| 1 | Clearing and grubbing (201E11000) | LS | 1 | $20,000 |
| 2 | Pavement removed (202E23000) | SY | 4,827 | $22.50 |
| 3 | Guardrail removed (202E38000) | FT | 1,169 | $2.00 |
| 4 | Removal misc.:inspection well (202E98100) | EACH | 1 | $325.00 |
| 5 | Removal misc.:conduit (202E98200) | FT | 150 | $12.00 |
| 6 | Excavation (203E10000) | CY | 1,991 | $25.00 |
| 7 | Embankment (203E20000) | CY | 8,317 | $25.00 |
| 8 | Embankment, as per plan (203E20001) | CY | 50 | $60.00 |
| 9 | Roadway, misc.: pre-construction video taping (203E98500) | LS | 1 | $450.00 |
| 10 | Subgrade compaction (204E10000) | SY | 2,080 | $1.50 |
| 11 | Proof rolling (204E45000) | HR | 3.50 | $250.00 |
| 12 | Cement (206E10500) | TON | 145 | $210.00 |
| 13 | Curing coat (206E11000) | SY | 4,773 | $1.25 |
| 14 | Cement stabilized subgrade, 14 inches deep (206E15020) | SY | 4,773 | $7.00 |
| 15 | Mixture design for chemically stabilized soils (206E30000) | LS | 1 | $5,000.00 |
| 16 | Guardrail, type MGS (606E15050) | FT | 750 | $22.00 |
| 17 | Anchor assembly, MGS type E (606E26150) | EACH | 3 | $2,500.00 |
| 18 | Fence removed and rebuilt, as per plan (607E35001) | FT | 67 | $65.00 |
| 19 | Reference monument, type A (623E40500) | EACH | 1 | $550.00 |
| 20 | Renovating existing soil, as per plan (654E10001) | MSF | 7 | $275.00 |
| 21 | Special - as-built construction plans (690E91000) | LS | 1 | $5,000.00 |
| 22 | Special - survey control verification (690E98400) | LS | 1 | $2,400.00 |
| 23 | Rock channel protection, type C with filter (601E32200) | CY | 25 | $250.00 |
| 24 | Soil analysis test (659E00100) | EACH | 2 | $25.00 |
| 25 | Topsoil (659E00300) | CY | 632 | $45.00 |
| 26 | Seeding and mulching (659E10000) | SY | 5,694 | $1.25 |
| 27 | Repair seeding and mulching (659E14000) | SY | 284 | $1.25 |
| 28 | Commercial fertilizer (659E20000) | TON | 0.77 | $250.00 |
| 29 | Lime (659E31000) | ACRE | 1.18 | $25.00 |
| 30 | Water (659E35000) | MGAL | 31 | $1.00 |
| 31 | Slope erosion protection (670E00500) | SY | 2,879 | $1.25 |
| 32 | Ditch erosion protection (670E00700) | SY | 56 | $1.50 |
| 33 | Erosion control mat (671E14000) | SY | 697 | $2.00 |
| 34 | Storm water pollution prevention plan (832E15000) | LS | 1 | $5,000.00 |
| 35 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $7,500.00 |
| 36 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,000 |
| 37 | Erosion control (832E30000) | EACH | 17,878 | $1.00 |
| 38 | Aggregate drains (605E31100) | FT | 418 | $15.00 |
| 39 | 6" conduit, type B (611E00900) | FT | 50 | $25.00 |
| 40 | 6" conduit, type E (611E01400) | FT | 50 | $25.00 |
| 41 | 6" conduit, type F (611E01500) | FT | 50 | $25.00 |
| 42 | Conduit, misc.:type C for drainage discharge conti (611E97400) | FT | 50 | $25.00 |
| 43 | Conduit, misc.:type E for drainage discharge conti (611E97400) | FT | 50 | $25.00 |
| 44 | Conduit, misc.:type F for drainage discharge conti (611E97400) | FT | 50 | $25.00 |
| 45 | Inspection well (611E99720) | EACH | 1 | $500.00 |
| 46 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,093 | $185.00 |
| 47 | Aggregate base (304E20000) | CY | 1,140 | $75.00 |
| 48 | Non-tracking tack coat (407E20000) | GAL | 712 | $2.00 |
| 49 | Prime coat, as per plan (408E10001) | GAL | 238 | $6.00 |
| 50 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 270 | $235.00 |
| 51 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 316 | $225.00 |
| 52 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 7 | $350.00 |
| 53 | Compacted aggregate (617E10100) | CY | 51 | $150.00 |
| 54 | Shoulder preparation (617E20000) | SY | 593 | $5.00 |
| 55 | Barrier reflector, type 2, BI-directional (626E00110) | EACH | 16 | $12.00 |
| 56 | Ground mounted support, no. 2 post (630E02100) | FT | 52 | $12.50 |
| 57 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 13.90 | $10.00 |
| 58 | Ground mounted support, no. 4 post (630E04100) | FT | 29.60 | $25.00 |
| 59 | Sign post reflector (630E08600) | EACH | 7 | $40.00 |
| 60 | Sign, flat sheet (630E80100) | SF | 54.50 | $20.00 |
| 61 | Removal of ground mounted sign and disposal (630E84900) | EACH | 13 | $5.00 |
| 62 | Removal of ground mounted post support and disposal (630E86002) | EACH | 13 | $5.00 |
| 63 | Edge line, 4" (644E00100) | MI | 0.51 | $5,000.00 |
| 64 | Center line (644E00300) | MI | 0.39 | $8,250.00 |
| 65 | Channelizing line, 8" (644E00400) | FT | 368 | $3.50 |
| 66 | Stop line (644E00500) | FT | 26 | $10.00 |
| 67 | Transverse/diagonal line (644E00700) | FT | 231 | $10.00 |
| 68 | Island marking (644E00900) | SF | 84 | $10.00 |
| 69 | Lane arrow (644E01300) | EACH | 6 | $150.00 |
| 70 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 16 | $125.00 |
| 71 | Detour signing (614E12420) | LS | 1 | $15,000 |
| 72 | Work zone marking sign (614E12460) | EACH | 6 | $90.00 |
| 73 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $300.00 |
| 74 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $900.00 |
| 75 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.39 | $1,500.00 |
| 76 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 368 | $2.00 |
| 77 | Work zone stop line, class III, 642 paint (614E26610) | FT | 26 | $10.00 |
| 78 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 6 | $100.00 |
| 79 | Water (616E10000) | MGAL | 20 | $5.00 |
| 80 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,500 |
| 81 | Maintaining traffic (614E11000) | LS | 1 | $24,518 |
| 82 | Field office, type B (619E16010) | MNTH | 6 | $3,500.00 |
| 83 | Construction layout stakes and surveying (623E10000) | LS | 1 | $29,880 |
| 84 | Mobilization (624E10000) | LS | 1 | $75,000 |