ODOT contract 260191 bid tabulation

POR-SR 303-04.50 (INTERSECTION). Let by Ohio DOT on April 9, 2026, POR. 1 bid received; low bid $1,255,541 by Karvo Companies Inc, +2.7% against the engineer's estimate of $1,223,000.

Owner
Ohio DOT
Letting
09 APR 2026
Pay items
84
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Karvo Companies Inc$1,255,541Low+3.0%
ODOT contract 260191: bids by rank

Engineer's estimate: $1,223,000.

Bid tabulation

LinePay itemUnitQuantity1. Karvo Companies Inc
1Clearing and grubbing (201E11000)LS1$20,000
2Pavement removed (202E23000)SY4,827$22.50
3Guardrail removed (202E38000)FT1,169$2.00
4Removal misc.:inspection well (202E98100)EACH1$325.00
5Removal misc.:conduit (202E98200)FT150$12.00
6Excavation (203E10000)CY1,991$25.00
7Embankment (203E20000)CY8,317$25.00
8Embankment, as per plan (203E20001)CY50$60.00
9Roadway, misc.: pre-construction video taping (203E98500)LS1$450.00
10Subgrade compaction (204E10000)SY2,080$1.50
11Proof rolling (204E45000)HR3.50$250.00
12Cement (206E10500)TON145$210.00
13Curing coat (206E11000)SY4,773$1.25
14Cement stabilized subgrade, 14 inches deep (206E15020)SY4,773$7.00
15Mixture design for chemically stabilized soils (206E30000)LS1$5,000.00
16Guardrail, type MGS (606E15050)FT750$22.00
17Anchor assembly, MGS type E (606E26150)EACH3$2,500.00
18Fence removed and rebuilt, as per plan (607E35001)FT67$65.00
19Reference monument, type A (623E40500)EACH1$550.00
20Renovating existing soil, as per plan (654E10001)MSF7$275.00
21Special - as-built construction plans (690E91000)LS1$5,000.00
22Special - survey control verification (690E98400)LS1$2,400.00
23Rock channel protection, type C with filter (601E32200)CY25$250.00
24Soil analysis test (659E00100)EACH2$25.00
25Topsoil (659E00300)CY632$45.00
26Seeding and mulching (659E10000)SY5,694$1.25
27Repair seeding and mulching (659E14000)SY284$1.25
28Commercial fertilizer (659E20000)TON0.77$250.00
29Lime (659E31000)ACRE1.18$25.00
30Water (659E35000)MGAL31$1.00
31Slope erosion protection (670E00500)SY2,879$1.25
32Ditch erosion protection (670E00700)SY56$1.50
33Erosion control mat (671E14000)SY697$2.00
34Storm water pollution prevention plan (832E15000)LS1$5,000.00
35Storm water pollution prevention inspections (832E15002)LS1$7,500.00
36Storm water pollution prevention inspection software (832E15010)LS1$10,000
37Erosion control (832E30000)EACH17,878$1.00
38Aggregate drains (605E31100)FT418$15.00
396" conduit, type B (611E00900)FT50$25.00
406" conduit, type E (611E01400)FT50$25.00
416" conduit, type F (611E01500)FT50$25.00
42Conduit, misc.:type C for drainage discharge conti (611E97400)FT50$25.00
43Conduit, misc.:type E for drainage discharge conti (611E97400)FT50$25.00
44Conduit, misc.:type F for drainage discharge conti (611E97400)FT50$25.00
45Inspection well (611E99720)EACH1$500.00
46Asphalt concrete base, PG64-22, (449) (301E56000)CY1,093$185.00
47Aggregate base (304E20000)CY1,140$75.00
48Non-tracking tack coat (407E20000)GAL712$2.00
49Prime coat, as per plan (408E10001)GAL238$6.00
50Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY270$235.00
51Asphalt concrete intermediate course, type 2, (449) (441E70300)CY316$225.00
52Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY7$350.00
53Compacted aggregate (617E10100)CY51$150.00
54Shoulder preparation (617E20000)SY593$5.00
55Barrier reflector, type 2, BI-directional (626E00110)EACH16$12.00
56Ground mounted support, no. 2 post (630E02100)FT52$12.50
57Ground mounted support, no. 3 post, as per plan (630E03101)FT13.90$10.00
58Ground mounted support, no. 4 post (630E04100)FT29.60$25.00
59Sign post reflector (630E08600)EACH7$40.00
60Sign, flat sheet (630E80100)SF54.50$20.00
61Removal of ground mounted sign and disposal (630E84900)EACH13$5.00
62Removal of ground mounted post support and disposal (630E86002)EACH13$5.00
63Edge line, 4" (644E00100)MI0.51$5,000.00
64Center line (644E00300)MI0.39$8,250.00
65Channelizing line, 8" (644E00400)FT368$3.50
66Stop line (644E00500)FT26$10.00
67Transverse/diagonal line (644E00700)FT231$10.00
68Island marking (644E00900)SF84$10.00
69Lane arrow (644E01300)EACH6$150.00
70Law enforcement officer with patrol car for assistance (614E11110)HR16$125.00
71Detour signing (614E12420)LS1$15,000
72Work zone marking sign (614E12460)EACH6$90.00
73Asphalt concrete for maintaining traffic (614E13000)CY10$300.00
74Portable changeable message sign, as per plan (614E18601)SNMT4$900.00
75Work zone center line, class III, 642 paint (614E21550)MI0.39$1,500.00
76Work zone channelizing line, class III, 8", 642 paint (614E23680)FT368$2.00
77Work zone stop line, class III, 642 paint (614E26610)FT26$10.00
78Work zone arrow, class III, 642 paint (614E30650)EACH6$100.00
79Water (616E10000)MGAL20$5.00
80Premium for contract performance bond and for payment bond (103E05000)LS1$12,500
81Maintaining traffic (614E11000)LS1$24,518
82Field office, type B (619E16010)MNTH6$3,500.00
83Construction layout stakes and surveying (623E10000)LS1$29,880
84Mobilization (624E10000)LS1$75,000
ODOT contract 260191: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy