00
83Mobilization (624E10000)LS1$40,000$40,000$204,138
ODOT contract 250135: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy