ODOT contract 260253 bid tabulation
WAY-SR 94-18.21 (INTERSECTION). Let by Ohio DOT on May 7, 2026, WAY. 3 bids received; low bid $2,062,603 by Shelly & Sands Inc, -7.8% against the engineer's estimate of $2,237,000.
- Owner
- Ohio DOT
- Letting
- 07 MAY 2026
- Pay items
- 134
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $2,062,603 | Low | -8.0% |
| 2 | Fechko Excavating LLC | $2,071,427 | 0.0% | -7.0% |
| 3 | Eclipse Co LLC | $2,165,915 | +5.0% | -3.0% |
Engineer's estimate: $2,237,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Fechko Excavating LLC | 3. Eclipse Co LLC |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $18,000 | $10,000 | $7,755.10 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $1,100.00 | $400.00 | $653.31 |
| 3 | Pavement removed (202E23000) | SY | 6,036 | $6.50 | $6.00 | $12.19 |
| 4 | Walk removed, as per plan (202E30001) | SF | 35 | $10.00 | $11.00 | $12.10 |
| 5 | Gutter removed (202E32600) | FT | 115 | $13.00 | $16.00 | $7.30 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 240 | $36.00 | $20.00 | $40.00 |
| 7 | Pipe removed, over 24" diameter (202E35200) | FT | 199 | $58.00 | $94.00 | $44.07 |
| 8 | Guardrail removed (202E38000) | FT | 1,005 | $2.20 | $2.20 | $2.20 |
| 9 | Fence removed (202E75000) | FT | 339 | $4.50 | $6.00 | $4.50 |
| 10 | Removal misc.: concrete planter (202E98100) | EACH | 4 | $223.00 | $200.00 | $78.01 |
| 11 | Removal misc.: post (202E98100) | EACH | 1 | $447.00 | $800.00 | $385.00 |
| 12 | Removal misc.: post with light (202E98100) | EACH | 1 | $447.00 | $400.00 | $385.00 |
| 13 | Removal misc.: private sign (202E98100) | EACH | 3 | $298.00 | $300.00 | $282.49 |
| 14 | Removal misc.:business sign foundation (202E98100) | EACH | 1 | $447.00 | $400.00 | $385.00 |
| 15 | Removal misc.: brick wall (202E98200) | FT | 32 | $18.00 | $60.00 | $39.21 |
| 16 | Removal misc.: erosion control (202E98300) | SY | 9 | $49.00 | $90.00 | $35.05 |
| 17 | Excavation (203E10000) | CY | 4,499 | $11.50 | $18.00 | $19.06 |
| 18 | Embankment, as per plan (203E20001) | CY | 6,999 | $18.50 | $19.00 | $17.59 |
| 19 | Subgrade compaction (204E10000) | SY | 1,389 | $5.00 | $6.30 | $2.90 |
| 20 | Proof rolling (204E45000) | HR | 3 | $250.00 | $385.00 | $356.02 |
| 21 | Cement (206E10500) | TON | 211 | $192.00 | $192.00 | $203.00 |
| 22 | Curing coat (206E11000) | SY | 7,389 | $1.20 | $1.20 | $1.15 |
| 23 | Cement stabilized subgrade, 12 inches deep (206E15010) | SY | 2,837 | $3.30 | $3.30 | $3.65 |
| 24 | Cement stabilized subgrade, 14 inches deep (206E15020) | SY | 4,553 | $4.25 | $4.04 | $0.45 |
| 25 | Guardrail, type MGS (606E15050) | FT | 488 | $20.50 | $20.50 | $20.50 |
| 26 | Guardrail, type MGS with long posts (606E15100) | FT | 425 | $26.00 | $26.00 | $26.00 |
| 27 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,485.00 | $1,385.00 | $1,385.00 |
| 28 | Monument assembly, type C (623E38500) | EACH | 7 | $2,330.00 | $2,015.00 | $1,006.45 |
| 29 | Reference monument, type A (623E40500) | EACH | 2 | $580.00 | $460.00 | $1,076.90 |
| 30 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $5,300.00 | $6,800.00 | $5,000.00 |
| 31 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,400.00 | $7,700.00 | $5,000.00 |
| 32 | Special - pavement overlay fabric composite (690E12060) | SY | 190 | $41.50 | $41.50 | $38.30 |
| 33 | Special - mailbox removed and reset (690E50350) | EACH | 2 | $750.00 | $925.00 | $245.00 |
| 34 | Riprap, type D (601E11000) | SY | 18 | $189.00 | $260.00 | $149.90 |
| 35 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 120 | $120.00 | $105.00 | $93.91 |
| 36 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 11 | $250.00 | $200.00 | $290.53 |
| 37 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 3 | $345.00 | $225.00 | $569.97 |
| 38 | Soil analysis test (659E00100) | EACH | 2 | $140.00 | $200.00 | $135.00 |
| 39 | Topsoil (659E00300) | CY | 1,400 | $16.00 | $18.00 | $75.79 |
| 40 | Seeding and mulching (659E10000) | SY | 9,997 | $0.50 | $2.25 | $0.83 |
| 41 | Repair seeding and mulching (659E14000) | SY | 566 | $0.80 | $2.25 | $0.80 |
| 42 | Inter-seeding (659E15000) | SY | 566 | $0.80 | $2.00 | $0.80 |
| 43 | Commercial fertilizer (659E20000) | TON | 2 | $900.00 | $1,850.00 | $891.39 |
| 44 | Lime (659E31000) | ACRE | 3 | $160.00 | $50.00 | $157.87 |
| 45 | Water (659E35000) | MGAL | 63 | $1.00 | $125.00 | $1.00 |
| 46 | Ditch erosion protection (670E00700) | SY | 741 | $1.50 | $4.25 | $1.49 |
| 47 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,200.00 | $3,200.00 | $3,200.00 |
| 48 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $10,700 | $10,700 | $3,240.00 |
| 49 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $11,000 | $11,000 | $10,976 |
| 50 | Erosion control (832E30000) | EACH | 75,000 | $1.00 | $1.00 | $1.00 |
| 51 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 259 | $5.50 | $4.80 | $5.47 |
| 52 | Seeding and erosion control with turf reinforcing mat, type 3 (836E10030) | SY | 280 | $7.00 | $5.10 | $6.87 |
| 53 | Concrete masonry (602E20000) | CY | 5.40 | $2,500.00 | $1,800.00 | $2,710.82 |
| 54 | 6" unclassified pipe underdrains, as per plan (605E13301) | FT | 100 | $27.00 | $15.00 | $16.85 |
| 55 | 6" unclassified pipe underdrains with geotextile fabric (605E13410) | FT | 140 | $21.00 | $15.00 | $22.37 |
| 56 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 3,506 | $16.00 | $15.00 | $20.06 |
| 57 | Aggregate drains (605E31100) | FT | 50 | $20.00 | $15.00 | $38.45 |
| 58 | 4" conduit, type C (611E00200) | FT | 18 | $30.00 | $15.00 | $43.50 |
| 59 | 4" conduit, type F (611E00406) | FT | 13 | $69.00 | $15.00 | $46.47 |
| 60 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 125 | $27.00 | $15.00 | $29.06 |
| 61 | 6" conduit, type F, as per plan (611E01501) | FT | 100 | $20.00 | $15.00 | $23.38 |
| 62 | 12" conduit, type D (611E04900) | FT | 55 | $86.00 | $50.00 | $76.32 |
| 63 | 15" conduit, type C (611E06100) | FT | 190 | $98.00 | $55.00 | $83.40 |
| 64 | 15" conduit, type D (611E06400) | FT | 64 | $97.00 | $55.00 | $93.83 |
| 65 | 18" conduit, type C (611E07600) | FT | 72 | $118.00 | $65.00 | $118.25 |
| 66 | 30" conduit, type A, as per plan, 706.02, 707.18 ( (611E13201) | FT | 139 | $199.00 | $230.00 | $179.77 |
| 67 | 54" conduit, type A, as per plan, 706.02, 707.18 ( (611E22201) | FT | 103 | $472.00 | $420.00 | $495.15 |
| 68 | Catch basin, no. 5 without apron (611E98330) | EACH | 2 | $4,250.00 | $3,200.00 | $6,359.27 |
| 69 | Precast reinforced concrete outlet (611E99710) | EACH | 15 | $580.00 | $650.00 | $607.11 |
| 70 | Pavement planing, asphalt concrete, 3 1/4" (254E01000) | SY | 759 | $20.00 | $20.00 | $15.50 |
| 71 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,152 | $199.00 | $199.00 | $173.00 |
| 72 | Aggregate base (304E20000) | CY | 1,577 | $99.00 | $77.00 | $100.75 |
| 73 | Tack coat (407E10000) | GAL | 861 | $3.05 | $3.05 | $2.75 |
| 74 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 308 | $276.00 | $276.00 | $263.00 |
| 75 | Asphalt concrete intermediate course, 12.5 MM, type A (448) (442E20170) | CY | 360 | $235.25 | $235.25 | $233.00 |
| 76 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 9 | $1,000.00 | $1,000.00 | $578.00 |
| 77 | Asphalt concrete intermediate course, 12.5 MM, type A (449) (442E22300) | CY | 11 | $750.00 | $750.00 | $490.00 |
| 78 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 595 | $108.00 | $125.00 | $112.00 |
| 79 | Non-reinforced concrete pavement, misc.: 12.25" TR (452E19200) | SY | 338 | $198.00 | $220.00 | $165.00 |
| 80 | Combination curb and gutter, type 2 (609E12000) | FT | 1,611 | $30.00 | $39.00 | $28.00 |
| 81 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 40 | $85.00 | $68.00 | $27.50 |
| 82 | Curb, type 2-A (609E14000) | FT | 216 | $46.00 | $20.00 | $20.50 |
| 83 | Combination curb and gutter, type 3, as per plan (609E18001) | FT | 291 | $67.00 | $39.00 | $27.50 |
| 84 | Curb, type 6 (609E26000) | FT | 1,311 | $26.00 | $22.00 | $20.50 |
| 85 | 4" conduit, type E, as per plan (611E00401) | FT | 140 | $8.00 | $14.00 | $7.50 |
| 86 | Connection, fused pull apart (625E00450) | EACH | 16 | $115.00 | $165.00 | $115.00 |
| 87 | Connection, unfused permanent, as per plan (625E00481) | EACH | 9 | $105.00 | $165.00 | $105.00 |
| 88 | Light pole, conventional (AT12B40) (625E10490) | EACH | 7 | $3,425.00 | $3,900.00 | $3,425.00 |
| 89 | Light pole, conventional (AT15B40) (625E10490) | EACH | 1 | $3,500.00 | $3,950.00 | $3,500.00 |
| 90 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 8 | $2,250.00 | $2,100.00 | $2,250.00 |
| 91 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 4,026 | $6.00 | $4.50 | $6.00 |
| 92 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,257 | $1.25 | $2.50 | $1.25 |
| 93 | Conduit, 3", 725.04 (625E25500) | FT | 875 | $45.00 | $32.00 | $45.00 |
| 94 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 189 | $101.00 | $125.00 | $101.00 |
| 95 | Luminaire, conventional, solid state (LED), type I (625E26252) | EACH | 8 | $400.00 | $650.00 | $400.00 |
| 96 | Trench, 24" deep (625E29002) | FT | 875 | $9.50 | $14.00 | $9.50 |
| 97 | Pull box, 725.08, 24", as per plan (625E30707) | EACH | 6 | $1,050.00 | $1,250.00 | $1,050.00 |
| 98 | Ground rod (625E32000) | EACH | 8 | $150.00 | $300.00 | $150.00 |
| 99 | Power service, as per plan (625E34001) | EACH | 1 | $9,750.00 | $8,900.00 | $9,750.00 |
| 100 | Underground warning marking tape (625E36010) | FT | 875 | $1.60 | $3.00 | $1.55 |
| 101 | Arc flash calculations and label, lighting control (625E76000) | EACH | 1 | $3,300.00 | $1,200.00 | $3,300.00 |
| 102 | Controller work pad, as per plan (633E67201) | EACH | 1 | $550.00 | $900.00 | $550.00 |
| 103 | Delineator, post ground mounted (620E00500) | EACH | 4 | $75.00 | $125.00 | $95.00 |
| 104 | RPM (621E00100) | EACH | 143 | $44.00 | $77.50 | $41.00 |
| 105 | Raised pavement marker removed (621E54000) | EACH | 30 | $10.00 | $115.00 | $18.55 |
| 106 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 507.40 | $15.00 | $16.00 | $18.00 |
| 107 | Sign post reflector (630E08600) | EACH | 4 | $40.00 | $65.00 | $44.00 |
| 108 | Sign, flat sheet (630E80100) | SF | 219.60 | $20.00 | $18.00 | $23.00 |
| 109 | Removal of ground mounted sign and storage (630E85000) | EACH | 42 | $35.00 | $35.00 | $25.00 |
| 110 | Removal of ground mounted sign and reerection (630E85100) | EACH | 9 | $65.00 | $95.00 | $70.00 |
| 111 | Removal of ground mounted post support and disposal (630E86002) | EACH | 39 | $25.00 | $40.00 | $20.00 |
| 112 | Signing, misc.:, 12" PVC pipe (630E97700) | EACH | 5 | $80.00 | $150.00 | $65.00 |
| 113 | Edge line, 6" (644E00104) | MI | 0.66 | $3,350.00 | $6,500.00 | $6,000.00 |
| 114 | Edge line, 6" (644E00104) | MI | 0.18 | $11,000 | $6,500.00 | $6,000.00 |
| 115 | Center line (644E00300) | MI | 0.38 | $5,000.00 | $12,500 | $8,500.00 |
| 116 | Transverse/diagonal line (644E00700) | FT | 114 | $10.00 | $10.00 | $10.00 |
| 117 | Dotted line, 12" (644E01520) | FT | 131 | $2.00 | $4.00 | $4.00 |
| 118 | Yield line (644E20800) | FT | 77 | $12.75 | $15.00 | $10.00 |
| 119 | Granular material, type E, as per plan (203E35141) | CY | 67 | $134.00 | $125.00 | $133.78 |
| 120 | Evergreen shrub, 12" height, juniperus sabina 'arc (661E30000) | EACH | 5 | $190.00 | $450.00 | $189.06 |
| 121 | Planting, misc.: weed barrier (661E99930) | SY | 400 | $4.25 | $3.00 | $4.05 |
| 122 | Building demolished, parcel 8-T, outbuilding and C (202E56000) | LS | 1 | $11,000 | $10,000 | $61,259 |
| 123 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $100.00 | $85.00 | $100.00 |
| 124 | Detour signing (614E12420) | LS | 1 | $13,000 | $30,150 | $19,977 |
| 125 | Asphalt concrete for maintaining traffic (614E13000) | CY | 20 | $400.00 | $400.00 | $250.00 |
| 126 | Portable changeable message sign, as per plan (614E18601) | SNMT | 10 | $800.00 | $1,200.00 | $1,210.76 |
| 127 | Business entrance sign, as per plan (614E40051) | EACH | 2 | $175.00 | $450.00 | $214.42 |
| 128 | Water (616E10000) | MGAL | 15 | $120.00 | $65.00 | $27.72 |
| 129 | Lighting, misc.: temporary lighting (625E98200) | LS | 1 | $3,800.00 | $8,000.00 | $3,800.00 |
| 130 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $9,000.00 | $17,000 | $21,693 |
| 131 | Maintaining traffic (614E11000) | LS | 1 | $18,000 | $5,000.00 | $36,279 |
| 132 | Field office, type B (619E16010) | MNTH | 6 | $4,660.00 | $1,740.00 | $3,747.94 |
| 133 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,548 | $23,000 | $11,226 |
| 134 | Mobilization (624E10000) | LS | 1 | $104,000 | $85,000 | $94,430 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.