ODOT contract 250260 bid tabulation
RIC-US 42/SR 545-00.41/02.36 (CULVERT REPLACEMENT). Let by Ohio DOT on May 8, 2025, RIC. 3 bids received; low bid $370,071 by BCC Ohio Inc, -26% against the engineer's estimate of $500,000.
- Owner
- Ohio DOT
- Letting
- 08 MAY 2025
- Pay items
- 61
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BCC Ohio Inc | $370,071 | Low | -26% |
| 2 | Eclipse Co LLC | $410,454 | +11% | -18% |
| 3 | Adena Corporation | $439,207 | +19% | -12% |
Engineer's estimate: $500,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BCC Ohio Inc | 2. Eclipse Co LLC | 3. Adena Corporation |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,084.00 | $10,461 | $13,104 |
| 2 | Structure removed, as per plan (202E11001) | LS | 1 | $5,835.00 | $7,105.00 | $11,943 |
| 3 | Headwall removed (202E20010) | EACH | 3 | $645.00 | $917.00 | $504.48 |
| 4 | Pavement removed (202E23000) | SY | 460 | $8.83 | $29.00 | $27.34 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 108 | $10.32 | $23.00 | $3.53 |
| 6 | Pipe removed, over 24" diameter (202E35200) | FT | 37 | $55.78 | $45.00 | $30.57 |
| 7 | Catch basin removed (202E58100) | EACH | 1 | $516.00 | $1,555.00 | $947.75 |
| 8 | Fence removed (202E75000) | FT | 159 | $2.58 | $7.00 | $4.80 |
| 9 | Removal misc.: fence post (202E98100) | EACH | 4 | $12.90 | $89.00 | $23.87 |
| 10 | Excavation (203E10000) | CY | 67 | $12.90 | $24.00 | $19.00 |
| 11 | Embankment (203E20000) | CY | 522 | $36.35 | $37.00 | $29.87 |
| 12 | Subgrade compaction (204E10000) | SY | 517 | $3.87 | $2.00 | $2.95 |
| 13 | Grading mailbox approaches (209E80000) | EACH | 3 | $258.00 | $202.00 | $63.67 |
| 14 | Monument assembly, type C (623E38500) | EACH | 5 | $2,121.75 | $1,729.00 | $3,300.48 |
| 15 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,890.00 | $1,890.00 | $3,061.22 |
| 16 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,890.00 | $1,890.00 | $3,061.22 |
| 17 | Special - mailbox support system, single (690E50100) | EACH | 3 | $262.50 | $488.00 | $435.91 |
| 18 | Riprap, type D (601E11000) | SY | 8 | $959.61 | $576.00 | $762.85 |
| 19 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 80 | $106.80 | $77.00 | $96.36 |
| 20 | Rock channel protection, type B with filter (601E32100) | CY | 65 | $143.07 | $160.00 | $142.19 |
| 21 | Soil analysis test (659E00100) | EACH | 4 | $157.50 | $131.00 | $125.00 |
| 22 | Topsoil (659E00300) | CY | 141 | $71.70 | $68.00 | $32.09 |
| 23 | Seeding and mulching (659E10000) | SY | 1,269 | $5.02 | $5.00 | $4.33 |
| 24 | Repair seeding and mulching (659E14000) | SY | 63 | $5.02 | $3.00 | $1.00 |
| 25 | Inter-seeding (659E15000) | SY | 63 | $5.02 | $0.11 | $1.00 |
| 26 | Commercial fertilizer (659E20000) | TON | 0.17 | $1,312.53 | $719.41 | $1,512.59 |
| 27 | Lime (659E31000) | ACRE | 0.26 | $157.50 | $21.00 | $282.58 |
| 28 | Water (659E35000) | MGAL | 7.02 | $1.05 | $0.55 | $1.00 |
| 29 | Slope erosion protection mat, type B (670E00520) | SY | 171 | $2.62 | $3.00 | $2.54 |
| 30 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 |
| 31 | Aggregate drains (605E31100) | FT | 248 | $8.43 | $23.00 | $7.40 |
| 32 | 6" conduit, type C (611E01100) | FT | 8 | $61.07 | $142.00 | $21.12 |
| 33 | 12" conduit, type C (611E04600) | FT | 24 | $104.55 | $99.00 | $55.30 |
| 34 | 15" conduit, type C (611E06100) | FT | 130 | $111.74 | $96.00 | $63.31 |
| 35 | 24" conduit, type C (611E10600) | FT | 8 | $291.94 | $222.00 | $126.12 |
| 36 | 36" conduit, type A (611E16200) | FT | 85 | $235.24 | $278.00 | $461.47 |
| 37 | 36" conduit, type B (611E16400) | FT | 60 | $261.36 | $207.00 | $531.07 |
| 38 | Catch basin, no. 5 (611E98300) | EACH | 1 | $7,097.70 | $4,901.00 | $4,911.42 |
| 39 | Catch basin, no. 2-5 (611E98570) | EACH | 1 | $11,624 | $5,971.00 | $5,995.09 |
| 40 | Manhole, no. 3 (611E99574) | EACH | 2 | $8,742.30 | $4,601.00 | $3,901.22 |
| 41 | Pavement planing, asphalt concrete (3.0") (254E01000) | SY | 189 | $21.00 | $22.00 | $25.59 |
| 42 | Pavement planing, asphalt concrete (varies 0" to 3 (254E01000) | SY | 329 | $12.60 | $14.00 | $16.16 |
| 43 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 101 | $378.00 | $304.00 | $358.88 |
| 44 | Aggregate base (304E20000) | CY | 129 | $137.57 | $113.00 | $140.68 |
| 45 | Aggregate base (304E20000) | CY | 34 | $140.15 | $98.00 | $130.44 |
| 46 | Tack coat (407E10000) | GAL | 142 | $3.15 | $16.00 | $21.05 |
| 47 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E22001) | CY | 85 | $483.00 | $341.00 | $402.45 |
| 48 | Compacted aggregate (617E10100) | CY | 3 | $218.10 | $196.00 | $50.00 |
| 49 | Raised pavement marker removed (621E54000) | EACH | 4 | $20.64 | $11.00 | $20.00 |
| 50 | Edge line, 6", type 1 (642E00104) | MI | 0.16 | $5,250.00 | $5,251.38 | $11,045 |
| 51 | Center line, type 1 (642E00300) | MI | 0.08 | $7,350.00 | $7,351.88 | $21,355 |
| 52 | Detour signing (614E12420) | LS | 1 | $6,972.00 | $11,800 | $12,207 |
| 53 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $892.50 | $1,160.00 | $1,088.57 |
| 54 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $1,452.00 | $9,441.00 | $11,208 |
| 55 | Concrete masonry (602E20000) | CY | 1.77 | $3,258.64 | $2,135.00 | $1,407.12 |
| 56 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $1,452.00 | $9,546.00 | $11,208 |
| 57 | Concrete masonry (602E20000) | CY | 0.94 | $3,247.66 | $3,201.03 | $1,731.21 |
| 58 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,482.43 | $5,910.00 | $7,935.60 |
| 59 | Maintaining traffic (614E11000) | LS | 1 | $4,540.50 | $7,932.00 | $14,683 |
| 60 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,180.00 | $6,302.00 | $17,631 |
| 61 | Mobilization (624E10000) | LS | 1 | $19,452 | $52,058 | $14,167 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 8, 2025. Compiled by Mirage Metrics.