ODOT contract 250341 bid tabulation
BEL-IR 70-10.08 (CULVERT REPLACEMENT). Let by Ohio DOT on July 17, 2025, BEL. 4 bids received; low bid $349,000 by Ohio-West Virginia Excavating Co.
- Owner
- Ohio DOT
- Letting
- 17 JUL 2025
- Pay items
- 30
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ohio-West Virginia Excavating Co | $349,000 | Low |
| 2 | LMS Construction Inc | $374,838 | +7.0% |
| 3 | Axis Civil Construction LLC | $407,927 | +17% |
| 4 | Stanley Miller Construction Company | $623,880 | +79% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohio-West Virginia Excavating Co | 2. LMS Construction Inc | 3. Axis Civil Construction LLC | 4. Stanley Miller Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $16,000 | $10,000 | $45,000 | $14,222 |
| 2 | Special - pipe cleanout over 48" (202E70130) | FT | 284 | $32.00 | $190.00 | $90.00 | $337.00 |
| 3 | Fence removed (202E75000) | FT | 84 | $4.40 | $6.00 | $10.00 | $20.00 |
| 4 | Excavation (203E10000) | CY | 5 | $93.00 | $500.00 | $100.00 | $500.00 |
| 5 | Embankment (203E20000) | CY | 1 | $575.00 | $1,000.00 | $300.00 | $1,000.00 |
| 6 | Fence, type 47 (607E15000) | FT | 117 | $62.00 | $35.00 | $49.50 | $65.00 |
| 7 | Riprap, type D, as per plan (601E11001) | SY | 76 | $385.00 | $250.00 | $450.00 | $250.00 |
| 8 | Rock channel protection, type A with aggregate filter (601E32010) | CY | 236 | $158.00 | $200.00 | $235.00 | $300.00 |
| 9 | Soil analysis test (659E00100) | EACH | 2 | $375.00 | $50.00 | $150.00 | $150.00 |
| 10 | Topsoil (659E00300) | CY | 80 | $80.00 | $10.00 | $90.00 | $100.00 |
| 11 | Seeding and mulching (659E10000) | SY | 717 | $5.00 | $3.00 | $4.00 | $10.00 |
| 12 | Repair seeding and mulching (659E14000) | SY | 36 | $5.00 | $3.00 | $4.00 | $5.00 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.10 | $1,600.00 | $3,000.00 | $1,250.00 | $800.00 |
| 14 | Lime (659E31000) | ACRE | 0.15 | $200.00 | $3,000.00 | $150.00 | $150.00 |
| 15 | Water (659E35000) | MGAL | 5 | $1.00 | $10.00 | $1.00 | $1.00 |
| 16 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 17 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $68,000 | $62,500 | $38,000 | $60,000 |
| 18 | Field paving of existing pipe, as per plan, 84" CO (611E96551) | FT | 284 | $220.00 | $300.00 | $185.00 | $363.00 |
| 19 | Special - work zone guardrail (614E12200) | FT | 100 | $74.55 | $35.00 | $78.00 | $100.00 |
| 20 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 2 | $3,525.00 | $2,300.00 | $3,200.00 | $5,000.00 |
| 21 | Asphalt concrete for maintaining traffic (614E13000) | CY | 15 | $1,015.00 | $150.00 | $240.00 | $200.00 |
| 22 | Barrier reflector, type 1, (one-way) (614E13310) | EACH | 18 | $25.00 | $20.00 | $20.00 | $35.00 |
| 23 | Object marker, one way (614E13350) | EACH | 18 | $38.00 | $20.00 | $27.00 | $50.00 |
| 24 | Water (616E10000) | MGAL | 5 | $12.50 | $10.00 | $1.00 | $1.00 |
| 25 | Portable barrier, unanchored (622E41100) | FT | 940 | $34.00 | $25.00 | $28.00 | $67.00 |
| 26 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,015.00 | $14,500 | $5,000.00 | $12,000 |
| 27 | Maintaining traffic (614E11000) | LS | 1 | $6,600.00 | $4,000.00 | $35,000 | $35,000 |
| 28 | Field office, type A (619E16000) | MNTH | 2 | $4,000.00 | $1,500.00 | $2,800.00 | $3,000.00 |
| 29 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,000.00 | $500.00 | $3,500.00 | $22,000 |
| 30 | Mobilization (624E10000) | LS | 1 | $16,609 | $23,300 | $40,000 | $65,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 17, 2025. Compiled by Mirage Metrics.