ODOT contract 254003 bid tabulation
BRO-SR 756-00.14 (CULVERT REPLACEMENT). Let by Ohio DOT on January 30, 2025, BRO. 4 bids received; low bid $294,156 by Alan Stone Co Inc, +9.4% against the engineer's estimate of $269,000.
- Owner
- Ohio DOT
- Letting
- 30 JAN 2025
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Alan Stone Co Inc | $294,156 | Low | +9.0% |
| 2 | Rack & Ballauer Excavating Co Inc | $335,100 | +14% | +25% |
| 3 | Axis Civil Construction LLC | $366,270 | +25% | +36% |
| 4 | R C Construction Company and Son Inc | $368,908 | +25% | +37% |
Engineer's estimate: $269,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alan Stone Co Inc | 2. Rack & Ballauer Excavating Co Inc | 3. Axis Civil Construction LLC | 4. R C Construction Company and Son Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $22,000 | $20,500 | $15,000 | $3,500.00 |
| 2 | Pavement removed (202E23000) | SY | 320 | $15.00 | $25.00 | $16.00 | $25.00 |
| 3 | Excavation (203E10000) | CY | 151 | $35.00 | $40.00 | $40.00 | $25.00 |
| 4 | Embankment (203E20000) | CY | 435 | $70.00 | $40.00 | $40.00 | $50.00 |
| 5 | Subgrade compaction (204E10000) | SY | 643 | $4.00 | $4.00 | $3.00 | $2.00 |
| 6 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $100.00 | $5,000.00 | $18,000 | $7,500.00 |
| 7 | Unclassified excavation (503E21300) | LS | 1 | $4,900.00 | $15,000 | $23,000 | $5,500.00 |
| 8 | Rock excavation (503E31100) | CY | 6 | $160.00 | $100.00 | $100.00 | $1,000.00 |
| 9 | Monument assembly, type C (623E38500) | EACH | 4 | $1,200.00 | $1,800.00 | $2,400.00 | $1,000.00 |
| 10 | Seeding and mulching (659E10000) | SY | 986 | $2.00 | $4.50 | $0.90 | $10.00 |
| 11 | Repair seeding and mulching (659E14000) | SY | 99 | $15.00 | $2.00 | $0.90 | $0.20 |
| 12 | Commercial fertilizer (659E20000) | TON | 0.09 | $660.00 | $1,500.00 | $1,250.00 | $1,900.00 |
| 13 | Lime (659E31000) | ACRE | 0.20 | $950.00 | $200.00 | $150.00 | $1,400.00 |
| 14 | Water (659E35000) | MGAL | 3 | $120.00 | $1.00 | $1.00 | $1.00 |
| 15 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Pipe removed, over 24", as per plan (202E35201) | FT | 11 | $35.00 | $60.00 | $200.00 | $200.00 |
| 17 | Special - fill and plug existing conduit (202E70000) | FT | 63 | $65.00 | $122.00 | $200.00 | $200.00 |
| 18 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 9 | $240.00 | $230.00 | $170.00 | $150.00 |
| 19 | Concrete masonry (602E20000) | CY | 2.20 | $3,500.00 | $2,300.00 | $2,600.00 | $1,800.00 |
| 20 | 48" conduit, type A, (for allowable material type (611E20700) | FT | 98 | $230.00 | $450.00 | $650.00 | $500.00 |
| 21 | Full depth pavement sawing (252E01500) | FT | 454 | $2.50 | $1.60 | $3.55 | $25.00 |
| 22 | Pavement repair (253E02000) | CY | 50 | $430.00 | $400.00 | $300.00 | $50.00 |
| 23 | Pavement planing, asphalt concrete (variable thick (254E01000) | SY | 409 | $25.00 | $17.00 | $9.00 | $25.00 |
| 24 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 62 | $35.00 | $260.00 | $350.00 | $400.00 |
| 25 | Aggregate base (304E20000) | CY | 67 | $90.00 | $95.00 | $130.00 | $150.00 |
| 26 | Tack coat (407E10000) | GAL | 291 | $5.50 | $5.00 | $4.00 | $10.00 |
| 27 | Stabilized crushed aggregate (411E10000) | CY | 44 | $95.00 | $150.00 | $150.00 | $150.00 |
| 28 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 163 | $370.00 | $385.00 | $280.00 | $400.00 |
| 29 | Aggregate drains (605E31100) | FT | 50 | $25.00 | $38.00 | $27.00 | $25.00 |
| 30 | RPM (621E00100) | EACH | 6 | $400.00 | $284.00 | $284.00 | $1,000.00 |
| 31 | Raised pavement marker removed (621E54000) | EACH | 6 | $40.00 | $10.00 | $50.00 | $50.00 |
| 32 | Edge line, 6", type 1 (642E00104) | MI | 0.12 | $13,000 | $10,850 | $10,850 | $25,000 |
| 33 | Center line, type 1 (642E00300) | MI | 0.06 | $16,000 | $13,640 | $13,640 | $35,000 |
| 34 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 8 | $110.00 | $75.00 | $65.00 | $20.00 |
| 35 | Detour signing (614E12420) | LS | 1 | $3,000.00 | $3,500.00 | $100.00 | $20,000 |
| 36 | Water (616E10000) | MGAL | 8 | $0.20 | $80.00 | $1.00 | $1.00 |
| 37 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,500.00 | $3,000.00 | $3,500.00 | $15,000 |
| 38 | Maintaining traffic (614E11000) | LS | 1 | $6,700.00 | $2,500.00 | $20,000 | $19,000 |
| 39 | Field office, type A (619E16000) | MNTH | 2 | $2,200.00 | $1,200.00 | $3,500.00 | $100.00 |
| 40 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,300.00 | $14,000 | $7,000.00 | $10,000 |
| 41 | Mobilization (624E10000) | LS | 1 | $34,000 | $30,000 | $30,000 | $12,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.