ODOT contract 250349 bid tabulation
SUM-SR 21-19.57/VAR (TWO LANE RESURFACING). Let by Ohio DOT on July 17, 2025, SUM. 8 bids received; low bid $811,775 by Kenmore Construction Co Inc.
- Owner
- Ohio DOT
- Letting
- 17 JUL 2025
- Pay items
- 47
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Kenmore Construction Co Inc | $811,775 | Low |
| 2 | Ronyak Paving Inc | $872,940 | +8.0% |
| 3 | Shelly & Sands Inc | $908,409 | +12% |
| 4 | Karvo Companies Inc | $984,017 | +21% |
| 5 | Shelly Company | $999,779 | +23% |
| 6 | Cook Paving & Construction Co Inc | $1,043,925 | +29% |
| 7 | Kokosing Construction Company Inc | $1,078,184 | +33% |
| 8 | Barbicas Construction Company Inc | $1,333,305 | +64% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kenmore Construction Co Inc | 2. Ronyak Paving Inc | 3. Shelly & Sands Inc | 4. Karvo Companies Inc | 5. Shelly Company | 6. Cook Paving & Construction Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Excavation (203E10000) | CY | 20 | $40.00 | $35.00 | $100.00 | $25.00 | $40.00 | $50.00 |
| 2 | Linear grading (209E60200) | STA | 31 | $150.00 | $50.00 | $150.00 | $225.00 | $150.00 | $375.00 |
| 3 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 5 | $1,500.00 | $1,550.00 | $185.00 | $1,125.00 | $1,200.00 | $925.00 |
| 4 | Special - as-built construction plans (690E20010) | LS | 1 | $3,000.00 | $1,000.00 | $2,000.00 | $800.00 | $8,000.00 | $1,500.00 |
| 5 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 6 | Catch basin adjusted to grade (611E98630) | EACH | 18 | $400.00 | $1,000.00 | $2,200.00 | $1,600.00 | $1,200.00 | $1,500.00 |
| 7 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 11 | $1,800.00 | $1,100.00 | $1,900.00 | $1,200.00 | $1,500.00 | $1,100.00 |
| 8 | Special - miscellaneous metal (611E99820) | LB | 400 | $3.50 | $4.00 | $5.00 | $2.00 | $5.00 | $2.00 |
| 9 | Partial depth pavement repair (441) (251E01000) | SY | 700 | $45.00 | $40.00 | $37.00 | $40.00 | $38.20 | $65.00 |
| 10 | Partial depth pavement repair (441) (251E01000) | SY | 150 | $50.00 | $65.00 | $85.00 | $75.00 | $83.00 | $75.00 |
| 11 | Pavement repair (253E01000) | SY | 250 | $120.00 | $115.00 | $140.00 | $125.00 | $120.00 | $160.00 |
| 12 | Pavement planing, asphalt concrete (T=1.5") (254E01000) | SY | 48,772 | $1.60 | $1.75 | $1.00 | $1.85 | $2.25 | $2.00 |
| 13 | Full depth pavement removal and rigid replacement, type 2, class QC RS (255E19100) | SY | 100 | $250.00 | $375.00 | $535.00 | $200.00 | $350.00 | $350.00 |
| 14 | Aggregate base (304E20000) | CY | 20 | $40.00 | $60.00 | $50.00 | $25.00 | $60.00 | $50.00 |
| 15 | Non-tracking tack coat, as per plan (407E20001) | GAL | 3,902 | $5.00 | $2.00 | $3.05 | $2.75 | $2.50 | $4.00 |
| 16 | Prime coat, as per plan (408E10001) | GAL | 733 | $5.00 | $2.00 | $3.50 | $6.50 | $5.00 | $4.00 |
| 17 | Asphalt concrete surface course, type 1, (448), PG70-22M (441E50100) | CY | 2,033 | $207.00 | $210.00 | $215.00 | $225.00 | $212.00 | $260.00 |
| 18 | Compacted aggregate, as per plan (617E10101) | CY | 51 | $100.00 | $180.00 | $150.00 | $150.00 | $150.00 | $200.00 |
| 19 | Valve box adjusted to grade, as per plan (638E10801) | EACH | 5 | $1,500.00 | $875.00 | $1,250.00 | $1,125.00 | $1,000.00 | $925.00 |
| 20 | Barrier reflector, type 2 (one-way) (626E00110) | EACH | 6 | $20.00 | $40.00 | $37.75 | $37.75 | $50.00 | $40.00 |
| 21 | Edge line, 6" (646E10010) | MI | 2.32 | $3,150.00 | $3,150.00 | $3,750.00 | $3,750.00 | $3,150.00 | $4,000.00 |
| 22 | Lane line, 6" (646E10110) | MI | 2.21 | $1,745.00 | $1,745.00 | $1,650.00 | $1,650.00 | $1,745.00 | $1,900.00 |
| 23 | Center line (646E10200) | MI | 1.55 | $3,400.00 | $3,400.00 | $3,850.00 | $3,850.00 | $3,400.00 | $4,000.00 |
| 24 | Channelizing line, 12" (646E10310) | FT | 1,575 | $1.52 | $1.52 | $2.25 | $2.25 | $1.55 | $2.50 |
| 25 | Stop line (646E10400) | FT | 214 | $12.00 | $12.00 | $12.50 | $12.50 | $12.00 | $14.00 |
| 26 | Crosswalk line, 24" (646E10520) | FT | 88 | $14.00 | $14.00 | $10.00 | $10.00 | $14.00 | $11.00 |
| 27 | Transverse/diagonal line (646E10600) | FT | 10 | $14.00 | $14.00 | $12.50 | $12.50 | $14.00 | $14.00 |
| 28 | Island marking (646E10800) | SF | 57 | $12.00 | $12.00 | $10.00 | $10.00 | $12.00 | $11.00 |
| 29 | Lane arrow (646E20300) | EACH | 32 | $155.00 | $155.00 | $175.00 | $175.00 | $155.00 | $200.00 |
| 30 | Dotted line, 6" (646E20504) | FT | 70 | $3.75 | $3.75 | $2.25 | $2.25 | $3.75 | $2.50 |
| 31 | Law enforcement officer for assistance (614E11130) | HR | 150 | $85.00 | $100.00 | $95.00 | $100.00 | $100.00 | $85.00 |
| 32 | Work zone marking sign (614E12460) | EACH | 25 | $150.00 | $85.00 | $85.00 | $85.00 | $65.00 | $100.00 |
| 33 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $200.00 | $245.00 | $500.00 | $200.00 | $120.00 | $145.00 |
| 34 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 2.21 | $555.00 | $555.00 | $750.00 | $750.00 | $555.00 | $850.00 |
| 35 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 2.21 | $555.00 | $555.00 | $675.00 | $675.00 | $555.00 | $750.00 |
| 36 | Work zone center line, class I, 642 paint (614E21100) | MI | 1.55 | $1,200.00 | $1,200.00 | $1,500.00 | $1,500.00 | $1,200.00 | $1,700.00 |
| 37 | Work zone center line, class III, 642 paint (614E21550) | MI | 1.55 | $1,100.00 | $1,100.00 | $1,250.00 | $1,250.00 | $1,100.00 | $1,400.00 |
| 38 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 2.32 | $588.00 | $588.00 | $750.00 | $750.00 | $588.00 | $850.00 |
| 39 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 1,575 | $0.65 | $0.65 | $0.75 | $0.75 | $0.65 | $0.75 |
| 40 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 1,575 | $0.60 | $0.60 | $0.75 | $0.75 | $0.60 | $0.75 |
| 41 | Work zone stop line, class I, 642 paint (614E26200) | FT | 214 | $3.25 | $3.25 | $3.50 | $3.50 | $3.25 | $3.50 |
| 42 | Work zone stop line, class III, 642 paint (614E26610) | FT | 214 | $3.00 | $3.00 | $3.50 | $3.50 | $3.00 | $3.50 |
| 43 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $6,398.54 | $3,000.00 | $18,000 | $5,000.00 | $5,000.00 |
| 44 | Maintaining traffic (614E11000) | LS | 1 | $35,000 | $64,420 | $78,471 | $80,000 | $162,500 | $70,000 |
| 45 | Field office, type B (619E16010) | MNTH | 6 | $3,500.00 | $2,000.00 | $3,500.00 | $2,500.00 | $2,000.00 | $1,500.00 |
| 46 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,000.00 | $2,995.00 | $2,000.00 | $1,500.00 | $8,000.00 | $5,000.00 |
| 47 | Mobilization (624E10000) | LS | 1 | $15,000 | $41,942 | $20,000 | $78,165 | $20,000 | $35,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 17, 2025. Compiled by Mirage Metrics.