ODOT contract 250175 bid tabulation
D08-LG LED FY25 (LIGHTING). Let by Ohio DOT on March 27, 2025, District 8. 6 bids received; low bid $440,699 by Capital Electric Line Builders Inc, -52% against the engineer's estimate of $916,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 17
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Capital Electric Line Builders Inc | $440,699 | Low | -52% |
| 2 | Miller Cable Company | $669,000 | +52% | -27% |
| 3 | Asplundh Construction LLC | $722,085 | +64% | -21% |
| 4 | Complete General Construction Company | $755,995 | +72% | -17% |
| 5 | Danbert Electrical Corp | $835,584 | +90% | -9.0% |
| 6 | Bansal Construction Inc | $1,019,754 | +131% | +11% |
Engineer's estimate: $916,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Capital Electric Line Builders Inc | 2. Miller Cable Company | 3. Asplundh Construction LLC | 4. Complete General Construction Company | 5. Danbert Electrical Corp | 6. Bansal Construction Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,204.00 | $75.00 | $3,536.06 | $3,500.00 | $14,400 | $5,000.00 |
| 2 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 13 | $150.00 | $275.00 | $222.52 | $350.00 | $318.00 | $415.00 |
| 3 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 64 | $150.00 | $275.00 | $222.52 | $350.00 | $318.00 | $415.00 |
| 4 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 735 | $163.00 | $285.00 | $235.96 | $375.00 | $330.00 | $430.00 |
| 5 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 20 | $163.00 | $310.00 | $235.96 | $370.00 | $354.00 | $430.00 |
| 6 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 94 | $193.00 | $330.00 | $279.64 | $390.00 | $378.00 | $475.00 |
| 7 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 6 | $193.00 | $360.00 | $405.84 | $380.00 | $414.00 | $460.00 |
| 8 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 109 | $193.00 | $360.00 | $262.84 | $380.00 | $414.00 | $460.00 |
| 9 | Luminaire, misc.: luminaire, conventional, solid S (625E27600) | EACH | 50 | $192.50 | $275.00 | $208.85 | $320.00 | $348.00 | $50.00 |
| 10 | Power service, as per plan (625E34001) | EACH | 12 | $13,772 | $15,500 | $24,767 | $10,125 | $17,930 | $17,500 |
| 11 | Special - maintain existing lighting (625E40000) | LS | 1 | $12,540 | $550.00 | $14,376 | $20,000 | $43,200 | $17,500 |
| 12 | Luminaire removed (625E75506) | EACH | 1,041 | $27.00 | $35.00 | $43.50 | $85.00 | $30.00 | $260.00 |
| 13 | Arc flash calculations and label (per S.S. 825) (625E76000) | EACH | 12 | $1,713.00 | $4,400.00 | $286.00 | $1,925.00 | $4,320.00 | $500.00 |
| 14 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 150 | $77.00 | $77.00 | $84.00 | $95.00 | $100.00 | $75.00 |
| 15 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,890.00 | $6,070.00 | $7,952.00 | $3,825.00 | $4,560.00 | $7,188.86 |
| 16 | Maintaining traffic (614E11000) | LS | 1 | $3,978.00 | $32,500 | $36,192 | $20,000 | $65,400 | $15,500 |
| 17 | Mobilization (624E10000) | LS | 1 | $8,033.00 | $20,000 | $38,416 | $55,000 | $20,136 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.