TxDOT contract A00133874 bid tabulation
Rehabilitate Existing Roadway, SH 34 (IH 20 EB Frontage Road to North of SH 243). Let by Texas DOT on August 5, 2026, Kaufman, Dallas District. 7 bids received; low bid $6,242,701 by Big Creek Construction, LTD., -13% against the engineer's estimate of $7,199,790.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 82
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Big Creek Construction, LTD. | $6,242,701 | Low | -13% |
| 2 | Foutsco Paving Company, LLC | $6,445,186 | +3.0% | -10% |
| 3 | Texas Materials Group, Inc. | $6,831,267 | +9.0% | -5.0% |
| 4 | Overland Corporation | $7,381,444 | +18% | +3.0% |
| 5 | Austin Bridge & Road Services, LP | $7,436,526 | +19% | +3.0% |
| 6 | A. L. Helmcamp, Inc. | $7,979,811 | +28% | +11% |
| 7 | Peachtree Construction, LTD. | $8,069,308 | +29% | +12% |
Engineer's estimate: $7,199,790.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Big Creek Construction, LTD. | 2. Foutsco Paving Company, LLC | 3. Texas Materials Group, Inc. | 4. Overland Corporation | 5. Austin Bridge & Road Services, LP | 6. A. L. Helmcamp, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 450.49 | $200.00 | $500.00 | $50.00 | $345.01 | $417.00 | $583.20 | $350.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 164 | $19.90 | $16.50 | $30.00 | $19.00 | $19.00 | $19.00 | $25.89 |
| 3 | Remove (12"-16") TRT/untrt base & asphalt pavement (105-7012) | SY | 309 | $14.00 | $15.00 | $25.00 | $12.50 | $54.00 | $12.50 | $14.00 |
| 4 | Excavation (channel) (110-7002) | CY | 92 | $7.50 | $55.00 | $70.00 | $35.00 | $35.00 | $35.00 | $95.00 |
| 5 | Subgr widen (OC) (112-7001) | STA | 1.43 | $620.00 | $1,500.00 | $1,500.00 | $12,500 | $12,500 | $12,500 | $5,000.00 |
| 6 | Embankment (final)(OC)(type C) (132-7005) | CY | 335 | $50.00 | $35.00 | $70.00 | $41.00 | $41.00 | $41.00 | $20.00 |
| 7 | Backfill (type A or B) (134-7004) | STA | 450.49 | $300.00 | $230.00 | $125.00 | $170.30 | $210.00 | $329.73 | $170.00 |
| 8 | Road grader work (ord comp) (152-7001) | STA | 1.43 | $200.00 | $1,500.00 | $150.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,100.00 |
| 9 | Block sodding (162-7002) | SY | 4,784 | $16.50 | $4.75 | $2.00 | $4.19 | $4.19 | $9.98 | $4.80 |
| 10 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 4,784 | $0.10 | $0.52 | $0.48 | $0.48 | $0.48 | $2.55 | $0.26 |
| 11 | Vegetative watering (168-7001) | TGL | 1,433 | $250.00 | $20.00 | $0.10 | $0.01 | $5.00 | $0.05 | $0.50 |
| 12 | FL BS (compacted in place)(type D GR 1-2) (12") (247-7125) | SY | 489 | $28.00 | $50.00 | $60.00 | $42.00 | $44.00 | $42.00 | $75.00 |
| 13 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 147 | $5.00 | $10.00 | $0.10 | $15.00 | $12.80 | $15.07 | $15.00 |
| 14 | SP mixes SP-C sac-B PG70-22 (344-7021) | TON | 19,626 | $128.00 | $120.00 | $151.50 | $135.00 | $165.00 | $142.01 | $140.00 |
| 15 | Tack coat (344-7077) | GAL | 19,571 | $4.00 | $3.50 | $0.10 | $4.00 | $3.50 | $4.60 | $5.00 |
| 16 | Flexible pavement structure repair(8") (351-7007) | SY | 17,616 | $65.00 | $75.00 | $65.00 | $78.00 | $92.00 | $78.00 | $125.00 |
| 17 | Plane & text asphalt concrete pavement(0" to 2") (354-7002) | SY | 175,989 | $3.00 | $2.25 | $1.60 | $2.59 | $2.75 | $1.90 | $2.25 |
| 18 | Flowable backfill (401-7001) | CY | 4 | $370.00 | $440.00 | $400.00 | $350.00 | $350.00 | $350.00 | $420.00 |
| 19 | Trench excavation protection (402-7001) | LF | 32 | $4.88 | $16.50 | $12.00 | $10.00 | $10.00 | $10.00 | $16.00 |
| 20 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 30 | $150.00 | $192.50 | $200.00 | $201.00 | $210.00 | $210.00 | $210.00 |
| 21 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 107 | $110.00 | $165.00 | $200.00 | $214.00 | $150.00 | $150.00 | $220.00 |
| 22 | Riprap (concrete)(5 in) (432-7002) | CY | 41 | $551.00 | $825.00 | $580.00 | $610.00 | $684.00 | $610.00 | $760.00 |
| 23 | Riprap (mow strip)(4 in) (432-7013) | CY | 616 | $530.00 | $625.00 | $605.00 | $669.77 | $625.00 | $612.00 | $700.00 |
| 24 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 7 | $375.00 | $175.00 | $652.00 | $300.00 | $170.00 | $300.00 | $280.00 |
| 25 | Riprap (stone common)(dry)(24 in) (432-7034) | CY | 107 | $200.00 | $125.00 | $145.00 | $250.00 | $170.00 | $250.00 | $315.00 |
| 26 | Riprap (stone protection)(18 in) (432-7043) | CY | 145 | $400.00 | $150.00 | $188.00 | $190.00 | $174.50 | $190.00 | $265.00 |
| 27 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 598 | $40.00 | $60.00 | $30.00 | $30.00 | $120.00 | $30.00 | $43.00 |
| 28 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 68 | $397.00 | $715.00 | $554.00 | $475.00 | $475.00 | $475.00 | $682.00 |
| 29 | RC pipe (CL III)(24 in) (464-7005) | LF | 36 | $90.00 | $110.00 | $130.00 | $105.00 | $105.00 | $105.00 | $105.00 |
| 30 | Set (type I)(S= 5 FT)(HW= 5 FT)(6:1)(P) (467-7102) | EACH | 1 | $1,200.00 | $22,000 | $11,250 | $32,000 | $39,405 | $35,000 | $21,000 |
| 31 | Set (type I)(S= 5 FT)(HW= 7 FT)(4:1)(C) (467-7112) | EACH | 1 | $2,500.00 | $19,800 | $14,000 | $24,250 | $30,650 | $26,250 | $18,900 |
| 32 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 1 | $1,555.00 | $1,760.00 | $2,500.00 | $3,000.00 | $3,000.00 | $3,000.00 | $1,680.00 |
| 33 | Removing structure (headwall) (496-7006) | EACH | 2 | $300.00 | $1,100.00 | $1,200.00 | $800.00 | $800.00 | $1,970.81 | $1,050.00 |
| 34 | Removing structure (pipe) (496-7007) | LF | 40 | $19.00 | $11.00 | $40.00 | $20.00 | $20.00 | $80.54 | $11.00 |
| 35 | Mobilization (500-7001) | LS | 1 | $651,345 | $300,000 | $350,000 | $377,300 | $73,000 | $818,018 | $650,000 |
| 36 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $20,000 | $6,500.00 | $40,000 | $29,000 | $12,000 | $33,889 | $10,000 |
| 37 | Portable changeable message sign (503-7002) | EACH | 2 | $4,000.00 | $10,000 | $8,000.00 | $9,500.00 | $19,250 | $7,047.00 | $12,500 |
| 38 | TMA (stationary) (505-7001) | DAY | 140 | $350.00 | $225.00 | $1.00 | $1.00 | $223.42 | $0.05 | $350.00 |
| 39 | TMA (mobile operation) (505-7003) | DAY | 10 | $500.00 | $500.00 | $1.00 | $400.00 | $928.09 | $150.00 | $750.00 |
| 40 | Construction exits (install) (type 1) (506-7020) | SY | 444 | $32.00 | $40.00 | $1.00 | $38.00 | $27.31 | $52.50 | $15.00 |
| 41 | Construction exits (remove) (506-7024) | SY | 444 | $10.00 | $15.00 | $1.00 | $14.00 | $9.47 | $21.25 | $5.00 |
| 42 | Temporary sediment control fence (install) (506-7039) | LF | 12,182 | $4.95 | $4.00 | $0.10 | $3.12 | $2.97 | $3.12 | $3.50 |
| 43 | Temporary sediment control fence (remove) (506-7041) | LF | 12,182 | $3.85 | $1.00 | $0.10 | $0.69 | $0.83 | $0.69 | $1.00 |
| 44 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,785 | $4.00 | $5.75 | $0.10 | $4.00 | $3.94 | $4.00 | $6.00 |
| 45 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,785 | $1.00 | $1.50 | $0.10 | $0.65 | $0.83 | $0.65 | $1.30 |
| 46 | Portable concrete traffic barrier (remove)(F-shape)(type 1) (512-7053) | LF | 215 | $200.00 | $30.00 | $75.00 | $11.86 | $33.50 | $32.09 | $80.00 |
| 47 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 73,613 | $0.10 | $0.30 | $0.15 | $0.15 | $0.10 | $0.15 | $0.16 |
| 48 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 34,590 | $0.10 | $0.32 | $0.15 | $0.15 | $0.12 | $0.15 | $0.16 |
| 49 | Metal W-beam guard fence (timber post) (540-7001) | LF | 5,744 | $35.00 | $28.00 | $22.00 | $23.00 | $22.00 | $26.00 | $23.00 |
| 50 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 3 | $1,825.00 | $1,980.00 | $1,700.00 | $2,600.00 | $3,305.00 | $1,800.00 | $1,785.00 |
| 51 | Short radius (28") (540-7013) | LF | 90 | $50.00 | $55.00 | $38.00 | $25.00 | $38.00 | $50.00 | $40.00 |
| 52 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 140 | $83.50 | $105.00 | $84.00 | $75.00 | $84.00 | $95.00 | $88.00 |
| 53 | Remove metal beam guard fence (542-7001) | LF | 3,525 | $2.80 | $1.00 | $2.00 | $2.50 | $2.00 | $1.00 | $2.10 |
| 54 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 10 | $255.00 | $105.00 | $150.00 | $250.00 | $150.00 | $95.00 | $158.00 |
| 55 | Guardrail end treatment (install) (544-7001) | EACH | 54 | $3,100.00 | $1,320.00 | $3,000.00 | $3,000.00 | $3,000.00 | $1,200.00 | $3,150.00 |
| 56 | Guardrail end treatment (remove) (544-7003) | EACH | 48 | $280.00 | $550.00 | $150.00 | $250.00 | $150.00 | $500.00 | $158.00 |
| 57 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 95 | $650.00 | $495.00 | $650.00 | $650.00 | $650.00 | $450.00 | $683.00 |
| 58 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 18 | $715.00 | $495.00 | $700.00 | $700.00 | $700.00 | $450.00 | $735.00 |
| 59 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 4 | $900.00 | $550.00 | $990.00 | $990.00 | $990.00 | $500.00 | $1,040.00 |
| 60 | Install small roadside sign support and assembly TYS80(1)SA(T-2EXT) (644-7029) | EACH | 1 | $1,100.00 | $1,650.00 | $990.00 | $990.00 | $990.00 | $1,500.00 | $1,040.00 |
| 61 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 4 | $650.00 | $825.00 | $1,105.00 | $990.00 | $990.00 | $750.00 | $1,040.00 |
| 62 | Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002) | EACH | 135 | $25.00 | $25.00 | $26.00 | $25.00 | $26.00 | $22.01 | $28.00 |
| 63 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 18 | $15.00 | $20.00 | $25.00 | $20.00 | $25.00 | $25.98 | $26.00 |
| 64 | Install OM SM RD sign (1-OM-con)Y (658-7079) | EACH | 7 | $28.00 | $20.00 | $20.00 | $20.00 | $20.00 | $74.27 | $21.00 |
| 65 | Install OM SM RD sign (1-OM-con)R (658-7080) | EACH | 40 | $28.00 | $20.00 | $20.00 | $20.00 | $20.00 | $25.99 | $21.00 |
| 66 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 189 | $0.55 | $1.50 | $10.00 | $0.64 | $0.54 | $0.50 | $0.53 |
| 67 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 380 | $0.55 | $1.50 | $10.00 | $0.64 | $0.50 | $0.50 | $0.53 |
| 68 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,830 | $2.20 | $0.86 | $0.86 | $0.86 | $0.93 | $0.86 | $0.90 |
| 69 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 517 | $7.00 | $6.77 | $6.77 | $6.77 | $7.36 | $6.77 | $6.75 |
| 70 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 26 | $170.00 | $170.00 | $170.00 | $170.00 | $184.72 | $170.00 | $152.00 |
| 71 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 14 | $187.00 | $160.00 | $160.00 | $160.00 | $173.85 | $160.00 | $158.00 |
| 72 | Ref pavement marking type I(W)36"(yld tri)(100MIL) (666-7090) | EACH | 15 | $125.00 | $44.00 | $44.00 | $44.00 | $47.81 | $44.00 | $68.00 |
| 73 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 78,600 | $0.17 | $0.25 | $0.20 | $0.20 | $0.22 | $0.20 | $0.26 |
| 74 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 78,600 | $0.17 | $0.25 | $0.20 | $0.20 | $0.22 | $0.20 | $0.26 |
| 75 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 287 | $0.54 | $0.59 | $0.59 | $0.59 | $0.64 | $0.59 | $0.55 |
| 76 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 76,526 | $0.54 | $0.53 | $0.52 | $0.52 | $0.57 | $0.53 | $0.53 |
| 77 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 5,544 | $0.56 | $0.52 | $0.53 | $0.53 | $0.59 | $0.52 | $0.53 |
| 78 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 46,023 | $0.55 | $0.52 | $0.52 | $0.52 | $0.57 | $0.52 | $0.53 |
| 79 | Reflectorized pavement marker type I-C (672-7002) | EACH | 93 | $4.40 | $4.00 | $4.00 | $4.00 | $4.35 | $4.00 | $3.70 |
| 80 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 1,320 | $4.07 | $3.80 | $3.80 | $3.80 | $4.13 | $3.80 | $3.70 |
| 81 | Full - width mowing (730-7019) | CYC | 2 | $5,000.00 | $5,000.00 | $5,000.00 | $2,275.00 | $6,000.00 | $2,275.00 | $7,000.00 |
| 82 | Ditch cleaning and reshaping (foot) (760-7001) | LF | 600 | $15.00 | $7.50 | $10.00 | $12.02 | $10.00 | $10.20 | $18.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.