TxDOT contract A00066973 bid tabulation

Reconstruct Existing Roadway, FM 55 (Navarro County Line to SH 34). Let by Texas DOT on October 8, 2025, Ellis, Dallas District. 5 bids received; low bid $8,523,201 by Texas Materials Group, Inc., -12% against the engineer's estimate of $9,725,831.

Owner
Texas DOT
Letting
08 OCT 2025
Pay items
108
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Texas Materials Group, Inc.$8,523,201Low-12%
2Knife River Corporation - South$8,683,141+2.0%-11%
3Big Creek Construction, LTD.$8,791,626+3.0%-10%
4A. L. Helmcamp, Inc.$8,970,458+5.0%-8.0%
5Grey Sky Construction LLC$10,562,186+24%+9.0%
TxDOT contract A00066973: bids by rank

Engineer's estimate: $9,725,831.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Texas Materials Group, Inc.2. Knife River Corporation - South3. Big Creek Construction, LTD.4. A. L. Helmcamp, Inc.5. Grey Sky Construction LLC
1Preparing row (100-7002)STA252.50$750.00$550.00$550.00$1,000.00$300.00$3,851.40
2Removing concrete (mowstrip) (104-7005)LF2,009$10.00$23.00$11.00$10.00$15.00$20.00
3Removing concrete (riprap) (104-7006)SY52$25.00$64.00$28.00$26.00$30.00$20.00
4Removing concrete (driveways) (104-7011)SY471$23.00$51.00$28.00$30.00$50.00$20.00
5Remove (2"-8") TRT/untrt base & asphalt pavement (105-7053)SY3,066$10.00$27.00$5.50$11.00$35.00$20.00
6Excavation (roadway) (110-7001)CY627.80$30.00$115.00$34.00$85.00$35.00$20.00
7Subgr widen (OC) (112-7001)STA231.10$450.00$518.00$300.00$750.00$150.00$350.00
8Embankment (final)(OC)(type C) (132-7005)CY11,067.60$25.00$10.00$25.00$19.00$19.00$30.00
9Backfill (type A or B) (134-7004)STA231.10$200.00$240.74$210.00$325.00$155.00$250.00
10Blading (150-7001)STA252.50$225.00$89.00$50.00$140.00$250.00$250.00
11Road grader work (ord comp) (152-7001)STA231.10$150.00$98.00$50.00$100.00$170.00$250.00
12Block sodding (162-7002)SY585$7.00$7.40$8.00$9.00$7.35$10.00
13Hydro mulch seed (permanent_rural_clay) (164-7018)SY185,335$0.20$0.41$0.42$0.50$0.44$0.35
14Hydro mulch seed (temporary_warm_cool) (164-7023)SY185,335$0.20$0.40$0.40$0.50$0.42$0.35
15Vegetative watering (168-7001)TGL55,235$7.00$0.01$0.01$0.01$0.15$1.00
16FL BS (compacted in place)(type D GR 1-2) (12") (247-7125)SY72,750$27.00$27.70$26.15$28.00$25.00$25.00
17FL BS (roadway del) (type D GR 1-2) (247-7209)TON14,848$35.00$34.00$36.50$36.00$35.00$50.00
18Rework BS metal (type C)(6")(ord comp) (251-7049)SY61,572$3.00$2.20$2.40$1.75$2.70$4.00
19Cement (275-7001)TON500$250.00$220.00$239.00$240.00$215.00$300.00
20Cement TRT (existing material & new base)(6") (275-7006)SY82,175$2.50$1.80$2.00$2.25$1.60$5.00
21Prime coat(MC-30 or AE-P) (310-7013)GAL14,553$5.00$5.00$6.05$4.25$5.50$5.00
22Asphalt (CRS-2P) (316-7012)GAL18,192$5.00$3.80$3.65$4.25$4.50$5.00
23Asphalt (AC-15P, AC-20-5TR or AC-20XP) (316-7071)GAL15,281$5.25$4.35$4.20$5.00$4.50$5.00
24Aggregate (type-B or L, GR-3)(sac-B) (316-7244)CY696$180.00$174.00$180.00$180.00$235.00$250.00
25SP mixes SP-C sac-B PG64-22 (344-7011)TON9,438$135.00$134.00$130.00$116.00$155.00$140.00
26Tack coat (344-7077)GAL583$3.00$3.05$6.50$8.00$5.00$6.00
27Planing asphalt concrete pavement(2") (354-7051)SY5,285$2.10$4.10$2.50$2.00$4.00$3.00
28Planing asphalt concrete pavement(3") (354-7052)SY61,629$2.20$2.75$1.25$2.50$3.00$3.00
29Cut & restore asphalt paving (400-7008)SY223$350.00$180.00$342.00$200.00$220.00$200.00
30Trench excavation protection (402-7001)LF244$12.00$1.00$22.00$8.00$21.00$10.00
31Temporary special shoring (403-7001)SF432$30.00$45.00$30.00$26.00$28.00$85.00
32Concrete structure repair (vertical & overhead) (429-7007)SF5$200.00$350.00$800.00$750.00$260.00$500.00
33Riprap (mow strip)(4 in) (432-7013)CY39.40$600.00$680.00$675.00$1,000.00$635.00$550.00
34Riprap (stone common)(dry)(12 in) (432-7031)CY119.20$225.00$260.00$238.00$350.00$225.00$155.00
35Riprap (stone protection)(18 in) (432-7043)CY1,180.50$300.00$160.00$233.00$140.00$190.00$150.00
36Cleaning and sealing existing joints (CL7) (438-7007)LF480$50.00$36.13$70.00$60.00$38.00$100.00
37Retrofit rail (type T631) (451-7020)LF366$350.00$95.00$92.00$155.00$100.00$200.00
38Concrete box culvert (5 FT X 3 FT) (462-7007)LF303$600.00$475.00$402.00$300.00$375.00$650.00
39Concrete box culvert (5 FT X 4 FT)(extend) (462-7063)LF96$1,150.00$935.00$907.00$750.00$848.00$850.00
40RC pipe (CL III)(18 in) (464-7003)LF530$100.00$65.00$70.00$75.00$66.00$65.00
41RC pipe (CL III)(24 in) (464-7005)LF501$120.00$85.00$95.00$145.00$89.00$110.00
42RC pipe (CL III)(30 in) (464-7007)LF473$145.00$122.00$106.00$185.00$100.00$120.00
43RC pipe (CL III)(36 in) (464-7009)LF264$185.00$180.00$151.00$155.00$142.00$140.00
44RC pipe (CL III)(42 in) (464-7010)LF137$210.00$220.00$255.00$220.00$238.00$200.00
45RC pipe (CL III)(48 in) (464-7011)LF159$290.00$280.00$246.00$300.00$230.00$225.00
46Headwall (CH - FW - 0) (diameter= 42 in) (466-7010)EACH2$13,000$9,000.00$11,300$12,000$10,570$9,500.00
47Headwall (CH - FW - 30) (diameter= 42 in) (466-7040)EACH2$14,000$9,600.00$11,600$16,250$10,920$10,000
48Headwall (CH - PW - 0) (diameter= 30 in) (466-7103)EACH2$10,000$8,100.00$12,000$13,250$11,300$13,500
49Headwall (CH - PW - S) (diameter= 42 in) (466-7121)EACH2$13,000$14,400$13,700$19,500$12,900$18,500
50Wingwall (FW - 0) (HW=4 FT) (466-7146)EACH1$20,000$9,125.00$11,700$13,500$10,900$15,500
51Wingwall (FW - 0) (HW=5 FT) (466-7147)EACH3$21,000$12,600$12,200$18,500$11,500$17,500
52Wingwall (FW - S) (HW=4 FT) (466-7160)EACH1$20,000$9,350.00$11,600$18,000$11,000$16,500
53Wingwall (FW - S) (HW=5 FT) (466-7161)EACH1$21,000$14,800$13,000$19,000$12,225$17,500
54Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH36$1,500.00$1,190.00$1,900.00$1,750.00$1,815.00$1,250.00
55Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325)EACH2$1,300.00$1,050.00$1,650.00$2,100.00$1,560.00$1,500.00
56Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH32$1,800.00$1,500.00$2,350.00$1,850.00$2,242.00$2,000.00
57Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346)EACH2$2,500.00$4,000.00$3,850.00$2,850.00$3,625.00$2,000.00
58Set (type II) (30 in) (RCP) (6: 1) (C) (467-7347)EACH2$3,500.00$4,300.00$6,000.00$4,000.00$5,610.00$2,650.00
59Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH24$3,000.00$3,100.00$5,250.00$2,850.00$5,000.00$4,000.00
60Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368)EACH16$4,000.00$7,100.00$9,400.00$5,500.00$8,875.00$6,250.00
61Set (type II) (48 in) (RCP) (6: 1) (P) (467-7392)EACH6$7,500.00$9,500.00$8,800.00$11,000$8,260.00$9,500.00
62Removing structure (wingwall) (496-7005)EACH6$1,800.00$1,000.00$1,740.00$2,300.00$1,650.00$2,500.00
63Removing structure (pipe) (496-7007)LF2,044.50$25.00$10.00$13.50$26.00$13.00$30.00
64Removing structure (box culvert) (496-7008)LF164$170.00$30.00$250.00$110.00$245.00$100.00
65Mobilization (500-7001)LS1$884,167$849,000$790,000$850,000$850,000$900,000
66Barricades, signs and traffic handling (502-7001)MO18$12,000$4,100.00$12,500$1,500.00$10,000$8,500.00
67Portable changeable message sign (503-7002)EACH2$14,000$5,600.00$18,000$22,000$15,000$20,000
68TMA (stationary) (505-7001)DAY267$250.00$95.00$15.00$200.00$225.00$250.00
69TMA (mobile operation) (505-7002)HR184$50.00$12.00$10.00$200.00$60.00$55.00
70Rock filter dams (install) (type 3) (506-7003)LF319$70.00$77.21$82.00$100.00$74.00$30.00
71Rock filter dams (remove) (506-7011)LF319$14.00$19.13$20.00$12.00$19.00$15.00
72Construction exits (install) (type 1) (506-7020)SY247$30.00$38.38$38.50$30.00$20.00$40.00
73Construction exits (remove) (506-7024)SY247$10.00$11.27$11.30$12.00$10.00$20.00
74Temporary sediment control fence (install) (506-7039)LF1,584$5.00$4.34$7.50$6.00$5.00$4.00
75Temporary sediment control fence (remove) (506-7041)LF1,584$1.00$0.94$1.00$1.20$1.30$2.00
76Intersections (ACP) (530-7002)SY1,290$50.00$67.00$60.00$58.00$70.00$45.00
77Driveways (concrete) (530-7006)SY452$150.00$135.00$175.00$125.00$165.00$110.00
78Driveways (ACP) (530-7010)SY2,459$55.00$75.00$61.00$42.00$92.00$45.00
79Mill rumble strips (asphalt) (shoulder) (533-7001)LF48,296$0.20$0.34$0.25$0.40$0.34$0.30
80Mill rumble strips (asphalt) (centerline) (533-7002)LF24,148$0.20$0.43$0.25$0.50$0.30$0.30
81Metal W-beam guard fence (timber post) (540-7001)LF2,025$25.00$22.50$22.00$25.00$24.00$25.00
82Metal W - beam guard fence (low fill culvert) (540-7018)LF45$95.00$75.00$95.00$100.00$79.00$50.00
83Remove metal beam guard fence (542-7001)LF1,630$3.50$2.50$2.75$3.00$2.60$3.00
84Remove terminal anchor section (542-7002)EACH2$300.00$150.00$275.00$200.00$158.00$1,850.00
85Guardrail end treatment (install) (544-7001)EACH14$3,300.00$2,950.00$3,100.00$3,300.00$3,100.00$3,850.00
86Mailbox install-S (TWW-post) type 4 (560-7008)EACH10$260.00$315.00$375.00$350.00$331.00$850.00
87Mailbox install-D (TWW-post) type 4 (560-7009)EACH1$270.00$400.00$400.00$425.00$420.00$850.00
88Mailbox install-M (TWW-post) type 4 (560-7010)EACH1$600.00$845.00$650.00$900.00$887.00$850.00
89Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH23$800.00$750.00$800.00$775.00$788.00$1,500.00
90Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007)EACH1$1,000.00$1,000.00$950.00$1,100.00$1,050.00$1,500.00
91Relocate SM RD SN sup&AM type 10BWG (644-7065)EACH2$500.00$575.00$750.00$600.00$604.00$1,250.00
92Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH48$30.00$25.00$34.00$30.00$26.00$100.00
93Install object marker assembly (OM-2Z)(WFLX)GNDHH (658-7249)EACH22$85.00$150.00$175.00$180.00$158.00$100.00
94Install OM SM RD sign (1-OM-PW)Y (658-7317)EACH21$5.00$10.00$16.00$12.00$11.00$100.00
95Install OM SM RD sign (1-OM-PW)R (658-7318)EACH5$5.00$10.00$16.00$12.00$11.00$100.00
96Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF3,620$0.50$0.37$1.10$1.25$1.12$0.75
97Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF30,265$0.50$0.37$0.28$0.35$0.28$0.75
98Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH2,602$1.75$1.04$1.60$2.00$1.10$6.00
99Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009)LF39$1.00$2.00$2.25$2.25$2.24$1.00
100Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF51$14.00$7.50$9.00$10.00$8.98$20.00
101Pavement sler 6" (666-7347)LF4,354$1.00$0.15$0.22$0.25$0.22$1.00
102Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF50,346$1.15$0.51$0.55$0.60$0.55$0.75
103Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF3,620$1.10$0.59$0.60$0.75$0.59$0.75
104Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF30,265$1.10$0.51$0.55$0.60$0.55$0.75
105Reflectorized pavement marker type II-A-A (672-7004)EACH576$5.50$3.55$4.20$4.50$4.21$6.00
106Eliminating existing PM & markers (4") (677-7001)LF4,354$0.50$0.55$0.45$0.50$0.45$1.00
107Pavement surface preparation for marking (6") (678-7002)LF4,354$0.50$0.05$0.11$0.15$0.11$0.75
108Full - width mowing (730-7019)CYC4$3,500.00$5,000.00$4,000.00$4,500.00$5,000.00$2,500.00
TxDOT contract A00066973: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of October 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy