TDOT contract CNZ100 bid tabulation
The interchange lighting on i-24 at joe b. jackson parkway (l.m. 20.26 - l.m. 20.94) (exit 84). Let by Tennessee DOT on March 21, 2025, Rutherford County. 1 bid received; low bid $1,585,152 by Stansell Electric Company, Inc..
- Owner
- Tennessee DOT
- Letting
- 21 MAR 2025
- Pay items
- 44
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Stansell Electric Company, Inc. | $1,585,152 | Low |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stansell Electric Company, Inc. |
|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $15,700 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $3,085.00 |
| 3 | Road & drainage excavation (unclassified) (203-01) | CY | 40 | $185.00 |
| 4 | 8" temporary slope drain (209-02.03) | LF | 1,320 | $18.50 |
| 5 | Temporary silt fence (with backing) (209-08.02) | LF | 4,525 | $6.50 |
| 6 | Filter sock check dam (209-08.09) | EACH | 1 | $373.00 |
| 7 | Sandbags (209-09.01) | BAG | 198 | $6.20 |
| 8 | Polyethylene sheeting (6 mil. minimum) (209-20.03) | SY | 1,464 | $2.60 |
| 9 | High-visibility construction fence (707-08.11) | LF | 4,625 | $2.20 |
| 10 | Machined rip-rap (class A-3) (709-05.05) | TON | 70 | $56.50 |
| 11 | Traffic control (712-01) | LS | 1 | $27,550 |
| 12 | Signs (construction) (712-06) | SF | 505 | $9.30 |
| 13 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,605.00 |
| 14 | Jacked or bored conduit (714-03) | LF | 1,530 | $43.50 |
| 15 | Direct burial conduit (2" PVC, schedule 40) (714-03.01) | LF | 17,480 | $9.00 |
| 16 | Conduit (structures - 1" RGS) (714-04.01) | LF | 300 | $36.50 |
| 17 | Pull boxes (type C) (714-05.04) | EACH | 31 | $734.00 |
| 18 | Cable (1/C # 8 AWG) (714-06.04) | LF | 2,250 | $1.80 |
| 19 | Cable (1/C # 6 AWG) (714-06.05) | LF | 46,014 | $1.90 |
| 20 | Cable (1/C # 4 AWG) (714-06.06) | LF | 7,566 | $2.90 |
| 21 | Cable (1/C # 8 bare) (714-06.08) | LF | 750 | $1.70 |
| 22 | Cable (1/C # 6 bare) (714-06.09) | LF | 15,338 | $2.30 |
| 23 | Cable (1/C # 4 bare) (714-06.10) | LF | 2,522 | $3.10 |
| 24 | Cable (1/C # 2/0 AWG) (714-06.11) | LF | 120 | $6.30 |
| 25 | Cable (1/C # 2/0 bare) (714-06.12) | LF | 40 | $6.30 |
| 26 | Cable (1/C # 3/0 AWG) (714-06.13) | LF | 1,650 | $7.70 |
| 27 | Cable (1/C # 3/0 bare) (714-06.14) | LF | 550 | $7.70 |
| 28 | Light standards (offset poles-44' M.H.) (714-08.09) | EACH | 23 | $4,340.00 |
| 29 | Light standards (highmast poles 150' M.H.) (714-08.10) | EACH | 2 | $62,900 |
| 30 | Light standards (highmast poles 100' M.H.) (714-08.11) | EACH | 8 | $35,850 |
| 31 | Foundation (only) for light standards (714-08.23) | EACH | 23 | $1,400.00 |
| 32 | Foundation for light standards - high mast (100' & 150' M.H.) (714-08.40) | EACH | 10 | $20,650 |
| 33 | Luminaires (206W LED 0FFSET light) (714-09.10) | EACH | 23 | $1,165.00 |
| 34 | Luminaires (295W LED high mast) (714-09.11) | EACH | 88 | $1,300.00 |
| 35 | Luminaires (72W LED underpass) (714-09.12) | EACH | 4 | $617.00 |
| 36 | Control center (no. 1) (714-12.01) | LS | 1 | $9,275.00 |
| 37 | Control center (no. 2) (714-12.02) | LS | 1 | $9,275.00 |
| 38 | Electrical connection (control center no. 1) (714-25.01) | LS | 1 | $2,205.00 |
| 39 | Electrical connection (control center no. 2) (714-25.02) | LS | 1 | $2,205.00 |
| 40 | Mobilization (717-01) | LS | 1 | $93,150 |
| 41 | Geotextile (type III)(erosion control) (740-10.03) | SY | 120 | $9.60 |
| 42 | Temporary sediment tube 8IN (740-11.01) | LF | 930 | $3.10 |
| 43 | Seeding (with mulch) (801-01) | UNIT | 25 | $46.00 |
| 44 | Water (seeding & sodding) (801-03) | MG | 3 | $249.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of March 21, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.