ODOT contract 250170 bid tabulation
WIL-US 6/SR 49/SR 191-00.00/00.00/00.00 (TWO LANE RESURFACING). Let by Ohio DOT on March 27, 2025, WIL. 1 bid received; low bid $4,365,970 by Gerken Paving Inc, +7.1% against the engineer's estimate of $4,078,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 80
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Gerken Paving Inc | $4,365,970 | Low | +7.0% |
Engineer's estimate: $4,078,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gerken Paving Inc |
|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 156 | $30.00 |
| 2 | Pavement removed (202E23000) | SY | 200 | $32.50 |
| 3 | Walk removed (202E30000) | SF | 2,659 | $3.85 |
| 4 | Curb removed (202E32000) | FT | 110 | $11.00 |
| 5 | Curb and gutter removed (202E32500) | FT | 187 | $12.00 |
| 6 | Excavation (203E10000) | CY | 2 | $75.00 |
| 7 | Embankment (203E20000) | CY | 2 | $75.00 |
| 8 | Linear grading (209E60500) | MI | 15 | $2,100.00 |
| 9 | Curb ramp (608E52000) | SF | 4,000 | $20.00 |
| 10 | Detectable warning (608E53020) | SF | 74 | $35.00 |
| 11 | Topsoil (659E00300) | CY | 1.50 | $100.00 |
| 12 | Seeding and mulching (659E10000) | SY | 10 | $10.00 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.01 | $1,500.00 |
| 14 | Water (659E35000) | MGAL | 0.03 | $500.00 |
| 15 | Erosion control (832E30000) | EACH | 2,500 | $1.00 |
| 16 | 4" conduit, type C (611E00200) | FT | 144 | $34.00 |
| 17 | Catch basin adjusted to grade (611E98630) | EACH | 8 | $2,350.00 |
| 18 | Manhole adjusted to grade (611E99654) | EACH | 10 | $1,950.00 |
| 19 | Pavement repair (253E02000) | CY | 1,873 | $244.00 |
| 20 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 613 | $11.00 |
| 21 | Pavement planing, asphalt concrete, 1.75" (254E01000) | SY | 49,871 | $3.25 |
| 22 | Pavement planing, asphalt concrete, 3.25" (254E01000) | SY | 52,559 | $3.80 |
| 23 | Pavement planing, asphalt concrete, 3.50" (254E01000) | SY | 35,695 | $2.40 |
| 24 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 35 | $300.00 |
| 25 | Aggregate base (304E20000) | CY | 39 | $80.00 |
| 26 | Tack coat (407E10000) | GAL | 17,068 | $2.50 |
| 27 | Fine graded polymer asphalt concrete, type B, (448), as per plan (424E14001) | CY | 992 | $236.00 |
| 28 | Fine graded polymer asphalt concrete, type B, (448), as per plan (424E14001) | CY | 116.50 | $236.00 |
| 29 | Asphalt concrete intermediate course, type 2, (446) (441E10200) | CY | 2,479 | $170.00 |
| 30 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 150 | $625.00 |
| 31 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00200) | CY | 2,425 | $238.00 |
| 32 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 2,191 | $232.00 |
| 33 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 131.50 | $232.00 |
| 34 | Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080) | CY | 2,556 | $198.00 |
| 35 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E22000) | CY | 9 | $700.00 |
| 36 | Combination curb and gutter, type 2 (609E12000) | FT | 285 | $45.00 |
| 37 | Curb, type 6 (609E26000) | FT | 110 | $35.00 |
| 38 | Compacted aggregate (617E10100) | CY | 1,390 | $85.00 |
| 39 | Rumble stripes, center line (asphalt concrete) (618E40900) | FT | 12,068 | $1.05 |
| 40 | Longitudinal joint preparation (874E20000) | FT | 12,068 | $3.40 |
| 41 | Longitudinal joint adhesive (875E10000) | LB | 7,273 | $1.75 |
| 42 | Valve box adjusted to grade (638E10800) | EACH | 3 | $775.00 |
| 43 | RPM (621E00100) | EACH | 349 | $44.50 |
| 44 | Raised pavement marker removed (621E54000) | EACH | 349 | $16.50 |
| 45 | Edge line, 6", type 1 (642E00104) | MI | 15.90 | $750.00 |
| 46 | Center line, type 1 (642E00300) | MI | 5.57 | $800.00 |
| 47 | Center line, type 1 (642E00300) | MI | 2.01 | $800.00 |
| 48 | Center line, type 1 (642E00300) | MI | 0.43 | $800.00 |
| 49 | Channelizing line, 12", type 1 (642E00404) | FT | 375 | $1.00 |
| 50 | Dotted line, 6", type 1 (642E01510) | FT | 250 | $1.00 |
| 51 | Stop line (644E00500) | FT | 150 | $7.00 |
| 52 | Crosswalk line, 24" (644E00630) | FT | 1,428 | $7.00 |
| 53 | Transverse/diagonal line (644E00700) | FT | 572 | $2.00 |
| 54 | Railroad symbol marking (644E01000) | EACH | 2 | $800.00 |
| 55 | School symbol marking, 72" (644E01100) | EACH | 2 | $800.00 |
| 56 | School symbol marking, 120" (644E01120) | EACH | 1 | $800.00 |
| 57 | Parking lot stall marking (644E01200) | FT | 2,785 | $2.00 |
| 58 | Lane arrow (644E01300) | EACH | 18 | $95.00 |
| 59 | Handicap symbol marking (644E01600) | EACH | 9 | $150.00 |
| 60 | Work zone marking sign (614E12460) | EACH | 50 | $125.00 |
| 61 | Replacement sign (614E12500) | EACH | 5 | $95.00 |
| 62 | Replacement drum (614E12600) | EACH | 5 | $60.00 |
| 63 | Work zone center line, class I (614E21000) | MI | 16.30 | $800.00 |
| 64 | Work zone center line, class III, 642 paint (614E21550) | MI | 8.10 | $800.00 |
| 65 | Work zone stop line, class I (614E26000) | FT | 200 | $2.00 |
| 66 | Work zone stop line, class III, 642 paint (614E26610) | FT | 100 | $2.00 |
| 67 | Railroad flagging services (900E00100) | EACH | 17,675 | $1.00 |
| 68 | Pavement planing, asphalt concrete, 1.75" (254E01000) | SY | 498 | $11.00 |
| 69 | Preformed elastomeric compression joint seal, as per plan (516E10001) | FT | 68 | $175.00 |
| 70 | Joint sealer (516E31000) | FT | 136 | $30.00 |
| 71 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 68 | $28.00 |
| 72 | Patching concrete structure (519E11100) | SF | 108 | $145.00 |
| 73 | Pavement planing, asphalt concrete, 1.75" (254E01000) | SY | 857 | $8.40 |
| 74 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 160 | $30.00 |
| 75 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $5,500.00 |
| 76 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $21,000 |
| 77 | Maintaining traffic (614E11000) | LS | 1 | $245,000 |
| 78 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,503.00 |
| 79 | Mobilization (624E10000) | LS | 1 | $135,500 |
| 100 | Preparing subgrade for shoulder paving (209E72050) | MI | 10.80 | $2,600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.