TxDOT contract A00064052 bid tabulation
Rehabilitate Existing Roadway, FM 2727 (SH 243 to FM 429). Let by Texas DOT on April 3, 2025, Kaufman, Dallas District. 9 bids received; low bid $16,864,509 by A. L. Helmcamp, Inc., -6.5% against the engineer's estimate of $18,042,938.
- Owner
- Texas DOT
- Letting
- 03 APR 2025
- Pay items
- 120
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | A. L. Helmcamp, Inc. | $16,864,509 | Low | -7.0% |
| 2 | Baker & Company Construction, LLC | $17,299,428 | +3.0% | -4.0% |
| 3 | A. K. Gillis & Sons, LLC | $17,377,791 | +3.0% | -4.0% |
| 4 | D. L. Lennon Incorporated - Contractor | $18,198,410 | +8.0% | +1.0% |
| 5 | Grey Sky Construction LLC | $19,665,213 | +17% | +9.0% |
| 6 | Texas Materials Group, Inc. | $20,543,921 | +22% | +14% |
| 7 | Granite Construction Company | $21,333,904 | +27% | +18% |
| 8 | Ed Bell Construction Company | $21,465,721 | +27% | +19% |
| 9 | Highway 19 Construction LLC | $22,786,829 | +35% | +26% |
Engineer's estimate: $18,042,938.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. A. L. Helmcamp, Inc. | 2. Baker & Company Construction, LLC | 3. A. K. Gillis & Sons, LLC | 4. D. L. Lennon Incorporated - Contractor | 5. Grey Sky Construction LLC | 6. Texas Materials Group, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 443.44 | $750.00 | $550.00 | $272.00 | $540.00 | $1,188.00 | $3,000.00 | $2,000.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 1,319 | $18.30 | $25.00 | $12.35 | $12.00 | $12.00 | $20.00 | $46.18 |
| 3 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 16,642 | $6.00 | $8.50 | $7.10 | $9.02 | $4.35 | $11.00 | $10.00 |
| 4 | Remove (19") TRT/untrt base & asphalt pavement (105-7039) | SY | 8,599 | $15.00 | $9.00 | $7.70 | $18.70 | $8.25 | $20.00 | $16.38 |
| 5 | Remove (0"-10") TRT/untrt base & asphalt pavement (105-7050) | SY | 2,904 | $11.75 | $8.00 | $8.90 | $18.65 | $7.25 | $20.00 | $9.11 |
| 6 | Excavation (roadway) (110-7001) | CY | 4,461 | $21.67 | $40.00 | $32.60 | $20.00 | $9.30 | $20.00 | $17.00 |
| 7 | Subgr widen (OC) (112-7001) | STA | 401.01 | $200.00 | $300.00 | $407.00 | $275.00 | $535.00 | $250.00 | $365.00 |
| 8 | Embankment (final)(OC)(type C) (132-7005) | CY | 8,950 | $30.00 | $35.00 | $31.60 | $20.00 | $12.25 | $30.00 | $32.00 |
| 9 | Backfill (type A or B) (134-7004) | STA | 449.44 | $300.00 | $280.00 | $238.00 | $300.00 | $490.00 | $250.00 | $285.00 |
| 10 | Road grader work (ord comp) (152-7001) | STA | 443.44 | $250.00 | $250.00 | $195.00 | $375.00 | $365.00 | $250.00 | $205.00 |
| 11 | Drill seed (permanent_rural_clay) (164-7010) | SY | 351,707 | $0.25 | $0.13 | $0.28 | $0.25 | $0.25 | $0.35 | $0.25 |
| 12 | Drill seed (temporary_warm_cool) (164-7015) | SY | 351,707 | $0.25 | $0.13 | $0.18 | $0.25 | $0.20 | $0.35 | $0.21 |
| 13 | Vegetative watering (168-7001) | TGL | 104,650 | $1.00 | $0.10 | $1.00 | $0.01 | $0.01 | $2.00 | $0.01 |
| 14 | FL BS (compacted in place)(type D GR 1-2) (6") (247-7056) | SY | 15,101 | $14.00 | $17.00 | $19.90 | $16.69 | $22.00 | $16.00 | $18.00 |
| 15 | FL BS (compacted in place)(type D GR 1-2) (10") (247-7102) | SY | 141,453 | $25.00 | $29.00 | $27.35 | $27.03 | $34.00 | $20.00 | $29.00 |
| 16 | Rework BS metal (type C)(10")(ord comp) (251-7053) | SY | 98,015 | $4.00 | $1.30 | $5.25 | $3.00 | $4.00 | $6.00 | $5.25 |
| 17 | Cement (275-7001) | TON | 893 | $295.00 | $245.00 | $275.00 | $216.00 | $230.00 | $265.00 | $260.00 |
| 18 | Cement TRT (existing material)(6") (275-7002) | SY | 136,200 | $3.00 | $2.20 | $5.22 | $3.00 | $4.00 | $6.00 | $2.60 |
| 19 | Cement TRT (new base)(6") (275-7010) | SY | 15,101 | $5.00 | $2.20 | $5.40 | $3.00 | $4.00 | $12.00 | $2.60 |
| 20 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 42,436 | $6.92 | $4.50 | $6.10 | $6.00 | $4.32 | $3.00 | $5.50 |
| 21 | Asphalt (CRS-2P) (316-7012) | GAL | 85,818 | $7.00 | $3.50 | $5.32 | $5.22 | $3.61 | $3.00 | $4.85 |
| 22 | Asphalt (RC-250) (316-7016) | GAL | 13,212 | $11.00 | $4.50 | $5.95 | $5.83 | $4.22 | $3.00 | $4.70 |
| 23 | Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071) | GAL | 19,811 | $7.00 | $4.50 | $8.25 | $5.56 | $3.86 | $3.00 | $5.05 |
| 24 | Aggregate (type-B, GR-3)(sac-B) (316-7171) | CY | 1,195 | $200.00 | $180.00 | $121.40 | $172.24 | $93.25 | $225.00 | $248.00 |
| 25 | Aggregate (type-B, GR-4)(sac-B) (316-7173) | CY | 1,361 | $190.00 | $180.00 | $121.40 | $162.25 | $83.25 | $225.00 | $220.00 |
| 26 | Aggregate (type-B, GR-5)(sac-B) (316-7175) | CY | 580 | $215.00 | $100.00 | $110.90 | $154.24 | $0.01 | $225.00 | $149.00 |
| 27 | Aggregate (type-L, GR-5)(sac-B) (316-7200) | CY | 580 | $215.00 | $150.00 | $121.00 | $154.24 | $63.00 | $225.00 | $149.00 |
| 28 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 23,345 | $145.00 | $140.00 | $144.85 | $135.95 | $145.00 | $160.00 | $151.00 |
| 29 | Temporary special shoring (403-7001) | SF | 2,604 | $60.00 | $50.00 | $21.90 | $5.00 | $65.00 | $65.00 | $34.63 |
| 30 | Riprap (concrete)(5 in) (432-7002) | CY | 74 | $850.00 | $660.00 | $880.00 | $625.00 | $625.00 | $650.00 | $1,038.00 |
| 31 | Riprap (mow strip)(4 in) (432-7013) | CY | 78 | $600.00 | $660.00 | $633.00 | $625.00 | $625.00 | $550.00 | $1,038.00 |
| 32 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 753 | $163.50 | $130.00 | $135.00 | $285.40 | $290.00 | $185.00 | $225.00 |
| 33 | Riprap (stone protection)(18 in) (432-7043) | CY | 1,651 | $225.50 | $130.00 | $132.70 | $285.40 | $290.00 | $170.00 | $225.00 |
| 34 | Rail (type T631) (450-7020) | LF | 362 | $95.00 | $80.00 | $85.00 | $102.45 | $152.00 | $250.00 | $107.00 |
| 35 | Concrete box culvert (4 FT X 3 FT)(extend) (462-7059) | LF | 10 | $769.00 | $1,000.00 | $632.50 | $975.00 | $975.00 | $1,000.00 | $900.00 |
| 36 | Concrete box culvert (5 FT X 2 FT)(extend) (462-7061) | LF | 30 | $798.00 | $1,100.00 | $688.00 | $1,075.00 | $1,075.00 | $1,100.00 | $945.00 |
| 37 | Concrete box culvert (5 FT X 3 FT)(extend) (462-7062) | LF | 6 | $825.00 | $1,200.00 | $825.00 | $1,125.00 | $1,125.00 | $1,200.00 | $1,025.00 |
| 38 | Concrete box culvert (6 FT X 3 FT)(extend) (462-7066) | LF | 15 | $880.00 | $1,200.00 | $908.00 | $1,175.00 | $1,175.00 | $1,500.00 | $1,050.00 |
| 39 | Concrete box culvert (6 FT X 4 FT)(extend) (462-7067) | LF | 33 | $915.00 | $1,300.00 | $963.00 | $1,225.00 | $1,225.00 | $1,600.00 | $1,250.00 |
| 40 | Concrete box culvert (8 FT X 6 FT)(extend) (462-7078) | LF | 28 | $975.00 | $1,500.00 | $1,045.00 | $1,375.00 | $1,375.00 | $2,000.00 | $1,700.00 |
| 41 | Concrete box culvert (10 FT X 5 FT)(extend) (462-7088) | LF | 19 | $1,250.00 | $1,500.00 | $1,320.00 | $1,400.00 | $1,400.00 | $2,000.00 | $2,125.00 |
| 42 | RC pipe (CL III)(18 in) (464-7003) | LF | 4,670 | $65.00 | $53.00 | $60.25 | $50.00 | $50.00 | $70.00 | $69.00 |
| 43 | RC pipe (CL III)(24 in) (464-7005) | LF | 1,228 | $95.00 | $90.00 | $85.00 | $85.00 | $85.00 | $95.00 | $160.00 |
| 44 | RC pipe (CL III)(30 in) (464-7007) | LF | 20 | $135.00 | $125.00 | $126.00 | $120.00 | $120.00 | $185.00 | $228.00 |
| 45 | RC pipe (CL III)(36 in) (464-7009) | LF | 40 | $150.00 | $175.00 | $156.00 | $165.00 | $165.00 | $200.00 | $327.00 |
| 46 | RC pipe (CL IV)(24 in) (464-7021) | LF | 90 | $135.00 | $110.00 | $108.00 | $105.00 | $105.00 | $165.00 | $183.00 |
| 47 | RC pipe (CL IV)(36 in) (464-7024) | LF | 30 | $158.00 | $220.00 | $194.00 | $200.00 | $200.00 | $185.00 | $344.00 |
| 48 | RC pipe (CL IV)(48 in) (464-7026) | LF | 13 | $175.00 | $350.00 | $532.00 | $330.00 | $330.00 | $350.00 | $459.00 |
| 49 | Headwall (CH - PW - 0) (diameter= 24 in) (466-7101) | EACH | 6 | $6,325.00 | $7,500.00 | $6,050.00 | $7,000.00 | $7,000.00 | $3,500.00 | $5,700.00 |
| 50 | Headwall (CH - PW - 0) (diameter= 36 in) (466-7105) | EACH | 4 | $8,000.00 | $11,000 | $9,625.00 | $10,000 | $10,000 | $5,500.00 | $9,200.00 |
| 51 | Headwall (CH - PW - S) (diameter= 36 in) (466-7120) | EACH | 2 | $8,500.00 | $12,000 | $10,175 | $11,000 | $11,000 | $5,500.00 | $9,795.00 |
| 52 | Headwall (CH - PW - S) (diameter= 48 in) (466-7122) | EACH | 2 | $9,000.00 | $15,000 | $14,025 | $14,000 | $14,000 | $12,500 | $16,000 |
| 53 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 2 | $30,000 | $35,000 | $29,840 | $33,000 | $33,000 | $30,000 | $30,000 |
| 54 | Wingwall (PW - 1) (HW=9 FT) (466-7179) | EACH | 2 | $43,000 | $48,000 | $50,490 | $46,000 | $46,000 | $35,000 | $51,000 |
| 55 | Wingwall (PW - 2) (HW=5 FT) (466-7189) | EACH | 8 | $15,000 | $20,000 | $14,850 | $19,000 | $19,000 | $25,000 | $11,250 |
| 56 | Wingwall (PW - 2) (HW=6 FT) (466-7190) | EACH | 2 | $17,500 | $24,000 | $16,885 | $23,000 | $23,000 | $30,000 | $18,000 |
| 57 | Wingwall (PW - 2) (HW=7 FT) (466-7191) | EACH | 2 | $20,000 | $35,000 | $30,745 | $33,000 | $33,000 | $35,000 | $22,900 |
| 58 | Wingwall (PW - 2) (HW=8 FT) (466-7192) | EACH | 2 | $22,500 | $45,000 | $35,750 | $43,000 | $43,000 | $42,500 | $30,000 |
| 59 | Wingwall (SW - 0) (HW=3 FT) (466-7202) | EACH | 2 | $12,000 | $6,500.00 | $10,750 | $6,000.00 | $6,000.00 | $21,000 | $5,700.00 |
| 60 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 353 | $1,000.00 | $900.00 | $980.00 | $825.00 | $825.00 | $1,000.00 | $1,000.00 |
| 61 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 4 | $1,200.00 | $1,200.00 | $1,820.00 | $1,100.00 | $1,100.00 | $1,500.00 | $2,050.00 |
| 62 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 89 | $1,500.00 | $1,400.00 | $1,460.00 | $1,300.00 | $1,300.00 | $1,500.00 | $2,500.00 |
| 63 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 2 | $2,500.00 | $2,600.00 | $2,850.00 | $2,500.00 | $2,500.00 | $3,500.00 | $3,950.00 |
| 64 | Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368) | EACH | 4 | $6,917.00 | $6,900.00 | $6,000.00 | $6,500.00 | $6,500.00 | $4,000.00 | $6,250.00 |
| 65 | Clean existing culverts (480-7001) | EACH | 19 | $1,600.00 | $1,300.00 | $2,010.00 | $1,200.00 | $1,200.00 | $1,500.00 | $1,150.00 |
| 66 | Removing structure (set) (496-7004) | EACH | 38 | $500.00 | $160.00 | $450.00 | $150.00 | $150.00 | $500.00 | $625.00 |
| 67 | Removing structure (wingwall) (496-7005) | EACH | 20 | $1,665.00 | $1,100.00 | $3,040.00 | $1,000.00 | $1,000.00 | $2,500.00 | $1,100.00 |
| 68 | Removing structure (headwall) (496-7006) | EACH | 22 | $1,362.00 | $1,100.00 | $770.00 | $1,000.00 | $1,000.00 | $2,500.00 | $1,100.00 |
| 69 | Removing structure (pipe) (496-7007) | LF | 226 | $29.57 | $11.00 | $75.00 | $10.00 | $10.00 | $50.00 | $33.00 |
| 70 | Mobilization (500-7001) | LS | 1 | $1,607,540 | $1,000,000 | $677,000 | $1,291,375 | $1,137,458 | $1,900,000 | $1,866,711 |
| 71 | Barricades, signs and traffic handling (502-7001) | MO | 24 | $15,000 | $16,000 | $14,573 | $10,450 | $5,684.02 | $12,500 | $21,000 |
| 72 | Portable changeable message sign (503-7002) | EACH | 3 | $7,500.00 | $12,000 | $11,000 | $19,500 | $15,000 | $20,000 | $28,000 |
| 73 | TMA (stationary) (505-7001) | DAY | 381 | $267.00 | $250.00 | $305.00 | $200.00 | $250.00 | $250.00 | $375.00 |
| 74 | TMA (mobile operation) (505-7003) | DAY | 40 | $183.12 | $250.00 | $1,505.00 | $200.00 | $250.00 | $550.00 | $1.00 |
| 75 | Rock filter dams (install) (type 1) (506-7001) | LF | 210 | $50.00 | $41.00 | $44.00 | $70.00 | $50.00 | $50.00 | $115.00 |
| 76 | Rock filter dams (install) (type 3) (506-7003) | LF | 315 | $65.00 | $77.00 | $88.00 | $105.00 | $80.00 | $50.00 | $82.00 |
| 77 | Rock filter dams (remove) (506-7011) | LF | 525 | $10.00 | $12.00 | $22.00 | $15.00 | $10.00 | $20.00 | $13.00 |
| 78 | Construction exits (install) (type 1) (506-7020) | SY | 164 | $30.00 | $20.00 | $55.00 | $30.00 | $50.00 | $40.00 | $41.00 |
| 79 | Construction exits (remove) (506-7024) | SY | 164 | $15.00 | $5.00 | $11.00 | $10.00 | $10.00 | $20.00 | $10.75 |
| 80 | Temporary sediment control fence (install) (506-7039) | LF | 4,741 | $3.00 | $3.20 | $3.60 | $5.00 | $5.00 | $4.00 | $4.50 |
| 81 | Temporary sediment control fence (remove) (506-7041) | LF | 4,741 | $1.00 | $1.00 | $1.10 | $2.00 | $1.00 | $2.00 | $1.10 |
| 82 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 3,292 | $6.00 | $3.70 | $3.15 | $8.00 | $8.00 | $18.00 | $5.85 |
| 83 | Biodegradable erosion control logs (remove) (506-7046) | LF | 3,292 | $1.00 | $1.00 | $1.10 | $1.00 | $1.00 | $9.00 | $1.15 |
| 84 | One-way traffic control (port traffic signal) (510-7003) | MO | 2 | $7,878.00 | $7,500.00 | $14,850 | $9,500.00 | $9,500.00 | $8,500.00 | $8,000.00 |
| 85 | Portable concrete traffic barrier (furnish and install)(F-shape)(type 1) (512-7005) | LF | 180 | $55.00 | $86.00 | $101.00 | $55.00 | $81.00 | $100.00 | $88.00 |
| 86 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 540 | $30.00 | $35.00 | $55.00 | $35.00 | $25.00 | $20.00 | $20.00 |
| 87 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 180 | $20.00 | $65.00 | $72.70 | $55.00 | $35.00 | $20.00 | $30.00 |
| 88 | Driveways (concrete) (hes) (530-7007) | SY | 1,366 | $150.00 | $110.00 | $236.50 | $100.00 | $115.00 | $100.00 | $220.00 |
| 89 | Driveways (ACP) (530-7010) | SY | 16,744 | $50.00 | $75.00 | $52.50 | $78.78 | $68.00 | $35.00 | $88.00 |
| 90 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 85,425 | $0.25 | $0.26 | $0.18 | $0.27 | $0.27 | $0.50 | $0.30 |
| 91 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 38,365 | $0.25 | $0.26 | $0.18 | $0.34 | $0.32 | $0.50 | $0.37 |
| 92 | Metal W-beam guard fence (timber post) (540-7001) | LF | 650 | $24.80 | $23.00 | $23.65 | $21.50 | $21.50 | $30.00 | $28.00 |
| 93 | Guardrail end treatment (install) (544-7001) | EACH | 8 | $3,079.41 | $3,200.00 | $3,300.00 | $3,000.00 | $3,000.00 | $3,250.00 | $3,400.00 |
| 94 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 6 | $2,000.00 | $1,100.00 | $2,750.00 | $2,500.00 | $2,500.00 | $6,500.00 | $930.00 |
| 95 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $2,000.00 | $1,100.00 | $11,000 | $1,000.00 | $1,000.00 | $2,500.00 | $1,385.00 |
| 96 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $15,000 | $9,200.00 | $9,240.00 | $8,400.00 | $8,400.00 | $21,000 | $8,250.00 |
| 97 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 107 | $300.00 | $250.00 | $358.00 | $220.00 | $185.00 | $850.00 | $245.00 |
| 98 | Mailbox install-D (TWW-post) type 4 (560-7009) | EACH | 17 | $400.00 | $270.00 | $380.00 | $255.00 | $285.00 | $850.00 | $285.00 |
| 99 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 9 | $725.00 | $580.00 | $853.00 | $550.00 | $750.00 | $850.00 | $620.00 |
| 100 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 76 | $750.25 | $720.00 | $688.00 | $685.00 | $800.00 | $1,050.00 | $770.00 |
| 101 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 17 | $800.00 | $860.00 | $803.00 | $815.00 | $900.00 | $1,050.00 | $900.00 |
| 102 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $833.00 | $1,000.00 | $853.00 | $955.00 | $800.00 | $1,050.00 | $1,050.00 |
| 103 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 1 | $1,271.67 | $1,400.00 | $1,645.00 | $1,300.00 | $2,000.00 | $1,050.00 | $1,425.00 |
| 104 | Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031) | EACH | 20 | $35.00 | $29.00 | $30.00 | $27.00 | $65.00 | $100.00 | $22.00 |
| 105 | Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059) | EACH | 68 | $70.00 | $70.00 | $61.00 | $65.00 | $65.00 | $100.00 | $50.00 |
| 106 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 694 | $1.47 | $0.75 | $6.80 | $2.45 | $2.00 | $6.00 | $1.20 |
| 107 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 5,542 | $1.63 | $0.75 | $2.05 | $2.45 | $2.00 | $6.00 | $1.20 |
| 108 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 322 | $2.45 | $2.20 | $2.20 | $2.00 | $2.00 | $8.00 | $2.21 |
| 109 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,845 | $1.36 | $1.15 | $1.10 | $0.97 | $0.97 | $8.00 | $1.05 |
| 110 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 185 | $8.62 | $9.00 | $7.70 | $6.00 | $6.00 | $20.00 | $6.70 |
| 111 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 16 | $168.63 | $180.00 | $143.00 | $140.00 | $140.00 | $250.00 | $155.00 |
| 112 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 16 | $198.81 | $215.00 | $165.00 | $170.00 | $170.00 | $250.00 | $189.00 |
| 113 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 700 | $0.33 | $0.30 | $2.20 | $2.00 | $2.00 | $3.00 | $2.15 |
| 114 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 22 | $5.57 | $3.50 | $5.50 | $8.00 | $8.00 | $20.00 | $8.95 |
| 115 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 88,019 | $0.90 | $0.70 | $0.75 | $0.56 | $0.56 | $1.00 | $0.60 |
| 116 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 28,438 | $1.00 | $0.80 | $0.83 | $0.63 | $0.63 | $1.00 | $0.70 |
| 117 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 40,469 | $0.90 | $0.70 | $0.75 | $0.56 | $0.56 | $1.00 | $0.61 |
| 118 | Reflectorized pavement marker type I-C (672-7002) | EACH | 97 | $5.61 | $5.50 | $5.50 | $5.00 | $5.00 | $6.00 | $5.61 |
| 119 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,375 | $5.55 | $5.50 | $5.50 | $5.00 | $5.00 | $6.00 | $5.61 |
| 120 | Full - width mowing (730-7019) | CYC | 6 | $5,500.00 | $5,000.00 | $7,150.00 | $3,000.00 | $3,500.00 | $5,000.00 | $6,150.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 3, 2025. Compiled by Mirage Metrics.