TxDOT contract A00131524 bid tabulation
Construct Ramps, SH 9 (Old Georgetown Road to BNSF Railway). Let by Texas DOT on September 4, 2025, Coryell, Waco District. 3 bids received; low bid $7,187,653 by Big Creek Construction, LTD., -42% against the engineer's estimate of $12,372,592.
- Owner
- Texas DOT
- Letting
- 04 SEP 2025
- Pay items
- 123
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Big Creek Construction, LTD. | $7,187,653 | Low | -42% |
| 2 | Texas Materials Group, Inc. | $8,249,567 | +15% | -33% |
| 3 | Jordan Foster Construction, LLC | $8,415,415 | +17% | -32% |
Engineer's estimate: $12,372,592.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Big Creek Construction, LTD. | 2. Texas Materials Group, Inc. | 3. Jordan Foster Construction, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 28.40 | $7,000.00 | $5,000.00 | $1,345.00 | $19,000 |
| 2 | Removing concrete (pavement) (104-7001) | SY | 236 | $40.00 | $40.00 | $65.00 | $40.00 |
| 3 | Remove (9"-13") TRT/untrt base & asphalt pavement (105-7009) | SY | 1,305 | $15.00 | $12.00 | $11.75 | $11.00 |
| 4 | Remove (14"-18") TRT/untrt base & asphalt pavement (105-7014) | SY | 3,182 | $20.00 | $20.00 | $15.00 | $13.00 |
| 5 | Remove (0"-8") TRT/untrt base & asphalt pavement (105-7048) | SY | 205 | $10.00 | $35.00 | $26.00 | $10.00 |
| 6 | Excavation (roadway) (110-7001) | CY | 79,850 | $48.00 | $16.00 | $30.00 | $10.50 |
| 7 | Embankment (final)(OC)(type B) (132-7003) | CY | 178 | $43.00 | $40.00 | $38.00 | $17.25 |
| 8 | Embankment (final)(DC)(type B) (132-7004) | CY | 28,269 | $42.00 | $14.00 | $6.10 | $17.25 |
| 9 | Furn & place topsoil (4") (160-7002) | SY | 138,384 | $4.00 | $1.50 | $3.75 | $3.10 |
| 10 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 138,384 | $0.50 | $0.27 | $0.12 | $0.20 |
| 11 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 138,384 | $1.50 | $0.45 | $0.42 | $0.70 |
| 12 | Vegetative watering (168-7001) | TGL | 2,247 | $60.00 | $35.00 | $64.88 | $55.00 |
| 13 | Soil ret BLKT(SL_mod_clay_long) (169-7002) | SY | 33,678 | $2.50 | $1.50 | $0.66 | $2.00 |
| 14 | Soil ret BLKT(chan_permanent_6 PSF) (169-7033) | SY | 5,633 | $4.50 | $3.00 | $7.73 | $5.35 |
| 15 | Proof rolling (216-7001) | HR | 6 | $115.00 | $125.00 | $130.00 | $120.00 |
| 16 | FL BS (compacted in place)(tyd GR1-2)(final pos) (247-7188) | CY | 7,321 | $80.00 | $72.00 | $62.00 | $75.00 |
| 17 | Lime (com or QK)(slurry) (260-7005) | TON | 30 | $350.00 | $350.00 | $285.00 | $335.00 |
| 18 | Lime TRT (existing material)(12") (260-7009) | SY | 916 | $6.00 | $15.00 | $27.00 | $25.00 |
| 19 | Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004) | GAL | 52,726 | $5.00 | $3.40 | $3.40 | $7.50 |
| 20 | Fog seal (CSS-1H) (315-7004) | GAL | 2,637 | $5.00 | $6.00 | $4.50 | $4.00 |
| 21 | Asphalt (CRS-2) (316-7011) | GAL | 11,863 | $4.75 | $3.80 | $3.50 | $4.15 |
| 22 | Aggregate (type-D or L, GR-4) (316-7253) | CY | 194 | $250.00 | $200.00 | $248.00 | $260.00 |
| 23 | D-GR HMA type-B PG64-22 (341-7001) | TON | 7,089 | $135.00 | $95.00 | $120.00 | $120.00 |
| 24 | SP mixes SP-C sac-B PG70-22 (344-7021) | TON | 4,056 | $140.00 | $102.00 | $140.00 | $138.00 |
| 25 | Tack coat (344-7077) | GAL | 2,352 | $5.30 | $3.60 | $3.05 | $4.15 |
| 26 | Tom-C PG76-22 sac-B (347-7002) | TON | 1,148 | $140.00 | $150.00 | $173.00 | $178.00 |
| 27 | Tack coat (347-7011) | GAL | 2,664 | $5.00 | $3.70 | $3.05 | $4.15 |
| 28 | Plan asphalt concrete pavement (0.75") (354-7079) | SY | 26,638 | $2.25 | $1.80 | $1.35 | $1.00 |
| 29 | Concrete pavement (CRCP) (9") (360-7003) | SY | 844 | $180.00 | $150.00 | $140.00 | $155.00 |
| 30 | Cut & restoring pavement (400-7006) | SY | 132 | $240.00 | $160.00 | $160.00 | $265.00 |
| 31 | Cem stabil BKFL (400-7010) | CY | 165 | $280.00 | $195.00 | $260.00 | $200.00 |
| 32 | Trench excavation protection (402-7001) | LF | 366 | $22.00 | $35.00 | $1.00 | $15.00 |
| 33 | Temporary special shoring (403-7001) | SF | 1,184 | $45.00 | $30.00 | $30.00 | $23.00 |
| 34 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 35 | $280.00 | $250.00 | $170.00 | $200.00 |
| 35 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 88 | $360.00 | $300.00 | $210.00 | $245.00 |
| 36 | Riprap (concrete)(5 in) (432-7002) | CY | 183 | $750.00 | $700.00 | $675.00 | $975.00 |
| 37 | Riprap (mow strip)(5 in) (432-7014) | CY | 2 | $500.00 | $1,000.00 | $1,000.00 | $1,200.00 |
| 38 | Riprap (stone protection)(18 in) (432-7043) | CY | 67 | $225.00 | $160.00 | $275.00 | $280.00 |
| 39 | Concrete box culvert (3 FT X 2 FT) (462-7001) | LF | 65 | $420.00 | $275.00 | $280.00 | $500.00 |
| 40 | Concrete box culvert (7 FT X 7 FT) (462-7019) | LF | 63 | $1,200.00 | $870.00 | $975.00 | $1,400.00 |
| 41 | RC pipe (CL III)(18 in) (464-7003) | LF | 122 | $110.00 | $85.00 | $80.00 | $185.00 |
| 42 | RC pipe (CL III)(24 in) (464-7005) | LF | 250 | $135.00 | $155.00 | $95.00 | $205.00 |
| 43 | RC pipe (CL III)(36 in) (464-7009) | LF | 373 | $245.00 | $185.00 | $210.00 | $280.00 |
| 44 | RC pipe (CL IV)(30 in) (464-7023) | LF | 96 | $195.00 | $150.00 | $150.00 | $290.00 |
| 45 | Manh (complete)(PRM)(72IN) (465-7004) | EACH | 1 | $12,000 | $23,000 | $8,800.00 | $40,000 |
| 46 | Inlet(complete)(pazd)(FG)(5FTX5FT-4FTX4FT) (465-7162) | EACH | 1 | $11,500 | $8,800.00 | $10,300 | $10,000 |
| 47 | Wingwall (PW - 2) (HW=8 FT) (466-7192) | EACH | 2 | $35,000 | $26,900 | $27,900 | $45,000 |
| 48 | Set (type I)(S= 3 FT)(HW= 3 FT)(3:1)(C) (467-7040) | EACH | 2 | $8,000.00 | $10,800 | $7,000.00 | $9,500.00 |
| 49 | Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305) | EACH | 2 | $1,950.00 | $875.00 | $900.00 | $2,000.00 |
| 50 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 1 | $2,000.00 | $1,060.00 | $1,220.00 | $2,400.00 |
| 51 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 1 | $2,000.00 | $1,350.00 | $1,100.00 | $2,000.00 |
| 52 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 1 | $2,050.00 | $1,410.00 | $1,350.00 | $2,400.00 |
| 53 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 1 | $2,200.00 | $1,600.00 | $1,600.00 | $3,111.00 |
| 54 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 2 | $2,720.00 | $2,500.00 | $2,500.00 | $4,300.00 |
| 55 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 5 | $4,500.00 | $3,400.00 | $3,000.00 | $6,600.00 |
| 56 | Removing structure (set) (496-7004) | EACH | 1 | $700.00 | $350.00 | $300.00 | $500.00 |
| 57 | Removing structure (pipe) (496-7007) | LF | 226 | $37.50 | $25.00 | $13.00 | $22.00 |
| 58 | Mobilization (500-7001) | LS | 1 | $626,891 | $700,000 | $500,000 | $800,000 |
| 59 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $12,000 | $5,000.00 | $5,000.00 | $8,500.00 |
| 60 | Portable changeable message sign (503-7002) | EACH | 4 | $10,000 | $9,750.00 | $6,000.00 | $11,000 |
| 61 | TMA (stationary) (505-7001) | DAY | 193 | $300.00 | $400.00 | $275.00 | $30.00 |
| 62 | TMA (mobile operation) (505-7002) | HR | 112 | $90.00 | $85.00 | $10.00 | $200.00 |
| 63 | Rock filter dams (install) (type 2) (506-7002) | LF | 216 | $49.00 | $45.00 | $45.16 | $41.00 |
| 64 | Rock filter dams (remove) (506-7011) | LF | 216 | $16.50 | $5.00 | $17.00 | $23.00 |
| 65 | Embankment (erosion & sediment control, in place) (506-7026) | CY | 743 | $50.00 | $25.00 | $20.00 | $10.00 |
| 66 | Temporary sediment control fence (install) (506-7039) | LF | 1,873 | $5.50 | $5.00 | $6.49 | $4.15 |
| 67 | Temporary sediment control fence (remove) (506-7041) | LF | 1,873 | $2.45 | $1.00 | $0.88 | $1.35 |
| 68 | Portable concrete traffic barrier (des source)(single slope)(type 1) (512-7013) | LF | 1,830 | $25.00 | $12.00 | $16.86 | $18.00 |
| 69 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 810 | $10.00 | $8.00 | $17.00 | $4.75 |
| 70 | Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037) | LF | 1,830 | $16.50 | $11.00 | $16.50 | $17.00 |
| 71 | Concrete curb & gutter (type I) (529-7008) | LF | 889 | $60.00 | $36.00 | $48.00 | $36.00 |
| 72 | Driveways (ACP) (530-7010) | SY | 155 | $100.00 | $60.00 | $75.00 | $130.00 |
| 73 | Concrete median (536-7002) | SY | 571 | $195.00 | $95.00 | $110.00 | $145.00 |
| 74 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 2 | $1,400.00 | $1,500.00 | $1,550.00 | $875.00 |
| 75 | Crash cushion attenuator (stockpile) (545-7003) | EACH | 2 | $1,225.00 | $1,000.00 | $810.00 | $1,020.00 |
| 76 | Crash cushion attenuator (install)(S)(W)(TL3) (545-7016) | EACH | 2 | $11,000 | $12,000 | $7,925.00 | $12,300 |
| 77 | Chain link fence (remove) (550-7007) | LF | 5,706 | $19.00 | $8.00 | $10.52 | $6.00 |
| 78 | Chain link fence(install)(6 )(barb top) (550-7008) | LF | 7,192 | $64.00 | $40.00 | $42.36 | $35.00 |
| 79 | Gate (remove) (550-7016) | EACH | 2 | $400.00 | $2,500.00 | $539.65 | $2,000.00 |
| 80 | Gate (install)(6'X24') (550-7018) | EACH | 2 | $2,500.00 | $10,000 | $2,914.08 | $10,000 |
| 81 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 11 | $5,350.00 | $6,500.00 | $4,000.00 | $4,700.00 |
| 82 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 7,734 | $21.00 | $10.00 | $8.00 | $9.40 |
| 83 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 220 | $28.00 | $80.00 | $65.00 | $75.00 |
| 84 | Electrical conductor (no.10) bare (620-7005) | LF | 10,399 | $2.00 | $1.50 | $1.00 | $1.20 |
| 85 | Ground box type A (122311)W/apron (624-7002) | EACH | 11 | $1,500.00 | $2,000.00 | $1,200.00 | $1,400.00 |
| 86 | Remove ground box (624-7013) | EACH | 5 | $500.00 | $150.00 | $92.00 | $110.00 |
| 87 | Remove electrical services (628-7002) | EACH | 1 | $1,200.00 | $800.00 | $552.00 | $650.00 |
| 88 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 1 | $9,500.00 | $8,500.00 | $7,000.00 | $8,300.00 |
| 89 | Aluminum signs (type G) (636-7002) | SF | 287 | $45.00 | $40.00 | $35.00 | $84.00 |
| 90 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $1,000.00 | $1,200.00 | $955.00 | $1,315.00 |
| 91 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 1 | $1,000.00 | $1,600.00 | $1,280.00 | $1,650.00 |
| 92 | Install small roadside sign support and assembly TYS80(1)SA(U-WC) (644-7035) | EACH | 3 | $1,250.00 | $1,500.00 | $1,265.00 | $1,615.00 |
| 93 | Install small roadside sign support and assembly TYS80(1)SA(U-exal) (644-7036) | EACH | 1 | $1,500.00 | $2,000.00 | $1,585.00 | $2,140.00 |
| 94 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 42 | $730.00 | $750.00 | $485.00 | $690.00 |
| 95 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $165.00 | $150.00 | $110.00 | $200.00 |
| 96 | Relocate SM RD SN sup & AM type temporary (644-7077) | EACH | 8 | $600.00 | $400.00 | $450.00 | $380.00 |
| 97 | Install LRSS (struct steel) (647-7001) | LB | 1,720 | $9.50 | $7.00 | $6.00 | $8.00 |
| 98 | Install delineator assembly (D-SW)SZ 2(WC)GND (658-7009) | EACH | 26 | $30.00 | $50.00 | $70.00 | $57.00 |
| 99 | Install delineator assembly (D-DW)SZ 2(WC)GND (658-7049) | EACH | 24 | $30.00 | $60.00 | $71.00 | $60.00 |
| 100 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 21 | $100.00 | $200.00 | $63.00 | $195.00 |
| 101 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 13,160 | $0.60 | $0.60 | $0.52 | $0.30 |
| 102 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 13,160 | $0.60 | $0.60 | $0.52 | $0.30 |
| 103 | Work zone pavement marking removing (reflectorized) type I-C (662-7049) | EACH | 8 | $2.00 | $7.00 | $5.00 | $6.00 |
| 104 | Work zone pavement marking removing (reflectorized) type II-A-A (662-7051) | EACH | 666 | $2.00 | $7.50 | $5.50 | $6.00 |
| 105 | Work zone pavement marking removing (traffic BTN) type W (662-7057) | EACH | 20 | $4.25 | $7.00 | $4.00 | $6.00 |
| 106 | Work zone pavement marking removing (traffic BTN) type Y (662-7059) | EACH | 20 | $4.25 | $7.00 | $4.00 | $6.00 |
| 107 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 165 | $1.60 | $2.00 | $1.12 | $2.35 |
| 108 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 3,855 | $1.20 | $1.50 | $1.10 | $1.25 |
| 109 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 15 | $3.45 | $7.00 | $6.50 | $5.90 |
| 110 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 25 | $12.00 | $15.00 | $13.00 | $11.80 |
| 111 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 990 | $1.00 | $1.10 | $0.90 | $0.85 |
| 112 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 14,370 | $1.00 | $1.00 | $0.87 | $0.70 |
| 113 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 11,143 | $1.00 | $1.00 | $0.87 | $0.70 |
| 114 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 1 | $300.00 | $500.00 | $205.00 | $265.00 |
| 115 | Reflectorized pavement marker type I-C (672-7002) | EACH | 266 | $7.20 | $8.00 | $7.00 | $6.90 |
| 116 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 125 | $7.20 | $8.50 | $7.50 | $6.90 |
| 117 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2 | $7.20 | $7.00 | $6.00 | $6.90 |
| 118 | Eliminating existing PM & markers (4") (677-7001) | LF | 26,320 | $0.65 | $0.40 | $0.30 | $0.65 |
| 119 | Removal of conduit (690-7001) | LF | 693 | $10.00 | $3.00 | $2.00 | $2.35 |
| 120 | Removal of cables (690-7009) | LF | 9,567 | $2.00 | $1.50 | $0.50 | $0.60 |
| 121 | Cleaning / sweeping (aggregate removal) (738-7103) | MI | 1.64 | $100.00 | $1,000.00 | $2,500.00 | $2,400.00 |
| 122 | Preformed in-lane (trans) rumble strip (6024-7001) | LF | 160 | $30.00 | $20.00 | $15.00 | $11.75 |
| 123 | Aluminum electrical cond (#8 XHHW) (6071-7004) | LF | 27,936 | $1.80 | $2.50 | $2.00 | $2.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of September 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.