SCDOT contract 3276951 bid tabulation
Replace the existing culvert along S-59 (Devils Backbone Rd. Let by South Carolina DOT on August 11, 2026, Lexington, District 1. 11 bids received; low bid $1,288,582 by Site-Prep, Inc. of NC.
- Owner
- South Carolina DOT
- Letting
- 11 AUG 2026
- Pay items
- 49
- Data through
- 13 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Site-Prep, Inc. of NC | $1,288,582 | Low |
| 2 | Integrated Site Solutions LLC | $1,421,935 | +10% |
| 3 | Coogler Construction, Inc. | $1,499,115 | +16% |
| 4 | Cherokee, Inc. | $1,521,843 | +18% |
| 5 | Aos Specialty Contractors, Inc. | $1,629,262 | +26% |
| 6 | Crescent Industries, LLC | $1,644,981 | +28% |
| 7 | Palmetto Sitework Services, LLC | $1,798,308 | +40% |
| 8 | Lindlers Construction of South Carolina, | $1,835,994 | +42% |
| 9 | Palmetto Corp. of Conway | $1,970,306 | +53% |
| 10 | L-J, Inc. | $1,979,872 | +54% |
| 11 | Ipw Construction Group, LLC | $2,219,101 | +72% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Site-Prep, Inc. of NC | 2. Integrated Site Solutions LLC | 3. Coogler Construction, Inc. | 4. Cherokee, Inc. | 5. Aos Specialty Contractors, Inc. | 6. Crescent Industries, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Mobilization (1031000) | LS | 1 | $45,200 | $80,000 | $375,000 | $77,500 | $80,190 | $108,000 |
| 0020 | Bonds and insurance (1032010) | LS | 1 | $23,650 | $45,000 | $16,270 | $30,500 | $24,514 | $35,000 |
| 0030 | Construction stakes, lines & grades (1050800) | EACH | 1 | $12,760 | $10,000 | $20,000 | $16,500 | $22,804 | $15,000 |
| 0040 | Utility staking (1052001) | LS | 1 | $5,500.00 | $10,000 | $15,000 | $3,500.00 | $17,103 | $10,000 |
| 0050 | Clearing & grubbing within roadway (2012000) | LS | 1 | $37,620 | $28,000 | $65,000 | $150,000 | $163,315 | $22,000 |
| 0060 | Selected clearing (no grubbing) (2016005) | ACRE | 0.15 | $42,825 | $100,000 | $64,935 | $250,000 | $166,585 | $97,403 |
| 0070 | Removal & disposal item no. 01 (2022000) | LS | 1 | $3,500.00 | $30,000 | $3,000.00 | $8,000.00 | $3,991.00 | $5,000.00 |
| 0080 | Removal & disposal of existing asphalt pavement (2025000) | SY | 160 | $49.00 | $10.00 | $31.25 | $35.00 | $93.00 | $37.50 |
| 0090 | Removal of exist. guardrail (2027801) | LF | 278 | $1.41 | $10.00 | $75.00 | $2.00 | $5.00 | $26.98 |
| 0100 | Unclassified excavation (2031000) | CY | 4,181 | $37.50 | $30.00 | $25.00 | $40.00 | $33.00 | $31.09 |
| 0110 | Borrow excavation (2033000) | CY | 1,517 | $53.00 | $40.00 | $35.00 | $35.00 | $33.00 | $36.26 |
| 0120 | Muck excavation (2034000) | CY | 4,854 | $32.00 | $40.00 | $51.00 | $50.00 | $73.00 | $41.20 |
| 0130 | Geotextile, separation (2036020) | SY | 301 | $3.30 | $10.00 | $9.00 | $5.00 | $5.00 | $19.93 |
| 0140 | Structure excavation for culverts (2041000) | CY | 1,015 | $23.50 | $40.00 | $20.00 | $35.00 | $52.00 | $101.48 |
| 0150 | No. 57 stone for backfill (2052000) | TON | 95 | $112.00 | $100.00 | $63.53 | $75.00 | $128.00 | $136.84 |
| 0160 | Fine grading (2081001) | SY | 178 | $63.00 | $20.00 | $15.00 | $30.00 | $69.00 | $16.85 |
| 0170 | Flowable fill (2103000) | CY | 9.60 | $220.00 | $400.00 | $350.00 | $400.00 | $795.00 | $416.67 |
| 0180 | Maintenance stone (3059900) | TON | 10 | $38.25 | $100.00 | $114.00 | $60.00 | $83.00 | $200.00 |
| 0190 | Liquid asphalt binder PG64-22 (4011004) | TON | 9 | $825.00 | $900.00 | $840.00 | $750.00 | $2,280.00 | $722.22 |
| 0200 | Milling existing asphalt pavement (variable) (4013990) | SY | 734 | $16.90 | $15.00 | $6.14 | $10.00 | $24.00 | $14.99 |
| 0210 | Asphalt base course - type B (4020320) | TON | 43 | $204.33 | $305.00 | $250.00 | $265.00 | $285.00 | $197.67 |
| 0220 | Asphalt intermediate course type C (4030330) | TON | 18 | $204.33 | $330.00 | $423.00 | $265.00 | $285.00 | $250.00 |
| 0230 | Asphalt surface course type D (4040350) | TON | 67 | $133.65 | $330.00 | $276.25 | $275.00 | $285.00 | $201.49 |
| 0240 | Driveway paving-surface type D (4047230) | TON | 18 | $133.65 | $330.00 | $2,050.00 | $330.00 | $285.00 | $250.00 |
| 0250 | Traffic control (6011000) | LS | 1 | $35,000 | $25,000 | $20,000 | $30,000 | $20,523 | $60,000 |
| 0260 | Barricade - type III (6041200) | LF | 84 | $10.30 | $90.00 | $46.00 | $25.00 | $28.00 | $35.71 |
| 0270 | Permanent construction signs (ground mounted) (6051120) | SF | 128 | $6.60 | $25.00 | $45.00 | $8.25 | $7.00 | $70.31 |
| 0280 | Permanent construction signs (barricade mounted) (6051125) | SF | 70 | $9.35 | $25.00 | $18.00 | $8.25 | $9.00 | $78.57 |
| 0290 | Type B - flashing light (608100B) | EACH | 16 | $104.50 | $200.00 | $210.00 | $50.00 | $142.00 | $281.25 |
| 0300 | Permanent yellow pavement markers BI-dir.- 4"X4" (6301100) | EACH | 12 | $11.00 | $25.00 | $25.00 | $20.00 | $11.00 | $125.00 |
| 0310 | Conc. for structures - class 4000(culvert) (7011402) | CY | 43.60 | $3,168.00 | $1,500.00 | $95.00 | $2,200.00 | $2,540.00 | $1,490.83 |
| 0320 | Reinf. steel for structures (roadway) (7031100) | LB | 8,434 | $2.75 | $3.00 | $0.64 | $3.35 | $3.50 | $4.15 |
| 0330 | 18" smooth wall pipe (7143618) | LF | 64 | $88.50 | $200.00 | $125.00 | $95.00 | $179.00 | $281.25 |
| 0340 | 9'X 9' P.C. box culvert {AASHTO M-259} FH = 10 (7223259) | LF | 148 | $2,486.00 | $2,900.00 | $2,100.00 | $2,500.00 | $1,997.00 | $3,175.68 |
| 0350 | Rip-rap (class C) (8041030) | TON | 144 | $169.00 | $200.00 | $74.27 | $150.00 | $139.00 | $263.89 |
| 0360 | Geotextile for erosion control under riprap(class 2)type C (8048210) | SY | 254 | $3.30 | $12.00 | $10.00 | $5.00 | $5.00 | $25.59 |
| 0370 | MT3 leading end treatment TL3 (8051151) | EACH | 3 | $3,550.00 | $3,500.00 | $3,206.51 | $3,070.00 | $4,047.00 | $8,000.00 |
| 0380 | MT2 leading end treatment TL2 (8051155) | EACH | 1 | $3,012.00 | $3,200.00 | $2,706.72 | $2,590.00 | $3,648.00 | $7,500.00 |
| 0390 | MGS3 GR standard shoulder (8052100) | LF | 150 | $31.20 | $35.00 | $28.09 | $27.00 | $29.00 | $90.00 |
| 0400 | MGS3CS GR compressed shoulder (8052150) | LF | 150 | $47.40 | $47.00 | $42.64 | $41.00 | $36.00 | $110.00 |
| 0410 | Temporary barrier fence (orange) (8068301) | LF | 350 | $3.20 | $10.00 | $5.25 | $4.00 | $2.20 | $12.86 |
| 0420 | Right of way marker(rebar and cap) (8091010) | EACH | 11 | $220.00 | $500.00 | $175.00 | $200.00 | $311.00 | $272.73 |
| 0430 | Right of way plat (8091050) | LS | 1 | $2,750.00 | $5,000.00 | $5,500.00 | $4,000.00 | $3,421.00 | $6,500.00 |
| 0440 | Permanent grassing for non-permitted resurfacing projects (8100102) | ACRE | 0.70 | $4,592.00 | $6,000.00 | $5,000.00 | $4,500.00 | $3,990.00 | $21,429 |
| 0450 | Silt fence (8153000) | LF | 2,000 | $3.76 | $7.00 | $4.75 | $5.00 | $3.00 | $7.50 |
| 0460 | Replace/repair silt fence (8153090) | LF | 200 | $4.88 | $20.00 | $4.75 | $5.00 | $4.50 | $12.50 |
| 0470 | Floating turbidity barrier- light duty(10'depth) (8153110) | LF | 150 | $36.03 | $40.00 | $25.00 | $40.00 | $85.00 | $53.33 |
| 0480 | Removal of silt retained by silt fence (8154050) | LF | 500 | $2.10 | $15.00 | $4.00 | $3.00 | $5.00 | $10.00 |
| 0490 | Stabilized construction entrance (8156490) | SY | 550 | $20.00 | $18.00 | $25.00 | $19.00 | $23.00 | $36.36 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from SCDOT's tabulation for this contract. SCDOT Tabulation of Bids PDFs, one per contract, from its public bid tabulation library, January 2022 to October 2026, with bidder names from each contract's vendor ranking. Bids that did not match their published total are left out.
Every contract let that day: SCDOT letting of August 11, 2026. Compiled by Mirage Metrics.