ODOT contract 250538 bid tabulation

AUG-GLSM East Bank CR (CULVERT REPLACEMENT). Let by Ohio DOT on November 13, 2025, AUG. 4 bids received; low bid $115,201 by Advanced Excavating & Demolition LLC, -15% against the engineer's estimate of $135,000.

Owner
Ohio DOT
Letting
13 NOV 2025
Pay items
20
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Advanced Excavating & Demolition LLC$115,201Low-15%
2Brumbaugh Construction Inc$116,140+1.0%-14%
3R B Jergens Contractors Inc$123,307+7.0%-9.0%
4Eagle Bridge Co$166,139+44%+23%
ODOT contract 250538: bids by rank

Engineer's estimate: $135,000.

Bid tabulation

LinePay itemUnitQuantity1. Advanced Excavating & Demolition LLC2. Brumbaugh Construction Inc3. R B Jergens Contractors Inc4. Eagle Bridge Co
1Pavement removed (202E23000)SY42$18.00$20.00$98.63$25.00
2Walk removed, as per plan (202E30001)SF48$15.00$10.00$27.49$15.00
3Pipe removed, over 24" diameter (202E35200)FT70$30.00$55.00$94.22$35.00
6Subgrade compaction (204E10000)SY29$5.00$5.00$44.79$20.00
76" concrete walk (608E13000)SF60$62.00$30.00$28.60$40.00
8Crushed aggregate slope protection, as per plan (601E20001)SY9$160.00$20.00$117.67$150.00
9Crushed aggregate slope protection, as per plan (601E20001)SY3$365.00$25.00$176.80$175.00
10Seeding and mulching, class 1, as per plan (659E00501)SY43$30.00$25.00$82.20$35.00
11Concrete masonry (602E20000)CY1.09$2,500.00$3,000.00$3,597.61$3,000.00
1248" conduit, type A, as per plan,707.34, (HDPE) (611E20701)FT67$525.00$800.00$708.59$925.00
13Conduit, misc.:, pipe sealing system (611E97200)EACH1$6,000.00$2,000.00$3,497.01$5,000.00
14Asphalt concrete base, PG64-22, (449) (301E56000)CY4$570.00$631.00$741.79$712.00
15Aggregate base (304E20000)CY5$100.00$90.00$161.68$300.00
16Aggregate base, as per plan (304E20001)CY5$180.00$90.00$161.68$650.00
17Non-tracking tack coat (407E20000)GAL21$5.00$7.00$15.90$5.50
18Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY1$1,250.00$1,992.50$1,324.62$600.00
19Maintaining traffic (614E11000)LS1$5,000.00$6,061.50$5,739.22$6,500.00
20Cofferdams and excavation bracing (503E11100)LS1$30,000$21,000$16,966$61,000
21Premium for contract performance bond and for payment bond (103E05000)LS1$5,000.00$1,200.00$5,793.38$2,000.00
22Mobilization (624E10000)LS1$15,000$15,000$13,476$7,500.00
ODOT contract 250538: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy