ODOT contract 250317 bid tabulation

MED-US 42-03.10 L Reconstr. (BRIDGE REPAIR). Let by Ohio DOT on June 12, 2025, MED. 4 bids received; low bid $875,141 by J D Williamson Construction Co Inc, -12% against the engineer's estimate of $1,000,000.

Owner
Ohio DOT
Letting
12 JUN 2025
Pay items
35
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1J D Williamson Construction Co Inc$875,141Low-12%
2Ohio Concrete Maintenance LLC$1,003,987+15%0.0%
3Ruhlin Company$1,022,248+17%+2.0%
4Great Lakes Construction Co$1,144,369+31%+14%
ODOT contract 250317: bids by rank

Engineer's estimate: $1,000,000.

Bid tabulation

LinePay itemUnitQuantity1. J D Williamson Construction Co Inc2. Ohio Concrete Maintenance LLC3. Ruhlin Company4. Great Lakes Construction Co
1Erosion control (832E30000)EACH1,000$1.00$1.00$1.00$1.00
2Edge line, 6" (646E10010)MI0.03$100,000$120,000$41,000$99,880
3Lane line, 6" (646E10110)MI0.03$33,000$40,000$20,000$32,885
4Removal of pavement marking (646E50300)MI0.03$77,000$85,000$126,500$76,655
5Detour signing (614E12420)LS1$20,000$12,000$14,000$10,850
6Portable changeable message sign, as per plan (614E18601)SNMT12$800.00$1,200.00$750.00$720.00
7Barrier, misc.: anchor hole repair (622E90100)LS1$2,000.00$5,000.00$2,300.00$3,500.00
8Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$99,500$133,000$170,000$213,500
9Epoxy coated reinforcing steel, as per plan (509E10001)LB21,193$2.40$2.50$2.60$2.50
10Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001)LB340$2.75$6.00$4.25$5.00
11No. 4 deformed GFRP reinforcement (509E30020)FT1,646$2.25$4.00$2.60$2.50
12Class QC2 concrete, bridge deck (511E34444)CY66$1,200.00$1,490.00$1,550.00$2,100.00
13Class QC2 concrete, bridge deck (parapet) (511E34448)CY19$1,000.00$2,290.00$1,280.00$1,900.00
14Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY140$30.00$40.00$40.00$35.00
15Structural steel members, level 3 (513E10260)LB40,400$4.30$5.00$5.20$5.00
16Surface preparation of existing structural steel (514E00050)SF160$175.00$240.00$175.00$175.00
17Field painting of existing structural steel, prime coat (514E00056)SF160$26.00$175.00$25.00$25.00
18Field painting structural steel, intermediate coat (514E00060)SF2,690$26.00$26.00$25.00$25.00
19Field painting structural steel, finish coat, as per plan (514E00067)SF2,690$13.50$26.00$13.00$13.00
20Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR1$1.00$150.00$1.00$1.00
21Final inspection repair (514E10000)EACH3$1.00$150.00$1.00$1.00
22Structural expansion joint including elastomeric strip seal, as per plan (516E11211)FT33$1,300.00$1,300.00$1,200.00$1,250.00
23Elastomeric bearing with internal laminates and load plate, as per plan (516E44001)EACH3$1,800.00$2,300.00$1,675.00$1,500.00
24Elastomeric bearing with internal laminates and load plate, as per plan (516E44001)EACH1$1,800.00$2,300.00$1,775.00$1,500.00
25Elastomeric bearing with internal laminates and load plate, as per plan (516E44001)EACH1$1,800.00$2,300.00$1,785.00$1,500.00
26Elastomeric bearing with internal laminates and load plate, as per plan (516E44001)EACH5$1,800.00$2,300.00$1,750.00$1,500.00
27Elastomeric bearing with internal laminates and load plate, as per plan (516E44001)EACH5$1,800.00$2,300.00$1,685.00$1,500.00
28Refurbish bearing device, as per plan (516E45305)EACH2$1,500.00$1,800.00$3,100.00$6,000.00
29Jacking and temporary support of superstructure, as per plan (516E47001)LS1$62,000$40,000$50,000$55,000
30Scuppers, including supports (518E12200)EACH2$3,700.00$3,750.00$5,200.00$3,500.00
31Premium for contract performance bond and for payment bond (103E05000)LS1$12,000$18,000$3,000.00$14,000
32Maintaining traffic (614E11000)LS1$52,000$20,000$62,500$85,000
33Field office, type B (619E16010)MNTH4$2,600.00$2,200.00$3,600.00$4,500.00
34Construction layout stakes and surveying (623E10000)LS1$10,000$4,000.00$20,000$14,000
35Mobilization (624E10000)LS1$40,000$34,000$51,112$57,225
ODOT contract 250317: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of June 12, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy