ODOT contract 250405 bid tabulation
BUT-SR 122-06.50R (CULVERT REPLACEMENT). Let by Ohio DOT on September 11, 2025, BUT. 4 bids received; low bid $1,093,394 by Temple & Temple Excavating & Paving Inc, -8.9% against the engineer's estimate of $1,200,000.
- Owner
- Ohio DOT
- Letting
- 11 SEP 2025
- Pay items
- 14
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Temple & Temple Excavating & Paving Inc | $1,093,394 | Low | -9.0% |
| 2 | Brumbaugh Construction Inc | $1,151,167 | +5.0% | -4.0% |
| 3 | Axis Civil Construction LLC | $1,268,000 | +16% | +6.0% |
| 4 | Sunesis Construction Co | $1,437,264 | +31% | +20% |
Engineer's estimate: $1,200,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Temple & Temple Excavating & Paving Inc | 2. Brumbaugh Construction Inc | 3. Axis Civil Construction LLC | 4. Sunesis Construction Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $7,500.00 | $20,000 | $25,000 | $35,119 |
| 2 | Special - pipe cleanout over 48" (202E70130) | FT | 393 | $45.00 | $270.00 | $100.00 | $265.50 |
| 3 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $50,000 | $200,000 | $135,000 | $455,599 |
| 4 | Topsoil (659E00300) | CY | 290 | $75.00 | $65.00 | $55.00 | $125.83 |
| 5 | Seeding and mulching (659E10000) | SY | 2,613 | $3.00 | $2.00 | $3.20 | $4.48 |
| 6 | Commercial fertilizer (659E20000) | TON | 0.35 | $1,800.00 | $600.00 | $690.00 | $1,555.11 |
| 7 | Lime (659E31000) | ACRE | 0.54 | $250.00 | $100.00 | $70.00 | $499.85 |
| 8 | Water (659E35000) | MGAL | 14.10 | $20.00 | $5.00 | $1.00 | $50.00 |
| 9 | Erosion control (832E30000) | EACH | 20,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 10 | Liner pipe, 132" 707.35, 707.75, 748.06, 707.18 (837E10000) | FT | 393 | $1,756.00 | $990.00 | $1,990.00 | $1,413.36 |
| 11 | Backfill for liner pipe (837E21000) | FT | 393 | $505.00 | $670.00 | $425.00 | $430.56 |
| 12 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $14,500 | $8,500.00 | $10,000 | $8,323.81 |
| 13 | Maintaining traffic (614E11000) | LS | 1 | $12,500 | $69,767 | $25,000 | $8,109.10 |
| 14 | Mobilization (624E10000) | LS | 1 | $52,000 | $50,000 | $40,000 | $31,395 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 11, 2025. Compiled by Mirage Metrics.