TxDOT contract A00130689 bid tabulation
Surfacing/Roadway Restoration, FM 1484 (FM 2432 to SH 105). Let by Texas DOT on February 6, 2025, Montgomery, Houston District. 6 bids received; low bid $8,353,736 by Durwood Greene Construction Co., -34% against the engineer's estimate of $12,606,975.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 60
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Durwood Greene Construction Co. | $8,353,736 | Low | -34% |
| 2 | Vulcan Materials Asphalt and Construction, LLC | $8,800,196 | +5.0% | -30% |
| 3 | Posillico Civil, Inc. | $11,603,914 | +39% | -8.0% |
| 4 | Hayden Paving, Inc. | $11,624,956 | +39% | -8.0% |
| 5 | Texas Materials Group, Inc. | $13,814,273 | +65% | +10% |
| 6 | CDM Holdings | $14,326,278 | +71% | +14% |
Engineer's estimate: $12,606,975.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Durwood Greene Construction Co. | 2. Vulcan Materials Asphalt and Construction, LLC | 3. Posillico Civil, Inc. | 4. Hayden Paving, Inc. | 5. Texas Materials Group, Inc. | 6. CDM Holdings |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (mowstrip) (104-7005) | LF | 4,685 | $10.66 | $25.00 | $15.50 | $5.00 | $55.00 | $26.00 | $5.00 |
| 2 | Backfill (type A or B) (134-7004) | STA | 531 | $361.00 | $150.00 | $161.09 | $400.00 | $125.00 | $330.00 | $245.00 |
| 3 | SP mixes SP-D PG70-22 (344-7051) | TON | 13,004 | $135.00 | $130.00 | $122.77 | $160.00 | $157.88 | $200.00 | $225.00 |
| 4 | SP mixes SP-D sac-A PG70-22 (344-7052) | TON | 14,061 | $150.00 | $140.00 | $128.73 | $160.00 | $164.35 | $210.00 | $225.00 |
| 5 | Tack coat (344-7077) | GAL | 10,421 | $5.28 | $3.00 | $4.56 | $6.85 | $4.00 | $5.35 | $4.50 |
| 6 | Flexible pavement structure repair(10") (351-7009) | SY | 9,390 | $100.00 | $40.00 | $70.39 | $128.50 | $95.00 | $127.00 | $105.00 |
| 7 | Planing asphalt concrete pavement(2") (354-7051) | SY | 19,579 | $2.80 | $7.00 | $3.70 | $2.35 | $1.05 | $13.75 | $1.00 |
| 8 | Planing asphalt concrete pavement(3") (354-7052) | SY | 173,683 | $5.00 | $1.25 | $0.76 | $0.75 | $1.10 | $3.75 | $1.00 |
| 9 | Planing asphalt concrete pavement (1.5") (354-7074) | SY | 14,118 | $2.75 | $1.00 | $0.95 | $2.75 | $1.00 | $6.00 | $1.00 |
| 10 | Riprap (mow strip)(4 in) (432-7013) | CY | 292 | $788.00 | $750.00 | $710.40 | $570.00 | $950.00 | $1,500.00 | $800.00 |
| 11 | Mobilization (500-7001) | LS | 1 | $1,145,258 | $270,000 | $716,652 | $1,000,000 | $900,000 | $1,200,000 | $1,500,000 |
| 12 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $5,000.00 | $10,000 | $23,249 | $30,000 | $5,000.00 | $1,270.00 | $15,000 |
| 13 | Portable changeable message sign (503-7001) | DAY | 126 | $105.00 | $200.00 | $81.84 | $98.00 | $250.00 | $180.00 | $500.00 |
| 14 | TMA (stationary) (505-7001) | DAY | 44 | $450.00 | $350.00 | $270.56 | $500.00 | $300.00 | $360.00 | $500.00 |
| 15 | TMA (mobile operation) (505-7002) | HR | 82 | $115.00 | $50.00 | $33.00 | $95.00 | $200.00 | $93.00 | $500.00 |
| 16 | Intersections (ACP) (530-7002) | SY | 4,439 | $62.00 | $25.00 | $26.71 | $95.00 | $105.00 | $44.00 | $45.00 |
| 17 | Driveways (ACP) (530-7010) | SY | 15,142 | $133.00 | $30.00 | $53.40 | $85.00 | $105.00 | $44.00 | $45.00 |
| 18 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 39,603 | $0.25 | $0.25 | $0.07 | $0.17 | $0.50 | $0.30 | $1.00 |
| 19 | Metal W-beam guard fence (timber post) (540-7001) | LF | 2,913 | $25.00 | $30.00 | $25.00 | $22.27 | $25.65 | $33.00 | $28.00 |
| 20 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 12 | $2,315.00 | $3,100.00 | $2,150.00 | $2,040.10 | $2,150.00 | $3,030.00 | $2,100.00 |
| 21 | Remove metal beam guard fence (542-7001) | LF | 3,032 | $3.00 | $2.50 | $3.00 | $2.02 | $2.00 | $3.00 | $4.00 |
| 22 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 8 | $221.00 | $300.00 | $250.00 | $151.87 | $256.00 | $225.00 | $500.00 |
| 23 | Guardrail end treatment (install) (544-7001) | EACH | 30 | $3,305.00 | $3,450.00 | $3,150.00 | $2,936.13 | $2,930.00 | $4,350.00 | $3,500.00 |
| 24 | Guardrail end treatment (remove) (544-7003) | EACH | 30 | $250.00 | $400.00 | $192.50 | $177.18 | $355.00 | $263.00 | $500.00 |
| 25 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 101 | $530.00 | $700.00 | $600.00 | $445.48 | $610.00 | $662.00 | $650.00 |
| 26 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 34 | $685.00 | $900.00 | $550.00 | $556.85 | $880.00 | $827.00 | $750.00 |
| 27 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 5 | $745.00 | $1,050.00 | $585.00 | $592.29 | $950.00 | $880.00 | $775.00 |
| 28 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 21 | $1,040.00 | $1,100.00 | $725.00 | $734.03 | $975.00 | $1,090.00 | $900.00 |
| 29 | Install small roadside sign support and assembly TYS80(2)SA(P-exal) (644-7049) | EACH | 1 | $1,820.00 | $2,200.00 | $1,500.00 | $1,518.69 | $2,000.00 | $2,255.00 | $2,000.00 |
| 30 | Remove SM RD SN sup&AM (644-7073) | EACH | 161 | $120.00 | $110.00 | $85.00 | $86.06 | $95.00 | $128.00 | $150.00 |
| 31 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 28 | $17.00 | $30.00 | $30.00 | $30.37 | $23.00 | $45.00 | $20.00 |
| 32 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 111 | $22.00 | $50.00 | $35.00 | $35.44 | $30.00 | $52.00 | $25.00 |
| 33 | Work zone pavement marking non-removing (W)4"(broken) (662-7001) | LF | 1,440 | $0.38 | $0.30 | $0.27 | $0.27 | $0.37 | $0.45 | $1.00 |
| 34 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 313,233 | $0.38 | $0.25 | $0.22 | $0.22 | $0.36 | $0.35 | $1.00 |
| 35 | Work zone pavement marking non-removing (W)8"(solid) (662-7012) | LF | 5,313 | $0.60 | $0.45 | $0.42 | $0.42 | $0.80 | $0.65 | $1.00 |
| 36 | Work zone pavement marking non-removing (W)12"(solid) (662-7015) | LF | 495 | $1.34 | $2.00 | $1.55 | $1.57 | $2.00 | $2.35 | $1.50 |
| 37 | Work zone pavement marking non-removing (W)24"(solid) (662-7017) | LF | 1,956 | $4.10 | $4.00 | $3.66 | $3.70 | $2.45 | $5.50 | $4.50 |
| 38 | Work zone pavement marking non-removing (W)(arrow) (662-7018) | EACH | 24 | $96.93 | $125.00 | $110.00 | $111.07 | $110.00 | $166.00 | $200.00 |
| 39 | Work zone pavement marking non-removing (W)(double arrow) (662-7019) | EACH | 6 | $195.00 | $140.00 | $125.00 | $126.21 | $150.00 | $188.00 | $250.00 |
| 40 | Work zone pavement marking non-removing(W)(word) (662-7030) | EACH | 24 | $111.00 | $125.00 | $110.00 | $111.07 | $150.00 | $165.00 | $200.00 |
| 41 | Work zone pavement marking non-removing (Y)4"(broken) (662-7033) | LF | 4,470 | $0.38 | $0.30 | $0.27 | $0.27 | $0.37 | $0.45 | $0.75 |
| 42 | Work zone pavement marking non-removing (Y)4"(solid) (662-7035) | LF | 286,779 | $0.38 | $0.25 | $0.22 | $0.22 | $0.37 | $0.35 | $0.75 |
| 43 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,771 | $1.55 | $1.50 | $1.25 | $1.26 | $1.00 | $1.85 | $1.75 |
| 44 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 165 | $3.50 | $5.00 | $3.98 | $4.02 | $3.35 | $6.00 | $4.00 |
| 45 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 652 | $7.00 | $10.00 | $6.20 | $6.26 | $7.00 | $9.35 | $8.00 |
| 46 | RE PV marking type I(black)6"(shadow)(100MIL) (666-7138) | LF | 480 | $1.06 | $2.20 | $1.99 | $2.01 | $2.00 | $3.00 | $5.00 |
| 47 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 89,532 | $0.68 | $0.85 | $0.78 | $0.79 | $1.00 | $1.15 | $1.25 |
| 48 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 2,200 | $0.63 | $1.00 | $0.81 | $0.82 | $1.00 | $1.25 | $1.00 |
| 49 | All-wther PM type I (W)6"(solid)(100MIL) (666-7309) | LF | 14,879 | $1.13 | $1.15 | $1.05 | $1.06 | $1.30 | $1.60 | $1.50 |
| 50 | All-wther PM type I (W)6"(broken)(100MIL) (666-7310) | LF | 480 | $1.80 | $1.15 | $1.05 | $1.06 | $1.30 | $1.60 | $2.00 |
| 51 | All-wther PM type I (Y)6"(solid)(100MIL) (666-7315) | LF | 93,393 | $1.21 | $1.15 | $1.05 | $1.06 | $1.28 | $1.60 | $1.50 |
| 52 | All-wther PM type I (Y)6"(broken)(100MIL) (666-7316) | LF | 1,490 | $1.53 | $1.15 | $1.05 | $1.06 | $1.30 | $1.60 | $1.50 |
| 53 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 8 | $238.00 | $275.00 | $225.00 | $227.19 | $300.00 | $339.00 | $300.00 |
| 54 | Prefabricated PM type C (W)(double arrow) (668-7093) | EACH | 2 | $370.00 | $300.00 | $242.00 | $244.35 | $500.00 | $367.00 | $500.00 |
| 55 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 8 | $290.00 | $285.00 | $235.00 | $237.28 | $400.00 | $354.00 | $400.00 |
| 56 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 6 | $50.00 | $90.00 | $59.00 | $59.57 | $100.00 | $89.00 | $100.00 |
| 57 | Reflectorized pavement marker type I-C (672-7002) | EACH | 90 | $3.00 | $7.00 | $6.49 | $6.55 | $7.00 | $9.75 | $10.00 |
| 58 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,595 | $4.00 | $7.00 | $6.49 | $6.55 | $7.00 | $9.75 | $10.00 |
| 59 | Underseal course (3006-7001) | GAL | 37,560 | $10.00 | $6.00 | $5.44 | $7.50 | $4.00 | $5.65 | $12.00 |
| 60 | High friction surface treatment (3009-7001) | SY | 69,729 | $23.00 | $21.50 | $19.39 | $20.70 | $20.50 | $27.85 | $32.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way