ODOT contract 250505 bid tabulation

WAR-SR 123-00.05 River St (TWO LANE RESURFACING). Let by Ohio DOT on November 13, 2025, WAR. 3 bids received; low bid $768,742 by Fillmore Construction, -26% against the engineer's estimate of $1,043,000.

Owner
Ohio DOT
Letting
13 NOV 2025
Pay items
41
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Fillmore Construction$768,742Low-26%
2Barrett Paving Materials Inc$785,484+2.0%-25%
3John R Jurgensen Company$1,063,957+38%+2.0%
ODOT contract 250505: bids by rank

Engineer's estimate: $1,043,000.

Bid tabulation

LinePay itemUnitQuantity1. Fillmore Construction2. Barrett Paving Materials Inc3. John R Jurgensen Company
1Walk removed (202E30000)SF1,458$5.00$8.00$7.00
2Curb removed (202E32000)FT243$10.00$22.00$22.00
3Curb and gutter removed (202E32500)FT135$10.00$25.00$25.00
44" concrete walk (608E10000)SF140$20.00$15.00$12.50
5Curb ramp, as per plan (608E52001)SF1,600$30.00$30.00$28.00
6Combination curb and gutter, type 2 (609E12000)FT197$50.00$55.00$51.75
7Curb, type 6 (609E26000)FT244$50.00$50.00$48.00
8Erosion control (832E30000)EACH10,000$1.00$1.00$1.00
94" conduit, type F (611E00406)FT11$80.00$85.00$108.25
10Catch basin reconstructed to grade (611E98634)EACH20$2,500.00$2,100.00$2,542.86
11Manhole adjusted to grade (611E99654)EACH3$1,000.00$1,300.00$1,207.27
12Valve box adjusted to grade (638E10800)EACH13$500.00$900.00$704.91
13Pavement repair, as per plan (253E02001)CY54$300.00$340.00$581.99
14Pavement repair, as per plan (253E02001)CY797$400.00$332.00$607.20
15Pavement planing, asphalt concrete, as per plan, 3 (254E01001)SY9,422$2.00$4.15$3.90
16Patching planed surface (254E01600)SY944$5.00$9.00$4.50
17Non-tracking tack coat (407E20000)GAL1,414$3.00$4.50$5.00
18Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY330$240.00$272.00$291.72
19Asphalt concrete intermediate course, type 2, (448) (441E50300)CY461$228.00$268.00$291.15
20Ground mounted support, no. 3 post (630E03100)FT76$15.50$15.50$15.50
21Sign, flat sheet (630E80100)SF28$16.00$16.00$16.00
22Lane line, 4" (644E00200)MI0.39$3,179.00$2,200.00$2,200.00
23Channelizing line, 8" (644E00400)FT276$2.31$3.00$3.00
24Stop line (644E00500)FT112$10.56$10.00$10.00
25Crosswalk line, 12" (644E00620)FT324$5.28$5.00$5.00
26Lane arrow (644E01300)EACH6$214.00$157.00$157.00
27Law enforcement officer with patrol car for assistance (614E11110)HR8$100.00$95.00$138.97
28Work zone lane line, class I, 4" (614E20000)MI0.39$2,420.00$925.00$925.00
29Work zone lane line, class III, 4", 642 paint (614E20550)MI0.39$2,420.00$925.00$925.00
30Work zone channelizing line, class I, 8" (614E23000)FT276$0.84$1.75$1.75
31Work zone channelizing line, class III, 8", 642 paint (614E23680)FT276$0.84$1.75$1.75
32Work zone stop line, class I (614E26000)FT112$6.00$5.75$5.75
33Work zone stop line, class III, 642 paint (614E26610)FT112$6.00$5.75$5.75
34Work zone crosswalk line, class I, 12" (614E27010)FT324$3.00$2.90$2.90
35Work zone crosswalk line, class III, 12", 642 paint (614E27250)FT324$3.00$2.90$2.90
36Work zone arrow, class I (614E30000)EACH6$59.00$69.00$69.00
37Work zone arrow, class III, 642 paint (614E30650)EACH6$59.00$69.00$69.00
38Premium for contract performance bond and for payment bond (103E05000)LS1$7,500.00$1,760.00$5,030.95
39Maintaining traffic (614E11000)LS1$30,000$20,000$35,967
40Construction layout stakes and surveying (623E10000)LS1$1,500.00$2,000.00$3,036.11
41Mobilization (624E10000)LS1$13,500$36,000$50,000
ODOT contract 250505: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy