ODOT contract 250384 bid tabulation
WAY-BH FY2026 (CULVERT REPLACEMENT). Let by Ohio DOT on August 14, 2025, WAY. 3 bids received; low bid $456,525 by Ohio Concrete Maintenance LLC, +1.9% against the engineer's estimate of $448,000.
- Owner
- Ohio DOT
- Letting
- 14 AUG 2025
- Pay items
- 39
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ohio Concrete Maintenance LLC | $456,525 | Low | +2.0% |
| 2 | Stanley Miller Construction Company | $749,277 | +64% | +67% |
| 3 | Madex Construction Co | $954,301 | +109% | +113% |
Engineer's estimate: $448,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohio Concrete Maintenance LLC | 2. Stanley Miller Construction Company | 3. Madex Construction Co |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $10,000 | $4,321.60 |
| 2 | Soil analysis test (659E00100) | EACH | 8 | $500.00 | $150.00 | $147.37 |
| 3 | Topsoil (659E00300) | CY | 862 | $45.00 | $55.00 | $34.74 |
| 4 | Seeding and mulching (659E10000) | SY | 7,751 | $3.00 | $3.20 | $3.47 |
| 5 | Repair seeding and mulching (659E14000) | SY | 389 | $6.00 | $1.00 | $3.47 |
| 6 | Inter-seeding (659E15000) | SY | 389 | $5.00 | $1.00 | $3.47 |
| 7 | Commercial fertilizer (659E20000) | TON | 1.11 | $1,100.00 | $800.00 | $1,564.72 |
| 8 | Lime (659E31000) | ACRE | 1.62 | $1,100.00 | $150.00 | $859.26 |
| 9 | Water (659E35000) | MGAL | 45 | $20.00 | $1.00 | $28.95 |
| 10 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 |
| 11 | Guardrail removed for reuse, as per plan (202E38201) | FT | 75 | $20.00 | $40.00 | $106.74 |
| 12 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 24 | $120.00 | $225.00 | $115.79 |
| 13 | Increased barrier delineation (614E11630) | FT | 710 | $2.00 | $10.00 | $4.63 |
| 14 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 3 | $500.00 | $7,000.00 | $3,473.68 |
| 15 | Barrier reflector, type 1 (1WAY) (614E13310) | EACH | 15 | $20.00 | $30.00 | $34.74 |
| 16 | Object marker, one way (614E13350) | EACH | 15 | $20.00 | $30.00 | $40.53 |
| 17 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.25 | $5,000.00 | $10,000 | $5,789.48 |
| 18 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 496 | $3.00 | $10.00 | $4.63 |
| 19 | Portable barrier, unanchored (622E41100) | FT | 710 | $20.00 | $60.00 | $91.05 |
| 20 | Special - pipe cleanout over 48" (202E70130) | FT | 140 | $42.00 | $105.00 | $48.90 |
| 21 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $11,000 | $12,000 | $26,829 |
| 22 | Field paving of existing pipe, as per plan (186" X (611E96551) | FT | 140 | $238.00 | $428.00 | $707.50 |
| 23 | Conduit, misc.: waterblast and paint (611E97500) | SY | 7 | $150.00 | $1,000.00 | $578.95 |
| 24 | Special - pipe cleanout over 48" (202E70130) | FT | 198 | $42.00 | $105.00 | $48.90 |
| 25 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $11,000 | $10,000 | $33,579 |
| 26 | Field paving of existing pipe, as per plan (120" X (611E96551) | FT | 198 | $230.00 | $300.00 | $512.77 |
| 27 | Special - pipe cleanout over 48" (202E70130) | FT | 90 | $295.00 | $300.00 | $48.90 |
| 28 | Excavation (203E10000) | CY | 6 | $975.00 | $300.00 | $173.68 |
| 29 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $11,000 | $10,000 | $26,764 |
| 30 | Field paving of existing pipe, as per plan (161" X (611E96551) | FT | 90 | $270.00 | $360.00 | $675.79 |
| 31 | Special - pipe cleanout over 48" (202E70130) | FT | 228 | $42.00 | $95.00 | $48.90 |
| 32 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $11,000 | $10,000 | $38,211 |
| 33 | Field paving of existing pipe, as per plan (168" D (611E96551) | FT | 228 | $235.00 | $385.00 | $693.35 |
| 34 | Conduit, misc.: waterblast and paint (611E97500) | SY | 70 | $50.00 | $500.00 | $57.90 |
| 35 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $20,000 | $18,000 | $41,548 |
| 36 | Maintaining traffic (614E11000) | LS | 1 | $20,000 | $40,000 | $87,895 |
| 37 | Field office, type B (619E16010) | MNTH | 4 | $1,000.00 | $1,000.00 | $857.89 |
| 38 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,000.00 | $5,000.00 | $14,579 |
| 39 | Mobilization (624E10000) | LS | 1 | $24,000 | $90,000 | $47,271 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.