TDOT contract CN261073 bid tabulation
The concrete pavement repair on i-75 from the i-40 eastbound exit ramp (l.m. 0.00) to the bridge over papermill drive (l.m. 0.30). Let by Tennessee DOT on October 2, 2026, Knox County. 4 bids received; low bid $843,886 by Bluegrass Contracting Corporation.
- Owner
- Tennessee DOT
- Letting
- 02 OCT 2026
- Pay items
- 25
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bluegrass Contracting Corporation | $843,886 | Low |
| 2 | Mid-State Construction Company, Inc. | $990,831 | +17% |
| 3 | APAC-Atlantic, Inc. | $1,003,543 | +19% |
| 4 | Southern Constructors, Inc. | $1,087,527 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bluegrass Contracting Corporation | 2. Mid-State Construction Company, Inc. | 3. APAC-Atlantic, Inc. | 4. Southern Constructors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Brooming & degrassing shoulders (208-01.05) | LM | 1 | $6,000.00 | $8,379.29 | $4,750.00 | $2,000.00 |
| 2 | Bituminous material for tack coat (TC) (403-01) | TON | 2 | $1,400.00 | $1,540.00 | $1,400.00 | $1,200.00 |
| 3 | Acs mix(PG76-22) grading D (411-03.10) | TON | 164 | $360.00 | $396.00 | $360.00 | $550.00 |
| 4 | Cold planing bituminous pavement (415-01.01) | TON | 162 | $250.00 | $275.00 | $250.00 | $250.00 |
| 5 | Full depth PCC pavement repair high early (502-03.25) | CY | 130 | $870.00 | $1,804.26 | $1,445.00 | $1,300.00 |
| 6 | Sawing concrete pavement (full depth) (502-04.01) | LF | 1,114 | $11.25 | $13.04 | $30.00 | $10.00 |
| 7 | Load transfer dowels (502-04.02) | EACH | 402 | $20.00 | $36.80 | $18.00 | $50.00 |
| 8 | Transverse tie-bars (502-04.03) | EACH | 242 | $23.50 | $36.72 | $22.00 | $40.00 |
| 9 | Resealing joints (silicone sealant) (502-08.02) | LF | 875 | $13.00 | $6.62 | $20.00 | $9.00 |
| 10 | Sealing shoulder joints (502-08.03) | LF | 285 | $8.00 | $13.41 | $10.00 | $45.00 |
| 11 | Sawing concrete joints (502-25) | LF | 120 | $6.00 | $13.89 | $9.00 | $12.00 |
| 12 | Grinding concrete pavement (503-01) | SY | 4,224 | $10.75 | $12.26 | $7.65 | $8.00 |
| 13 | Traffic control (712-01) | LS | 1 | $113,500 | $122,895 | $86,250 | $180,000 |
| 14 | Interconnected portable barrier rail (712-02.02) | LF | 3,488 | $55.00 | $40.00 | $59.00 | $50.00 |
| 15 | Remove and relocate portable barrier rail (712-02.36) | LF | 3,488 | $29.00 | $5.31 | $20.00 | $25.00 |
| 16 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 2 | $8,350.00 | $6,820.00 | $9,885.00 | $10,000 |
| 17 | Flexible drums (channelizing) (712-04.01) | EACH | 488 | $25.00 | $35.20 | $39.00 | $60.00 |
| 18 | Barrier rail delineator (712-04.50) | EACH | 31 | $12.50 | $8.75 | $20.00 | $25.00 |
| 19 | Warning lights (type A) (712-05.01) | EACH | 244 | $20.50 | $11.00 | $17.00 | $35.00 |
| 20 | Signs (construction) (712-06) | SF | 1,465 | $5.50 | $8.09 | $8.50 | $15.00 |
| 21 | Arrow board (type C) (712-08.03) | EACH | 2 | $900.00 | $880.00 | $900.00 | $4,000.00 |
| 22 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 6,281 | $4.50 | $4.18 | $5.00 | $5.00 |
| 23 | Changeable message sign unit (713-16.01) | EACH | 2 | $5,000.00 | $7,260.00 | $8,150.00 | $8,000.00 |
| 24 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 1 | $7,500.00 | $8,580.00 | $9,100.00 | $9,000.00 |
| 25 | Mobilization (717-01) | LS | 1 | $40,000 | $156,375 | $132,450 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.