ODOT contract 260139 bid tabulation
ERI-/HUR TSG FY2026 (SIGNALIZATION). Let by Ohio DOT on March 12, 2026, ERI. 3 bids received; low bid $723,082 by Ruhlin Company, +0.3% against the engineer's estimate of $721,000.
- Owner
- Ohio DOT
- Letting
- 12 MAR 2026
- Pay items
- 63
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ruhlin Company | $723,082 | Low | 0.0% |
| 2 | Perram Electric Inc | $751,000 | +4.0% | +4.0% |
| 3 | Miller Cable Company | $945,100 | +31% | +31% |
Engineer's estimate: $721,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ruhlin Company | 2. Perram Electric Inc | 3. Miller Cable Company |
|---|---|---|---|---|---|---|
| 1 | Guardrail removed (202E38000) | FT | 37.50 | $4.80 | $5.00 | $5.25 |
| 2 | Guardrail removed, as per plan (202E38001) | FT | 36 | $45.00 | $45.00 | $48.00 |
| 3 | Excavation (203E10000) | CY | 43 | $50.00 | $120.00 | $130.00 |
| 4 | Embankment (203E20000) | CY | 5 | $50.00 | $100.00 | $110.00 |
| 5 | Guardrail, type 5A (606E13050) | FT | 37.50 | $112.00 | $112.00 | $120.00 |
| 6 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,250.00 | $2,010.00 | $8,200.00 |
| 7 | Post construction survey monument verification and report (623E51000) | LS | 1 | $818.00 | $2,010.00 | $6,500.00 |
| 8 | Soil analysis test (659E00100) | EACH | 2 | $200.00 | $200.00 | $225.00 |
| 9 | Topsoil (659E00300) | CY | 22 | $175.00 | $75.00 | $142.00 |
| 10 | Seeding and mulching (659E10000) | SY | 198 | $10.50 | $5.00 | $16.00 |
| 11 | Repair seeding and mulching (659E14000) | SY | 10 | $5.30 | $15.00 | $16.00 |
| 12 | Inter-seeding (659E15000) | SY | 10 | $0.10 | $15.00 | $16.00 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.03 | $930.00 | $500.00 | $1,600.00 |
| 14 | Lime (659E31000) | ACRE | 0.04 | $75.00 | $1,000.00 | $850.00 |
| 15 | Water (659E35000) | MGAL | 1.10 | $1.00 | $50.00 | $53.00 |
| 16 | Slope erosion protection mat, type C (670E00530) | SY | 70 | $9.50 | $15.00 | $16.00 |
| 17 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 |
| 18 | 4" conduit, type E (611E00400) | FT | 220 | $12.00 | $5.55 | $8.00 |
| 19 | Connection, fused pull apart (625E00450) | EACH | 8 | $185.00 | $142.50 | $130.00 |
| 20 | Connection, unfused pull apart (625E00460) | EACH | 15 | $175.00 | $140.00 | $130.00 |
| 21 | Bracket arm, 12' (625E18100) | EACH | 3 | $1,250.00 | $1,060.00 | $1,175.00 |
| 22 | Bracket arm, 15' (625E18200) | EACH | 1 | $1,450.00 | $1,150.00 | $1,350.00 |
| 23 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 1,203 | $2.50 | $3.95 | $3.50 |
| 24 | No. 10 AWG pole and bracket cable (625E23400) | FT | 531 | $2.00 | $1.65 | $2.50 |
| 25 | Luminaire, conventional, solid state (LED), ies-II (625E26252) | EACH | 4 | $625.00 | $410.00 | $375.00 |
| 26 | Conduit, 3", 725.04 (625E25500) | FT | 256 | $40.00 | $46.90 | $30.00 |
| 27 | Conduit, 4", 725.04 (625E25600) | FT | 77 | $62.00 | $80.20 | $45.00 |
| 28 | Conduit, jacked or drilled, 725.04, 4" (625E25902) | FT | 433 | $92.00 | $95.80 | $76.00 |
| 29 | Trench (625E29000) | FT | 333 | $17.00 | $13.80 | $12.00 |
| 30 | Pull box, 725.08, 18" (625E30700) | EACH | 5 | $1,280.00 | $1,825.00 | $1,200.00 |
| 31 | Pull box, 725.08, 24" (625E30706) | EACH | 6 | $1,395.00 | $2,025.00 | $1,450.00 |
| 32 | Ground rod (625E32000) | EACH | 11 | $275.00 | $325.00 | $275.00 |
| 33 | Underground warning marking tape (625E36010) | FT | 333 | $2.00 | $1.25 | $3.00 |
| 34 | Arc flash calculations and label , power service (625E76000) | EACH | 3 | $1,000.00 | $1,200.00 | $3,625.00 |
| 35 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate, as per plan (632E05007) | EACH | 25 | $1,150.00 | $1,032.00 | $1,525.00 |
| 36 | Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate, as per plan (632E05087) | EACH | 2 | $1,750.00 | $1,785.00 | $2,325.00 |
| 37 | Covering of vehicular signal head (632E25000) | EACH | 27 | $50.00 | $20.00 | $45.00 |
| 38 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 1,854 | $3.00 | $3.05 | $3.10 |
| 39 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 926 | $3.50 | $3.20 | $3.50 |
| 40 | Signal support foundation (632E64010) | EACH | 8 | $7,250.00 | $8,535.00 | $8,200.00 |
| 41 | Power cable, 3 conductor, no. 6 AWG (632E68300) | FT | 212 | $7.00 | $8.00 | $9.00 |
| 42 | Service cable, 3 conductor, no. 6 AWG (632E69800) | FT | 127 | $5.00 | $8.15 | $8.50 |
| 43 | Power service, as per plan (632E70001) | EACH | 3 | $3,400.00 | $3,515.00 | $2,500.00 |
| 44 | Conduit riser, 2" diameter (632E70400) | EACH | 3 | $925.00 | $1,050.00 | $725.00 |
| 45 | Signal support, type TC-12.31 design 10 pole, with mast arms TC-81.22 design 12 and design 12 (632E71348) | EACH | 3 | $25,560 | $23,760 | $27,400 |
| 46 | Signal support, type TC-81.22, design 12 (632E72130) | EACH | 1 | $12,820 | $13,145 | $15,200 |
| 47 | Combination signal support, type TC-81.22, design 4 (632E79110) | EACH | 1 | $11,225 | $11,550 | $13,150 |
| 48 | Combination signal support, type TC-81.22, design 13 (632E79140) | EACH | 3 | $16,140 | $16,405 | $18,950 |
| 49 | Removal of traffic signal installation (632E90100) | EACH | 3 | $2,500.00 | $5,565.00 | $4,500.00 |
| 50 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 3 | $17,900 | $15,420 | $18,000 |
| 51 | Cabinet foundation (633E67100) | EACH | 3 | $1,250.00 | $3,600.00 | $2,900.00 |
| 52 | Controller work pad (633E67200) | EACH | 3 | $500.00 | $900.00 | $750.00 |
| 53 | Uninterruptible power supply (UPS), 1000 watt (633E75000) | EACH | 3 | $7,800.00 | $8,190.00 | $8,200.00 |
| 54 | Controller item, misc.: communications (633E99000) | EACH | 3 | $250.00 | $735.00 | $975.00 |
| 55 | Advance radar detection, as per plan (809E69001) | EACH | 9 | $10,300 | $9,495.00 | $15,500 |
| 56 | Stop line radar detection, as per plan (809E69101) | EACH | 7 | $9,900.00 | $9,340.00 | $15,000 |
| 57 | Atc controller, as per plan (809E69123) | EACH | 3 | $800.00 | $700.00 | $1,300.00 |
| 58 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 150 | $95.00 | $70.00 | $75.00 |
| 59 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,400.00 | $10,470 | $3,735.92 |
| 60 | Maintaining traffic (614E11000) | LS | 1 | $8,530.00 | $30,500 | $85,000 |
| 61 | Field office, type B (619E16010) | MNTH | 12 | $1,500.00 | $1,550.00 | $850.00 |
| 62 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,225.00 | $4,970.00 | $15,000 |
| 63 | Mobilization (624E10000) | LS | 1 | $36,000 | $20,000 | $35,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 12, 2026. Compiled by Mirage Metrics.