SCDOT contract 2473910 bid tabulation
S-24-102 over Ninety Six Creek Bridge Replacement Asset 2547. Let by South Carolina DOT on March 10, 2026, Greenwood, District 2. 8 bids received; low bid $6,059,969 by Dane Construction, LLC.
- Owner
- South Carolina DOT
- Letting
- 10 MAR 2026
- Pay items
- 95
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dane Construction, LLC | $6,059,969 | Low |
| 2 | Palmetto Infrastructure, Inc. | $6,199,734 | +2.0% |
| 3 | Mastec Civil, LLC | $6,726,179 | +11% |
| 4 | United Infrastructure Group, Inc. | $6,777,855 | +12% |
| 5 | Coogler Construction, Inc. | $7,155,008 | +18% |
| 6 | Aos Specialty Contractors, Inc. | $7,185,205 | +19% |
| 7 | Whaley Construction, LLC | $7,763,047 | +28% |
| 8 | Reeves Construction Company | $7,773,105 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dane Construction, LLC | 2. Palmetto Infrastructure, Inc. | 3. Mastec Civil, LLC | 4. United Infrastructure Group, Inc. | 5. Coogler Construction, Inc. | 6. Aos Specialty Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $302,995 | $310,000 | $335,000 | $338,893 | $292,924 | $283,555 |
| 0020 | Mobilization - subcontractor (1031100) | LS | 1 | $302,995 | $107,500 | $335,000 | $338,893 | $302,500 | $109,377 |
| 0030 | Bridge construction access (1031200) | LS | 1 | $45,000 | $215,000 | $80,000 | $67,779 | $10,000 | $275,909 |
| 0040 | Bonds and insurance (1032010) | LS | 1 | $121,195 | $124,000 | $200,000 | $203,336 | $61,902 | $65,516 |
| 0050 | Construction stakes, lines & grades (1050800) | EACH | 1 | $35,000 | $42,500 | $85,000 | $50,000 | $100,301 | $69,117 |
| 0060 | CPM progress schedule (1080300) | LS | 1 | $20,000 | $8,750.00 | $8,250.00 | $10,000 | $20,000 | $20,122 |
| 0070 | Clearing & grubbing within right of way (2011000) | LS | 1 | $55,000 | $248,000 | $338,000 | $250,000 | $85,000 | $57,597 |
| 0080 | Selected clearing (2015010) | LS | 1 | $8,000.00 | $8,000.00 | $9,000.00 | $1.00 | $10,000 | $6,456.00 |
| 0090 | Removal & disposal of existing asphalt pavement (2025000) | SY | 2,837 | $14.28 | $3.00 | $11.00 | $8.00 | $10.50 | $23.00 |
| 0100 | Removal of exist. guardrail (2027801) | LF | 763 | $3.00 | $2.00 | $2.25 | $2.00 | $5.00 | $4.50 |
| 0110 | Removal & disposal of existing bridge (2028100) | LS | 1 | $175,455 | $350,000 | $250,000 | $391,000 | $295,000 | $386,706 |
| 0120 | Unclassified excavation (2031000) | CY | 4,197 | $14.50 | $14.50 | $11.00 | $28.00 | $26.00 | $54.00 |
| 0130 | Borrow excavation (2033000) | CY | 26,935 | $24.95 | $24.95 | $30.00 | $38.00 | $29.00 | $30.00 |
| 0140 | Borrow pit set-UP (2033100) | LS | 1 | $3,500.00 | $3,500.00 | $2,000.00 | $1.00 | $50,000 | $16,925 |
| 0150 | Geogrid reinforcement (uniaxial) (2037000) | SY | 6,960 | $3.68 | $3.68 | $11.00 | $11.00 | $9.00 | $10.00 |
| 0160 | Fine grading (2081001) | SY | 4,804 | $5.00 | $5.00 | $6.50 | $14.00 | $7.50 | $16.50 |
| 0170 | Maintenance stone (3059900) | TON | 100 | $42.00 | $42.00 | $75.00 | $50.00 | $60.00 | $88.00 |
| 0180 | Liquid asphalt binder PG64-22 (4011004) | TON | 110 | $726.75 | $655.00 | $697.00 | $661.55 | $655.00 | $754.00 |
| 0190 | Full depth asph. pav. patching 6" unif. (4012060) | SY | 1,000 | $87.93 | $61.00 | $64.00 | $60.60 | $60.00 | $69.00 |
| 0200 | Milling existing asphalt pavement (variable) (4013990) | SY | 318 | $26.26 | $46.00 | $48.00 | $45.45 | $22.50 | $52.00 |
| 0210 | Asphalt base course - type B (4020320) | TON | 658 | $125.55 | $149.00 | $158.00 | $149.48 | $148.00 | $171.00 |
| 0220 | Asphalt intermediate course type B (4030320) | TON | 480 | $132.41 | $142.00 | $148.00 | $141.40 | $140.00 | $161.00 |
| 0230 | Asphalt intermediate course type C (4030330) | TON | 429 | $135.59 | $146.00 | $155.00 | $146.45 | $145.00 | $167.00 |
| 0240 | Asphalt surface course type D (4040350) | TON | 470 | $132.19 | $152.00 | $160.00 | $151.50 | $150.00 | $173.00 |
| 0250 | Asphalt surface course type E (4040360) | TON | 24 | $307.86 | $165.00 | $175.00 | $166.65 | $165.00 | $190.00 |
| 0260 | Traffic control (6011000) | LS | 1 | $13,540 | $8,500.00 | $20,000 | $50,060 | $20,000 | $29,375 |
| 0270 | Barricade - type III (6041200) | LF | 84 | $25.00 | $30.00 | $43.00 | $25.00 | $44.00 | $34.00 |
| 0280 | Permanent construction signs (ground mounted) (6051120) | SF | 128 | $7.25 | $8.00 | $9.00 | $7.25 | $42.41 | $9.00 |
| 0290 | Permanent construction signs (barricade mounted) (6051125) | SF | 94 | $8.95 | $8.00 | $9.00 | $8.95 | $13.80 | $9.00 |
| 0300 | Type B - flashing light (608100B) | EACH | 16 | $80.00 | $125.00 | $164.00 | $165.00 | $124.06 | $144.00 |
| 0310 | Pavement markings(temporary-paint)-4" white solid lines (609115A) | LF | 4,500 | $0.20 | $0.20 | $0.22 | $0.20 | $0.20 | $0.23 |
| 0320 | Pavement markings(temporary-paint)-4" yellow solid lines (609115B) | LF | 4,500 | $0.20 | $0.20 | $0.22 | $0.20 | $0.20 | $0.23 |
| 0330 | 4" white solid lines (PVT. edge lines) thermo.- 90 mil. (6271010) | LF | 4,500 | $0.75 | $0.75 | $0.83 | $0.76 | $0.75 | $0.86 |
| 0340 | 4" yellow solid lines(PVT.edge lines) thermo- 90 mil. (6271074) | LF | 4,500 | $0.75 | $0.75 | $0.83 | $0.76 | $0.75 | $0.86 |
| 0350 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 54 | $10.00 | $10.00 | $11.00 | $545.40 | $10.00 | $11.50 |
| 0360 | Furnish & install 2.0" schedule 80 PVC conduit (6750278) | LF | 1,588 | $15.00 | $17.00 | $15.00 | $14.00 | $11.00 | $18.00 |
| 0370 | Conc. for structures - class 4000 (7011400) | CY | 808.10 | $1,455.00 | $1,100.00 | $1,300.00 | $1,100.00 | $1,835.00 | $1,587.00 |
| 0380 | Grooved surface finish (7023200) | SY | 1,422.20 | $4.65 | $25.00 | $8.00 | $10.00 | $7.00 | $6.00 |
| 0390 | Reinf. steel for structures (bridge) (7031200) | LB | 205,975 | $1.75 | $1.50 | $1.38 | $1.50 | $1.55 | $2.00 |
| 0400 | Hoop reinforcing steel for structures (bridge) (7031220) | LB | 10,943 | $3.25 | $3.00 | $2.73 | $3.00 | $3.30 | $7.00 |
| 0410 | Prestressed concrete florida I-beam(45") (7045445) | LF | 1,752 | $475.00 | $480.00 | $400.00 | $340.00 | $450.00 | $480.00 |
| 0420 | 42" MASH concrete barrier parapet/railing wall (7051050) | LF | 792 | $100.00 | $125.00 | $110.00 | $85.00 | $136.85 | $108.00 |
| 0430 | Pile driving set-UP (7110010) | EACH | 12 | $2,500.00 | $5,000.00 | $6,140.00 | $8,000.00 | $8,000.00 | $6,688.00 |
| 0440 | Reinf. pile tips (HP14 X 73) (7111560) | EACH | 12 | $500.00 | $250.00 | $200.00 | $250.00 | $300.00 | $197.00 |
| 0450 | Steel H bearing piling (HP14 X 73) (7112220) | LF | 380 | $68.75 | $70.00 | $96.00 | $50.00 | $85.00 | $93.00 |
| 0460 | Drilled shaft set-UP (7120006) | EACH | 6 | $4,500.00 | $30,000 | $20,000 | $20,000 | $55,000 | $6,912.00 |
| 0470 | Crosshole sonic logging setup (7120010) | EACH | 6 | $2,850.00 | $3,000.00 | $665.00 | $3,300.00 | $6,500.00 | $4,511.00 |
| 0480 | Drilled shaft with rock excavation - 48" diameter (7120162) | LF | 136 | $2,220.00 | $600.00 | $1,900.00 | $332.24 | $1,100.00 | $336.00 |
| 0490 | Drilled shaft with wet & dry excavation - 54" diameter (7120171) | LF | 179 | $1,000.00 | $1,600.00 | $1,000.00 | $1,646.17 | $1,100.00 | $1,803.00 |
| 0500 | Construction casing - 54" diameter (7120175) | LF | 179 | $525.00 | $500.00 | $540.00 | $398.71 | $600.00 | $461.00 |
| 0510 | 18" smooth wall pipe (7143618) | LF | 48 | $125.00 | $145.00 | $100.00 | $180.00 | $122.00 | $199.00 |
| 0520 | 4' slope flume (6" curb style with cutoffs) (7199200) | LF | 64 | $350.00 | $495.00 | $362.00 | $297.63 | $110.00 | $275.00 |
| 0530 | Concrete curb and gutter(2'-0") vertical face (7203210) | LF | 129 | $98.00 | $88.00 | $78.00 | $56.64 | $40.00 | $105.00 |
| 0540 | Compression seal joint (7232320) | LF | 77.70 | $90.00 | $100.00 | $76.00 | $200.00 | $150.00 | $171.00 |
| 0550 | Elastomeric bearing (7243100) | EACH | 40 | $500.00 | $350.00 | $1,390.00 | $1,200.00 | $500.00 | $1,025.00 |
| 0560 | Waterproofing (7282000) | SY | 25.90 | $105.00 | $120.00 | $109.00 | $170.00 | $65.00 | $122.00 |
| 0570 | Aggregate underdrain(agg#789)with 4"perf.pipe for struc (8011210) | TON | 136 | $90.00 | $65.00 | $89.00 | $90.00 | $100.00 | $121.00 |
| 0580 | 12" temporary pipe slope drain (8034120) | LF | 205 | $25.00 | $25.00 | $49.00 | $40.00 | $45.00 | $53.00 |
| 0590 | Rip-rap (class A) (8041010) | TON | 239 | $82.00 | $82.00 | $113.00 | $120.00 | $95.00 | $104.00 |
| 0600 | Rip-rap (class B) (8041020) | TON | 1,091 | $82.00 | $82.00 | $109.00 | $120.00 | $95.00 | $97.00 |
| 0610 | Rip-rap (class C) (8041030) | TON | 280 | $95.00 | $95.00 | $101.00 | $120.00 | $100.00 | $98.00 |
| 0620 | Geotextile for erosion control under riprap(class 1)type A (8048100) | SY | 1,685 | $3.50 | $3.50 | $5.40 | $11.50 | $9.00 | $12.00 |
| 0630 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 1,523 | $3.50 | $3.50 | $5.40 | $10.75 | $9.00 | $8.00 |
| 0640 | MT3 leading end treatment TL3 (8051151) | EACH | 4 | $3,200.00 | $3,200.00 | $3,500.00 | $3,800.00 | $3,278.16 | $3,571.00 |
| 0650 | MGS3 GR standard shoulder (8052100) | LF | 1,287.50 | $21.50 | $21.50 | $26.00 | $26.50 | $24.60 | $28.00 |
| 0660 | MTBBC3 MASH thrie-beam barrier connector TL3 (8053253) | EACH | 4 | $3,000.00 | $3,000.00 | $3,400.00 | $3,400.00 | $3,232.29 | $3,830.00 |
| 0670 | Flume inlet at guardrail (handwork) (8053257) | EACH | 2 | $3,000.00 | $4,400.00 | $5,800.00 | $4,737.36 | $1,800.00 | $4,891.00 |
| 0680 | Non-mow strip under guardrail (8055250) | SY | 104 | $122.00 | $125.00 | $95.00 | $128.73 | $80.00 | $129.00 |
| 0690 | Woven wire fence - type 1 with 1 strand barbed (8061110) | LF | 1,114 | $9.50 | $12.00 | $10.00 | $20.00 | $21.10 | $19.00 |
| 0700 | Temporary barrier fence (orange) (8068301) | LF | 2,325 | $3.00 | $4.00 | $3.56 | $3.05 | $5.25 | $4.00 |
| 0710 | Moving item no. 01 (8081000) | LS | 1 | $2,500.00 | $2,500.00 | $11,000 | $1.00 | $3,342.00 | $6,168.00 |
| 0720 | Right of way marker(rebar and cap) (8091010) | EACH | 12 | $120.00 | $200.00 | $240.00 | $150.00 | $150.00 | $231.00 |
| 0730 | Right of way plat (8091050) | LS | 1 | $3,475.00 | $5,000.00 | $1,750.00 | $5,000.00 | $5,500.00 | $5,760.00 |
| 0740 | Permanent cover (8100100) | ACRE | 3.30 | $1,700.00 | $2,200.00 | $1,540.00 | $1,319.92 | $3,500.00 | $2,132.00 |
| 0750 | Temporary cover (8100200) | ACRE | 6.60 | $1,300.00 | $1,250.00 | $1,070.00 | $1,167.62 | $2,000.00 | $1,439.00 |
| 0760 | Compost (8101105) | CY | 89 | $50.00 | $120.00 | $15.00 | $50.77 | $85.50 | $44.00 |
| 0770 | Fertilizer (nitrogen) (8104005) | LB | 990 | $4.00 | $3.55 | $2.20 | $3.05 | $24.00 | $2.60 |
| 0780 | Fertilizer (phosphoric acid) (8104010) | LB | 990 | $4.00 | $3.55 | $2.20 | $3.05 | $24.00 | $2.60 |
| 0790 | Fertilizer (potash) (8104015) | LB | 990 | $4.00 | $3.55 | $2.20 | $3.05 | $24.00 | $2.60 |
| 0800 | Agricultural granular lime (8105005) | LB | 6,600 | $0.11 | $0.50 | $1.08 | $0.40 | $1.50 | $0.81 |
| 0810 | Selective watering (8109050) | GAL | 54,300 | $0.11 | $0.10 | $0.06 | $0.08 | $0.25 | $0.17 |
| 0820 | Mowing (8109901) | ACRE | 19.80 | $250.00 | $550.00 | $450.00 | $406.13 | $1,500.00 | $346.00 |
| 0830 | Turf reinforcement matting (TRM) type 1 (8151101) | MSY | 3.50 | $4,000.00 | $4,900.00 | $4,500.00 | $3,756.70 | $3,800.00 | $6,570.00 |
| 0840 | Temporary erosion control blanket (ecb) (8151110) | MSY | 5.08 | $1,700.00 | $1,600.00 | $2,500.00 | $1,624.52 | $2,800.00 | $1,619.00 |
| 0850 | Hydraulic erosion control product (hecp) - type 1 (8151201) | ACRE | 1.95 | $1,700.00 | $2,500.00 | $1,200.00 | $1,345.30 | $4,500.00 | $1,843.00 |
| 0860 | Hydraulic erosion control product (hecp) - type 3 (8151203) | ACRE | 7.95 | $3,400.00 | $4,200.00 | $3,600.00 | $2,944.44 | $4,500.00 | $4,147.00 |
| 0870 | Silt fence (8153000) | LF | 2,160 | $3.00 | $4.00 | $4.00 | $3.30 | $4.75 | $3.25 |
| 0880 | Replace/repair silt fence (8153090) | LF | 216 | $3.00 | $6.50 | $4.00 | $4.32 | $4.75 | $4.30 |
| 0890 | Silt basins (8154000) | CY | 678 | $16.00 | $16.00 | $10.00 | $20.82 | $35.00 | $30.00 |
| 0900 | Cleaning silt basins (8154010) | CY | 713 | $18.00 | $18.00 | $27.00 | $20.51 | $30.00 | $78.00 |
| 0910 | Removal of silt retained by silt fence (8154050) | LF | 750 | $6.00 | $6.00 | $1.71 | $11.35 | $4.00 | $4.78 |
| 0920 | Inlet filter cleaning (8154155) | EACH | 4 | $150.00 | $560.00 | $290.00 | $709.43 | $250.00 | $250.00 |
| 0930 | Inlet structure filter - type B (8156210) | EACH | 14 | $250.00 | $250.00 | $200.00 | $776.81 | $355.00 | $415.00 |
| 0940 | Aggregate no.5 or 57 for erosion control (8156410) | TON | 100 | $65.00 | $65.00 | $85.00 | $112.84 | $100.00 | $89.00 |
| 0950 | Stabilized construction entrance (8156490) | SY | 1,100 | $15.00 | $17.00 | $24.00 | $32.07 | $20.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of March 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.