TDOT contract CNZ272 bid tabulation
The repair of the bridge on i-240 over i-40, i-240 nb, u.s. 70 (s.r. 1), and ramps (l.m. 19.65). Let by Tennessee DOT on October 3, 2025, Shelby County. 3 bids received; low bid $1,792,966 by Bell & Associates Construction, LLC.
- Owner
- Tennessee DOT
- Letting
- 03 OCT 2025
- Pay items
- 36
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bell & Associates Construction, LLC | $1,792,966 | Low |
| 2 | Dement Construction Group, LLC | $1,799,750 | 0.0% |
| 3 | Thomson & Thomson, Inc. | $1,937,138 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bell & Associates Construction, LLC | 2. Dement Construction Group, LLC | 3. Thomson & Thomson, Inc. |
|---|---|---|---|---|---|---|
| 1 | Placing spreading soil for landscaping (203-04.01) | CY | 14 | $150.00 | $250.00 | $150.00 |
| 2 | Temporary silt fence (without backing) (209-08.03) | LF | 162 | $10.00 | $8.50 | $7.50 |
| 3 | Treated permeable base (313-03) | SY | 304 | $130.00 | $118.00 | $185.00 |
| 4 | Cleaning joints (502-01.02) | LF | 87 | $65.00 | $100.00 | $120.00 |
| 5 | Concrete pavement removal (502-03.13) | SY | 304 | $175.00 | $200.00 | $245.00 |
| 6 | Full depth PCC pavement repair high early (502-03.25) | CY | 85 | $1,750.00 | $2,000.00 | $2,150.00 |
| 7 | Sawing concrete pavement (full depth) (502-04.01) | LF | 155 | $10.00 | $13.00 | $95.00 |
| 8 | Load transfer dowels (502-04.02) | EACH | 192 | $60.00 | $100.00 | $65.00 |
| 9 | Resealing joints (hot poured elastic) (502-08.01) | LF | 219 | $30.00 | $10.00 | $7.50 |
| 10 | Steel bar reinforcement (bridges) (604-03.02) | LB | 38 | $10.00 | $12.00 | $4.50 |
| 11 | Class A concrete (wall) (604-03.07) | CY | 1 | $12,500 | $15,000 | $3,300.00 |
| 12 | Bridge end drains(2'X8') (604-04.03) | EACH | 2 | $1,500.00 | $750.00 | $4,000.00 |
| 13 | Expansion joint repairs (604-10.44) | LF | 44 | $200.00 | $200.00 | $235.00 |
| 14 | Bridge deck repairs (partial depth of slab) (604-10.50) | SY | 1 | $2,500.00 | $3,000.00 | $990.00 |
| 15 | Deck drains (clean) (610-10.45) | EACH | 17 | $250.00 | $200.00 | $2,000.00 |
| 16 | Type 1 thin epoxy overlay (epoxy-urethane) (617-04.01) | SY | 11,059 | $37.25 | $30.75 | $35.00 |
| 17 | Rubble stone rip-rap (grouted) (709-02.01) | CY | 1 | $2,500.00 | $1,000.00 | $1,500.00 |
| 18 | Machined rip-rap (class A-1) (709-05.06) | TON | 71 | $200.00 | $70.00 | $77.50 |
| 19 | Traffic control (712-01) | LS | 1 | $247,500 | $350,000 | $170,000 |
| 20 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 560 | $100.00 | $175.00 | $92.50 |
| 21 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 1 | $15,000 | $5,500.00 | $5,500.00 |
| 22 | Flexible drums (channelizing) (712-04.01) | EACH | 604 | $35.00 | $33.00 | $33.00 |
| 23 | Barrier rail delineator (712-04.50) | EACH | 277 | $13.50 | $12.50 | $12.50 |
| 24 | Warning lights (type A) (712-05.01) | EACH | 4 | $30.00 | $28.00 | $28.00 |
| 25 | Signs (construction) (712-06) | SF | 223.50 | $8.00 | $6.25 | $6.25 |
| 26 | Temporary barricades (type III) (712-07.03) | LF | 24 | $15.00 | $13.00 | $13.00 |
| 27 | Arrow board (type C) (712-08.03) | EACH | 1 | $1,500.00 | $650.00 | $650.00 |
| 28 | Portable queue warning system (712-08.14) | DAY | 16 | $2,650.00 | $2,500.00 | $2,500.00 |
| 29 | Truck-mounted & trailer-mounted attenuators (TMA) (712-08.25) | EACH | 2 | $20,000 | $46,400 | $12,200 |
| 30 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 59,218 | $5.75 | $4.00 | $8.00 |
| 31 | Temporary curb W/flexible delineator (712-12.10) | LF | 360 | $43.00 | $40.00 | $40.00 |
| 32 | Changeable message sign unit (713-16.01) | EACH | 5 | $10,000 | $3,500.00 | $3,500.00 |
| 33 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 3.60 | $16,500 | $15,300 | $15,300 |
| 34 | Mobilization (717-01) | LS | 1 | $165,000 | $179,780 | $250,000 |
| 35 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 109 | $8.00 | $12.00 | $12.00 |
| 36 | Sodding (new sod) (803-01) | SY | 40 | $40.00 | $20.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 3, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.