ODOT contract 260089 bid tabulation
MOT-GMR Trail IMP CR22A (BIKEWAYS). Let by Ohio DOT on February 19, 2026, MOT. 4 bids received; low bid $322,529 by L J Deweese Co Inc, -5.1% against the engineer's estimate of $340,000.
- Owner
- Ohio DOT
- Letting
- 19 FEB 2026
- Pay items
- 47
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | L J Deweese Co Inc | $322,529 | Low | -5.0% |
| 2 | Fillmore Construction | $367,505 | +14% | +8.0% |
| 3 | Sunesis Construction Co | $383,818 | +19% | +13% |
| 4 | Belgray, Inc | $393,232 | +22% | +16% |
Engineer's estimate: $340,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. L J Deweese Co Inc | 2. Fillmore Construction | 3. Sunesis Construction Co | 4. Belgray, Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,500.00 | $7,500.00 | $2,204.41 | $4,126.80 |
| 2 | Pavement removed (202E23000) | SY | 301 | $45.00 | $15.00 | $40.44 | $25.00 |
| 3 | Walk removed (202E30000) | SF | 947 | $5.00 | $5.00 | $6.61 | $6.00 |
| 4 | Curb removed (202E32000) | FT | 123 | $20.00 | $10.00 | $15.94 | $23.50 |
| 5 | Curb and gutter removed (202E32500) | FT | 86 | $20.00 | $10.00 | $21.94 | $23.00 |
| 6 | Subgrade compaction (204E10000) | SY | 170 | $1.00 | $10.00 | $29.81 | $21.50 |
| 7 | 4" concrete walk (608E10000) | SF | 144 | $25.00 | $20.00 | $57.56 | $13.50 |
| 8 | Curb ramp, as per plan (608E52001) | SF | 2,213 | $35.00 | $20.00 | $28.30 | $38.00 |
| 9 | Topsoil (659E00300) | CY | 33 | $100.00 | $75.00 | $111.56 | $115.00 |
| 10 | Seeding and mulching, class 1 (659E00500) | SY | 300 | $5.00 | $7.50 | $11.00 | $8.00 |
| 11 | Repair seeding and mulching (659E14000) | SY | 15 | $5.00 | $2.20 | $14.47 | $1.25 |
| 12 | Inter-seeding (659E15000) | SY | 15 | $5.00 | $2.20 | $0.72 | $1.25 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.04 | $1,000.00 | $2,000.00 | $1,302.00 | $1,000.00 |
| 14 | Lime (659E31000) | ACRE | 0.06 | $1,000.00 | $500.00 | $1.50 | $800.00 |
| 15 | Water (659E35000) | MGAL | 1.66 | $10.00 | $10.00 | $0.72 | $100.00 |
| 16 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 9 | $400.00 | $300.00 | $875.82 | $1,200.00 |
| 17 | Aggregate base (304E20000) | CY | 29 | $150.00 | $100.00 | $230.44 | $180.00 |
| 18 | Non-tracking tack coat (407E20000) | GAL | 12 | $50.00 | $10.00 | $80.35 | $25.00 |
| 19 | Stabilized crushed aggregate (411E10000) | CY | 43 | $150.00 | $100.00 | $1.76 | $250.00 |
| 20 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 6 | $900.00 | $500.00 | $969.76 | $3,150.00 |
| 21 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 6 | $900.00 | $500.00 | $843.24 | $3,150.00 |
| 22 | Combination curb and gutter, type 2 (609E12000) | FT | 86 | $75.00 | $50.00 | $65.15 | $100.00 |
| 23 | Curb, type 6 (609E26000) | FT | 147 | $75.00 | $40.00 | $48.86 | $65.00 |
| 24 | Low strength mortar backfill (613E41200) | CY | 9 | $400.00 | $300.00 | $240.71 | $160.00 |
| 25 | Valve box adjusted to grade (638E10800) | EACH | 1 | $500.00 | $750.00 | $424.52 | $250.00 |
| 26 | Ground mounted support, no. 3 post (630E03100) | FT | 434 | $16.00 | $20.00 | $15.88 | $16.00 |
| 27 | Sign post reflector (630E08600) | EACH | 10 | $67.00 | $75.00 | $66.29 | $67.00 |
| 28 | Sign support assembly, pole mounted (630E79500) | EACH | 4 | $140.00 | $200.00 | $135.20 | $136.00 |
| 29 | Sign, flat sheet (630E80100) | SF | 213 | $20.00 | $30.00 | $19.18 | $19.25 |
| 30 | Sign, street name (630E80510) | EACH | 1 | $300.00 | $25.00 | $296.14 | $297.00 |
| 31 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $75.00 | $100.00 | $74.92 | $75.00 |
| 32 | Removal of ground mounted sign and delivery (630E85200) | EACH | 37 | $24.00 | $50.00 | $23.02 | $25.00 |
| 33 | Removal of ground mounted post support and disposal (630E86002) | EACH | 18 | $31.00 | $50.00 | $30.69 | $31.00 |
| 34 | Signing, misc.:removal and reinstallation of bikew (630E97700) | EACH | 2 | $1,400.00 | $200.00 | $1,362.24 | $1,375.00 |
| 35 | Signing, misc.:solar-powered border-enhanced LED S (630E97700) | EACH | 3 | $2,400.00 | $9,350.00 | $2,320.05 | $2,325.00 |
| 36 | Signing, misc.:solar-powered rectangular rapid fla (630E97700) | EACH | 8 | $8,000.00 | $9,350.00 | $7,784.38 | $8,000.00 |
| 37 | Edge line, 6", type 1 (642E00104) | MI | 0.01 | $31,000 | $38,700 | $38,700 | $30,515 |
| 38 | Stop line, type 1 (642E00500) | FT | 51 | $9.00 | $1.50 | $1.50 | $8.15 |
| 39 | Crosswalk line, 24", type 1 (642E00630) | FT | 383 | $8.00 | $10.00 | $10.00 | $7.90 |
| 40 | Transverse/diagonal line, type 1 (642E00700) | FT | 23 | $8.00 | $10.00 | $10.00 | $7.65 |
| 41 | Removal of pavement marking (642E30000) | FT | 365 | $7.00 | $5.90 | $5.90 | $6.30 |
| 42 | Detour signing, as per plan (614E12421) | LS | 1 | $10,000 | $14,735 | $8,497.25 | $9,000.00 |
| 43 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,500.00 | $3,500.00 | $2,763.54 | $4,000.00 |
| 44 | Maintaining traffic (614E11000) | LS | 1 | $5,000.00 | $50,000 | $27,123 | $35,000 |
| 45 | Construction layout stakes and surveying (623E10000) | LS | 1 | $13,000 | $7,500.00 | $9,500.00 | $8,000.00 |
| 46 | Mobilization (624E10000) | LS | 1 | $7,500.00 | $30,000 | $63,677 | $10,000 |
| 100 | Erosion control (832E30000) | EACH | 30,000 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.