ODOT contract 260388 bid tabulation
MED-SR 162-25.11 (INTERSECTION). Let by Ohio DOT on August 27, 2026, MED. 4 bids received; low bid $1,640,945 by Shelly & Sands Inc, -13% against the engineer's estimate of $1,887,000.
- Owner
- Ohio DOT
- Letting
- 27 AUG 2026
- Pay items
- 115
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $1,640,945 | Low | -13% |
| 2 | S E T Inc | $2,018,670 | +23% | +7.0% |
| 3 | Tri-Mor Corp | $2,029,895 | +24% | +8.0% |
| 4 | Grassbaugh LLC | $2,058,575 | +25% | +9.0% |
Engineer's estimate: $1,887,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. S E T Inc | 3. Tri-Mor Corp | 4. Grassbaugh LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $22,000 | $40,000 | $25,000 | $50,000 |
| 2 | Pavement removed (202E23000) | SY | 4,671 | $2.30 | $16.00 | $20.00 | $18.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 566 | $33.00 | $17.00 | $30.00 | $65.00 |
| 4 | Catch basin removed (202E58100) | EACH | 1 | $932.00 | $1,000.00 | $500.00 | $500.00 |
| 5 | Fence removed (202E75000) | FT | 162 | $10.00 | $5.00 | $8.50 | $5.00 |
| 6 | Removal misc.: post removed (202E98100) | EACH | 1 | $46.00 | $350.00 | $205.00 | $688.00 |
| 7 | Removal misc.: rock removed (202E98100) | EACH | 10 | $91.00 | $325.00 | $30.00 | $206.39 |
| 8 | Excavation (203E10000) | CY | 3,196 | $15.25 | $24.00 | $30.00 | $27.50 |
| 9 | Embankment (203E20000) | CY | 2,620 | $16.25 | $21.00 | $15.00 | $18.00 |
| 10 | Granular material, type E, as per plan (203E35141) | CY | 55 | $245.00 | $90.00 | $200.00 | $160.00 |
| 11 | Subgrade compaction (204E10000) | SY | 578 | $7.80 | $3.00 | $2.00 | $4.00 |
| 12 | Proof rolling (204E45000) | HR | 4 | $300.00 | $225.00 | $275.00 | $135.00 |
| 13 | Cement (206E10500) | TON | 231 | $200.00 | $215.00 | $216.00 | $231.00 |
| 14 | Curing coat (206E11000) | SY | 7,512 | $1.30 | $1.50 | $1.50 | $1.25 |
| 15 | Cement stabilized subgrade, 14 inches deep (206E15020) | SY | 7,512 | $4.55 | $5.50 | $6.50 | $3.80 |
| 16 | Fence, misc.: temporary construction fence (607E98200) | LS | 1 | $3,400.00 | $6,000.00 | $5,500.00 | $7,500.00 |
| 17 | Combination curb and gutter, type 2 (609E12000) | FT | 1,021 | $34.00 | $27.00 | $37.00 | $26.52 |
| 18 | Curb, type 3-B, as per plan (609E22001) | FT | 295 | $33.00 | $27.00 | $43.00 | $26.52 |
| 19 | Curb, type 6 (609E26000) | FT | 1,206 | $22.50 | $21.00 | $23.00 | $20.40 |
| 20 | Curb, type 6, as per plan (609E26001) | FT | 196 | $54.00 | $23.00 | $37.00 | $22.44 |
| 21 | Monument assembly, type D (623E38550) | EACH | 2 | $2,825.00 | $1,200.00 | $1,800.00 | $2,000.00 |
| 22 | Reference monument, type A (623E40500) | EACH | 1 | $1,425.00 | $1,200.00 | $1,100.00 | $2,000.00 |
| 23 | Right-of-way monument, type B (623E40520) | EACH | 12 | $180.00 | $450.00 | $400.00 | $2,000.00 |
| 24 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $5,800.00 | $4,500.00 | $3,500.00 | $7,500.00 |
| 25 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,900.00 | $4,500.00 | $3,500.00 | $8,000.00 |
| 26 | Special - mailbox removed and reset (690E50350) | EACH | 8 | $1,140.00 | $600.00 | $250.00 | $100.00 |
| 27 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 129 | $100.00 | $130.00 | $75.00 | $38.00 |
| 28 | Rock channel protection, type C with filter (601E32200) | CY | 9 | $476.00 | $250.00 | $450.00 | $440.00 |
| 29 | Topsoil (659E00300) | CY | 1,101 | $21.00 | $75.00 | $58.00 | $35.00 |
| 30 | Seeding and mulching (659E10000) | SY | 9,915 | $0.85 | $1.00 | $3.00 | $2.00 |
| 31 | Repair seeding and mulching (659E14000) | SY | 496 | $0.80 | $1.00 | $3.00 | $1.75 |
| 32 | Inter-seeding (659E15000) | SY | 496 | $0.80 | $1.00 | $2.50 | $0.10 |
| 33 | Commercial fertilizer (659E20000) | TON | 1.34 | $950.00 | $950.00 | $2,500.00 | $860.00 |
| 34 | Lime (659E31000) | ACRE | 2.05 | $162.00 | $160.00 | $300.00 | $40.00 |
| 35 | Water (659E35000) | MGAL | 27 | $1.00 | $10.00 | $250.00 | $0.50 |
| 36 | Slope erosion protection (670E00500) | SY | 1,959 | $1.50 | $2.00 | $5.00 | $4.56 |
| 37 | Ditch erosion protection (670E00700) | SY | 245 | $1.70 | $2.00 | $15.00 | $3.34 |
| 38 | Ditch erosion protection mat, type B (670E00720) | SY | 316 | $1.70 | $2.00 | $5.00 | $3.49 |
| 39 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,500.00 | $4,500.00 | $3,900.00 | $3,500.00 |
| 40 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,425.00 | $6,500.00 | $12,000 | $3,210.00 |
| 41 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $8,220.00 | $14,000 | $12,000 | $5,500.00 |
| 42 | Erosion control (832E30000) | EACH | 45,260 | $1.00 | $1.00 | $1.00 | $1.00 |
| 43 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 84 | $6.00 | $3.00 | $55.00 | $9.00 |
| 44 | Seeding and erosion control with turf reinforcing mat, type 3 (836E10030) | SY | 291 | $7.25 | $3.00 | $55.00 | $12.00 |
| 45 | Concrete masonry (602E20000) | CY | 2 | $2,640.00 | $3,500.00 | $3,100.00 | $2,800.00 |
| 46 | 6" unclassified pipe underdrains (605E13300) | FT | 462 | $22.50 | $22.00 | $13.50 | $20.00 |
| 47 | 6" base pipe underdrains (605E14000) | FT | 2,912 | $14.50 | $20.00 | $13.50 | $20.00 |
| 48 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 39 | $83.50 | $30.00 | $15.00 | $50.00 |
| 49 | 12" conduit, type D (611E04900) | FT | 308 | $85.00 | $80.00 | $89.00 | $105.00 |
| 50 | 24" conduit, type D (611E10900) | FT | 36 | $133.00 | $145.00 | $165.00 | $196.00 |
| 51 | 30" conduit, type A , 706.02, 707.33, 707.04 (0.1 (611E13200) | FT | 111 | $198.00 | $225.00 | $275.00 | $200.00 |
| 52 | Inlet, side ditch (611E98700) | EACH | 1 | $1,800.00 | $2,800.00 | $2,000.00 | $3,000.00 |
| 53 | Manhole adjusted to grade (611E99654) | EACH | 1 | $1,750.00 | $2,000.00 | $850.00 | $2,000.00 |
| 54 | Manhole reconstructed to grade (611E99660) | EACH | 1 | $3,762.00 | $5,000.00 | $1,400.00 | $3,500.00 |
| 55 | Manhole reconstructed to grade, as per plan (611E99661) | EACH | 3 | $2,768.00 | $5,500.00 | $2,400.00 | $3,500.00 |
| 56 | Precast reinforced concrete outlet (611E99710) | EACH | 6 | $610.00 | $425.00 | $550.00 | $700.00 |
| 57 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 886 | $177.83 | $245.00 | $265.00 | $200.00 |
| 58 | Aggregate base (304E20000) | CY | 1,360 | $100.00 | $85.00 | $100.00 | $81.00 |
| 59 | Non-tracking tack coat (407E20000) | GAL | 758 | $3.25 | $4.00 | $4.00 | $3.00 |
| 60 | Stabilized crushed aggregate, as per plan (411E10001) | CY | 88 | $175.00 | $95.00 | $255.00 | $141.00 |
| 61 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 265 | $276.00 | $250.00 | $270.00 | $342.00 |
| 62 | Asphalt concrete intermediate course, 12.5 MM, type A (448) (442E20170) | CY | 310 | $219.50 | $250.00 | $270.00 | $292.00 |
| 63 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 56 | $200.00 | $95.00 | $98.00 | $81.60 |
| 64 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 422 | $87.00 | $125.00 | $92.00 | $112.20 |
| 65 | 8" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011) | SY | 477 | $123.50 | $145.00 | $116.00 | $130.56 |
| 66 | 6" water main ductile iron pipe ansi class 52, push-on joints and fittings (638E00600) | FT | 8 | $373.00 | $350.00 | $300.00 | $600.00 |
| 67 | 6" gate valve (638E07480) | EACH | 2 | $2,195.00 | $3,000.00 | $7,200.00 | $2,500.00 |
| 68 | 6" fire hydrant (638E10200) | EACH | 2 | $4,176.00 | $9,500.00 | $12,750 | $8,500.00 |
| 69 | Special - valve box rebuilt to grade, (medina coun (638E20502) | EACH | 4 | $1,287.00 | $1,300.00 | $750.00 | $850.00 |
| 70 | Special - fire hydrant removed for storage, (medin (638E20752) | EACH | 2 | $650.00 | $2,000.00 | $750.00 | $1,500.00 |
| 71 | Water work, misc.: relocate service box (638E98000) | EACH | 1 | $1,407.50 | $3,500.00 | $3,550.00 | $2,500.00 |
| 72 | Water work, misc.: water flushing assembly adjuste (638E98000) | EACH | 2 | $1,020.00 | $1,300.00 | $2,000.00 | $4,200.00 |
| 73 | 4" conduit, type E (611E00400) | FT | 120 | $6.00 | $12.00 | $16.00 | $6.10 |
| 74 | Connection, fused pull apart (625E00450) | EACH | 24 | $115.00 | $140.00 | $170.00 | $136.50 |
| 75 | Connection, unfused permanent (625E00480) | EACH | 15 | $100.00 | $80.00 | $90.00 | $136.50 |
| 76 | Light pole, conventional, AT12B40 (625E10490) | EACH | 12 | $3,450.00 | $4,200.00 | $4,300.00 | $3,726.24 |
| 77 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 12 | $1,750.00 | $1,900.00 | $2,600.00 | $2,332.50 |
| 78 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 5,515 | $5.60 | $4.00 | $4.00 | $5.01 |
| 79 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,872 | $1.50 | $2.00 | $1.50 | $2.31 |
| 80 | Conduit, 3", 725.04 (625E25500) | FT | 1,585 | $35.00 | $40.00 | $46.00 | $30.84 |
| 81 | Luminaire, conventional, solid state (LED), 14000- (625E26252) | EACH | 12 | $475.00 | $650.00 | $500.00 | $426.00 |
| 82 | Trench, 24" deep (625E29002) | FT | 1,585 | $7.00 | $18.00 | $11.00 | $10.97 |
| 83 | Pull box, 725.08, 18" (625E30700) | EACH | 1 | $775.00 | $1,500.00 | $1,315.00 | $964.50 |
| 84 | Pull box, 725.08, 24" (625E30706) | EACH | 4 | $875.00 | $1,300.00 | $1,500.00 | $1,066.50 |
| 85 | Ground rod (625E32000) | EACH | 12 | $150.00 | $250.00 | $200.00 | $247.50 |
| 86 | Power service, as per plan (625E34001) | EACH | 1 | $5,500.00 | $4,000.00 | $5,200.00 | $4,155.00 |
| 87 | Transformer pad, concrete (625E34300) | EACH | 1 | $400.00 | $600.00 | $1,400.00 | $2,092.50 |
| 88 | Control center cabinet, complete (625E34450) | EACH | 1 | $3,950.00 | $13,000 | $6,500.00 | $6,807.00 |
| 89 | Underground warning marking tape (625E36010) | FT | 1,585 | $1.40 | $1.00 | $2.00 | $1.84 |
| 90 | Temporary lighting (625E39000) | LS | 1 | $3,700.00 | $2,000.00 | $5,500.00 | $23,910 |
| 91 | Arc flash calculations and label, power service (625E76000) | EACH | 1 | $3,300.00 | $1,600.00 | $2,500.00 | $3,030.00 |
| 92 | Delineator, misc.: high intensity retro-reflective (620E70000) | EACH | 4 | $150.00 | $175.00 | $200.00 | $150.00 |
| 93 | RPM (621E00100) | EACH | 126 | $58.00 | $85.00 | $68.00 | $79.00 |
| 94 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 422.20 | $13.00 | $15.00 | $15.00 | $12.50 |
| 95 | Sign post reflector (630E08600) | EACH | 4 | $45.00 | $50.00 | $50.00 | $45.00 |
| 96 | Sign, flat sheet (630E80100) | SF | 229.20 | $25.00 | $30.00 | $30.00 | $25.00 |
| 97 | Removal of ground mounted sign and disposal (630E84900) | EACH | 34 | $5.00 | $10.00 | $6.00 | $5.00 |
| 98 | Removal of ground mounted sign and reerection, as per plan (630E85101) | EACH | 1 | $175.00 | $200.00 | $200.00 | $175.00 |
| 99 | Removal of ground mounted post support and disposal (630E86002) | EACH | 19 | $5.00 | $10.00 | $6.00 | $5.00 |
| 100 | Edge line, 6" (644E00104) | MI | 0.99 | $6,000.00 | $6,500.00 | $6,700.00 | $6,000.00 |
| 101 | Center line (644E00300) | MI | 0.40 | $8,500.00 | $9,000.00 | $9,400.00 | $8,500.00 |
| 102 | Transverse/diagonal line (644E00700) | FT | 330 | $10.00 | $11.00 | $12.00 | $10.00 |
| 103 | Dotted line, 8" (644E01514) | FT | 184 | $5.00 | $6.00 | $6.00 | $5.00 |
| 104 | Yield line (644E20800) | FT | 67 | $15.00 | $16.00 | $17.00 | $15.00 |
| 105 | Removal of pavement marking (644E30000) | FT | 390 | $7.50 | $8.00 | $9.00 | $7.50 |
| 106 | Planting, misc.: weed barrier (661E99920) | SF | 2,971 | $0.60 | $1.00 | $1.00 | $2.00 |
| 107 | Traffic compacted surface, type A (410E10000) | CY | 180 | $44.00 | $95.00 | $90.00 | $119.00 |
| 108 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $95.00 | $95.00 | $100.00 | $110.00 |
| 109 | Roads for maintaining traffic (615E10000) | LS | 1 | $13,000 | $15,000 | $4,000.00 | $15,000 |
| 110 | Water (616E10000) | MGAL | 27 | $100.00 | $125.00 | $120.00 | $1.00 |
| 111 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $20,000 | $17,000 | $20,000 |
| 112 | Maintaining traffic (614E11000) | LS | 1 | $19,327 | $65,000 | $27,000 | $30,000 |
| 113 | Field office, type B (619E16010) | MNTH | 10 | $3,700.00 | $2,500.00 | $2,000.00 | $1,500.00 |
| 114 | Construction layout stakes and surveying (623E10000) | LS | 1 | $25,000 | $50,000 | $25,000 | $50,000 |
| 115 | Mobilization (624E10000) | LS | 1 | $82,000 | $60,000 | $50,000 | $150,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of August 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.