Faris Industries, Inc.: TxDOT bid record
Faris Industries, Inc. submitted 21 bids on Texas DOT contracts in the data, from 04 NOV 2020 to 07 JAN 2022, and was the low bidder on 1 of them (5%). When it was not low, its total sat a median +16% above the low bid.
- Owner
- Texas DOT
- Low bid volume
- $3,777,155
- Latest bid
- 07 JAN 2022
- Data through
- 19 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 2 | 0 | 0% |
| 2021 | 17 | 1 | 6% |
| 2022 | 2 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Corpus Christi District | 6 | 0 | 0% |
| Laredo District | 5 | 0 | 0% |
| San Antonio District | 4 | 1 | 25% |
| Yoakum District | 3 | 0 | 0% |
| Brownwood District | 2 | 0 | 0% |
| Austin District | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Temporary sediment control fence (install) | 506-7039 | LF | 19 | 11 (58%) | $2.90 | $4.00 |
| Reflectorized pavement marker type II-A-A | 672-7004 | EACH | 20 | 10 (50%) | $3.92 | $5.00 |
| TMA (stationary) | 505-7001 | DAY | 19 | 10 (53%) | $170.00 | $230.00 |
| Temporary sediment control fence (remove) | 506-7041 | LF | 19 | 9 (47%) | $0.67 | $1.00 |
| Reflectorized pavement marker type I-C | 672-7002 | EACH | 11 | 9 (82%) | $4.00 | $5.00 |
| Remove SM RD SN sup&AM | 644-7073 | EACH | 16 | 8 (50%) | $85.93 | $110.00 |
| Remove metal beam guard fence | 542-7001 | LF | 12 | 8 (67%) | $1.50 | $3.00 |
| Construction exits (remove) | 506-7024 | SY | 14 | 7 (50%) | $6.75 | $10.00 |
| Install small roadside sign support and assembly type 10BWG(1)SA(P) | 644-7001 | EACH | 13 | 7 (54%) | $550.00 | $710.00 |
| Vegetative watering | 168-7001 | MG | 13 | 7 (54%) | $14.58 | $29.97 |
| RC pipe (CL III)(18 in) | 464-7003 | LF | 9 | 7 (78%) | $54.00 | $82.44 |
| Removing structure (wingwall) | 496-7005 | EACH | 8 | 7 (88%) | $1,005.65 | $1,700.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Hunter Industries, LTD. | 17 | 14 of 17 |
| CK Newberry, LLC | 12 | 8 of 12 |
| Angel Brothers Holdings Corp. | 10 | 5 of 10 |
| Anderson Columbia Co., Inc. | 8 | 4 of 8 |
| J. Carroll Weaver, Inc. | 7 | 6 of 7 |
| Dean Word Company, LTD. | 6 | 5 of 6 |
| Texas Materials Group, Inc. | 5 | 3 of 5 |
| Salinas Construction Technologies, LTD. | 5 | 3 of 5 |
| Brannan Paving Co., LTD. | 5 | 3 of 5 |
| Tierra Lease Service, LLC | 4 | 3 of 4 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 07 JAN 2022 | 01223203 | Corpus Christi District | SH 239 Rehabilitate existing roadway from FM 81 to N INTERS. OF FM 2043 | 2 of 5 | $10,597,661 | +5.0% |
| 07 JAN 2022 | 01223206 | Laredo District | IH 35 Rehabilitate existing roadway from 3.055 MI N OF FM 133 to FM 133 (EFR) | 2 of 7 | $4,388,971 | 0.0% |
| 04 NOV 2021 | 11213207 | Laredo District | US 277 Grade,base,acp,surf,str,pav mrk from 0.72 MILES EAST OF SL 480 to 2.72 MILES EAST OF SL 480 | 3 of 3 | $6,491,106 | +18% |
| 04 NOV 2021 | 11213208 | Austin District | SH 71 Roadway rehabilitation/reconstruction with no add from SPUR 191 to BLANCO/BURNET C/L | 6 of 7 | $11,918,674 | +36% |
| 03 NOV 2021 | 11213016 | Yoakum District | FM 822 Surfacing/roadway restoration from CR 112 to SL 521 | 5 of 5 | $3,365,426 | +11% |
| 01 SEP 2021 | 09213027 | San Antonio District | FM 2924 Rehabilitate existing roadway from FM 791 to FM 99 | 4 of 6 | $7,909,116 | +8.0% |
| 01 SEP 2021 | 09213028 | San Antonio District | FM 1344 Hazard elimination & safety from FM 541 to 0.089 MI N OF CR 209 | 2 of 5 | $6,730,046 | +9.0% |
| 05 AUG 2021 | 08214206 | Corpus Christi District | IH0037 Rehabilitation of existing roadway from IH0037 FRONTAGE ROAD (WESTSIDE) to FM 234 TO CR 1400 (CR 40) | 8 of 8 | $1,720,385 | +32% |
| 04 AUG 2021 | 08214002 | Corpus Christi District | FM0081 Rehabilitation of existing roadway from US 181 to 359.04 FT WEST OF SH 123 ON FM 81 | 6 of 7 | $715,403 | +38% |
| 02 JUL 2021 | 07213227 | Corpus Christi District | FM 3162 Widen road - add shoulders from FM 534 to END OF STATE MAINTENANCE | 8 of 9 | $3,117,939 | +33% |
| 01 JUL 2021 | 07213005 | Laredo District | FM 2688 Base, acp, grad, str, pav mrks, signs from US 83 to 4.356 MILES WEST OF US 83 | 5 of 5 | $11,964,162 | +15% |
| 01 JUL 2021 | 07213014 | San Antonio District | RM 473 Hazard elimination & safety from 0.727 MI W OF RM 474 to RM 474 | 1 of 4 | $3,777,155 | Low, 1.0% under the second |
| 01 JUL 2021 | 07213022 | San Antonio District | FM 1283 Hazard elimination & safety from RED BLUFF LN to LAKE FOREST RD | 2 of 5 | $3,039,951 | +3.0% |
| 04 JUN 2021 | 06213208 | Yoakum District | FM 794 Widen roadway and install centerline rumble stri from 0.5 MI NORTH OF CR 235 to US 90A | 4 of 5 | $6,302,414 | +21% |
| 04 JUN 2021 | 06213213 | Laredo District | FM 624 Widen shldr, sealcoat, prof mrk on edge&ctr line from 13.624 MI W OF MCMULLEN CL to MCMULLEN CL | 9 of 10 | $6,894,425 | +24% |
| 03 JUN 2021 | 06213006 | Laredo District | SH 359 Widen road - add lanes and shoulders from 17.16 MILES EAST OF SL 20 to 18.9 MILES EAST OF SL 20 | 3 of 4 | $5,819,927 | +13% |
| 05 MAY 2021 | 05213020 | Brownwood District | SH 36 Resurface roadway from EASTLAND C/L to FM 1477 | 9 of 9 | $3,897,789 | +68% |
| 04 FEB 2021 | 02213007 | Corpus Christi District | SH 239 Rehabilitate existing roadway from 0.2 MI WEST OF FM 2442 to FM 81 | 3 of 7 | $8,013,424 | +7.0% |
| 04 FEB 2021 | 02213012 | Yoakum District | FM 609 Pavement repair and surfacing from 0.18 MI N. OF FM 2436 to 2.2 MI N. OF FM 2237 | 7 of 8 | $4,310,204 | +27% |
| 03 DEC 2020 | 12203209 | Brownwood District | US 87 Reconstruct existing roadway & landscape work from BRADY CREEK BRIDGE to .4 MILES WEST OF US 283 | 3 of 6 | $7,512,256 | +6.0% |
| 04 NOV 2020 | 11203029 | Corpus Christi District | FM 81 Rehab roadway and widen from SH 80 to SH 123 | 7 of 7 | $10,160,838 | +19% |
How this record was read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.