TDOT contract CNZ100 bid tabulation

The interchange lighting on i-24 at joe b. jackson parkway (l.m. 20.26 - l.m. 20.94) (exit 84). Let by Tennessee DOT on March 21, 2025, Rutherford County. 1 bid received; low bid $1,585,152 by Stansell Electric Company, Inc..

Owner
Tennessee DOT
Letting
21 MAR 2025
Pay items
44
Data through
02 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Stansell Electric Company, Inc.$1,585,152Low
TDOT contract CNZ100: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Stansell Electric Company, Inc.
1Construction stakes, lines and grades (105-01)LS1$15,700
2Clearing and grubbing (201-01)LS1$3,085.00
3Road & drainage excavation (unclassified) (203-01)CY40$185.00
48" temporary slope drain (209-02.03)LF1,320$18.50
5Temporary silt fence (with backing) (209-08.02)LF4,525$6.50
6Filter sock check dam (209-08.09)EACH1$373.00
7Sandbags (209-09.01)BAG198$6.20
8Polyethylene sheeting (6 mil. minimum) (209-20.03)SY1,464$2.60
9High-visibility construction fence (707-08.11)LF4,625$2.20
10Machined rip-rap (class A-3) (709-05.05)TON70$56.50
11Traffic control (712-01)LS1$27,550
12Signs (construction) (712-06)SF505$9.30
13Arrow board (type C) (712-08.03)EACH2$1,605.00
14Jacked or bored conduit (714-03)LF1,530$43.50
15Direct burial conduit (2" PVC, schedule 40) (714-03.01)LF17,480$9.00
16Conduit (structures - 1" RGS) (714-04.01)LF300$36.50
17Pull boxes (type C) (714-05.04)EACH31$734.00
18Cable (1/C # 8 AWG) (714-06.04)LF2,250$1.80
19Cable (1/C # 6 AWG) (714-06.05)LF46,014$1.90
20Cable (1/C # 4 AWG) (714-06.06)LF7,566$2.90
21Cable (1/C # 8 bare) (714-06.08)LF750$1.70
22Cable (1/C # 6 bare) (714-06.09)LF15,338$2.30
23Cable (1/C # 4 bare) (714-06.10)LF2,522$3.10
24Cable (1/C # 2/0 AWG) (714-06.11)LF120$6.30
25Cable (1/C # 2/0 bare) (714-06.12)LF40$6.30
26Cable (1/C # 3/0 AWG) (714-06.13)LF1,650$7.70
27Cable (1/C # 3/0 bare) (714-06.14)LF550$7.70
28Light standards (offset poles-44' M.H.) (714-08.09)EACH23$4,340.00
29Light standards (highmast poles 150' M.H.) (714-08.10)EACH2$62,900
30Light standards (highmast poles 100' M.H.) (714-08.11)EACH8$35,850
31Foundation (only) for light standards (714-08.23)EACH23$1,400.00
32Foundation for light standards - high mast (100' & 150' M.H.) (714-08.40)EACH10$20,650
33Luminaires (206W LED 0FFSET light) (714-09.10)EACH23$1,165.00
34Luminaires (295W LED high mast) (714-09.11)EACH88$1,300.00
35Luminaires (72W LED underpass) (714-09.12)EACH4$617.00
36Control center (no. 1) (714-12.01)LS1$9,275.00
37Control center (no. 2) (714-12.02)LS1$9,275.00
38Electrical connection (control center no. 1) (714-25.01)LS1$2,205.00
39Electrical connection (control center no. 2) (714-25.02)LS1$2,205.00
40Mobilization (717-01)LS1$93,150
41Geotextile (type III)(erosion control) (740-10.03)SY120$9.60
42Temporary sediment tube 8IN (740-11.01)LF930$3.10
43Seeding (with mulch) (801-01)UNIT25$46.00
44Water (seeding & sodding) (801-03)MG3$249.00
TDOT contract CNZ100: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.

Every contract let that day: TDOT letting of March 21, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy