TxDOT contract A00134792 bid tabulation
Rehabilitate Bridge, COUNTY ROAD 213 (CR 213 AT MIXON CREEK #1 to STR# AA04-37-001). Let by Texas DOT on November 6, 2025, Lavaca, Yoakum District. 4 bids received; low bid $747,400 by Cekra Inc., -10% against the engineer's estimate of $830,897.
- Owner
- Texas DOT
- Letting
- 06 NOV 2025
- Pay items
- 47
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cekra Inc. | $747,400 | Low | -10% |
| 2 | Garret Shields Infrastructure | $1,052,536 | +41% | +27% |
| 3 | Ragle Construction, Inc. | $1,382,566 | +85% | +66% |
| 4 | Southern Road & Bridge, LLC | $2,037,285 | +173% | +145% |
Engineer's estimate: $830,897.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Cekra Inc. | 2. Garret Shields Infrastructure | 3. Ragle Construction, Inc. | 4. Southern Road & Bridge, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3 | $5,000.00 | $7,500.00 | $1,000.00 | $40,000 | $5,000.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 113 | $22.00 | $18.00 | $40.00 | $200.00 | $65.00 |
| 3 | Excavation (channel) (110-7002) | CY | 92 | $20.00 | $250.00 | $40.00 | $200.00 | $65.00 |
| 4 | Embankment (final)(OC)(type C) (132-7005) | CY | 31 | $50.00 | $450.00 | $40.00 | $200.00 | $65.00 |
| 5 | Blading (150-7002) | HR | 20 | $120.00 | $200.00 | $80.00 | $177.00 | $95.00 |
| 6 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 1,000 | $3.00 | $0.60 | $3.00 | $1.20 | $15.00 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 250 | $0.40 | $0.30 | $3.00 | $1.85 | $15.00 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 250 | $0.40 | $0.20 | $1.50 | $1.85 | $15.00 |
| 9 | Vegetative watering (168-7001) | TGL | 8.42 | $45.00 | $25.00 | $50.00 | $151.00 | $500.00 |
| 10 | FL BS (compacted in place)(type E GR 5)(final pos) (247-7196) | CY | 113 | $125.00 | $125.00 | $80.00 | $160.00 | $450.00 |
| 11 | Asphalt (RC-250) (316-7016) | GAL | 88 | $15.00 | $11.00 | $10.00 | $12.00 | $125.00 |
| 12 | Aggregate (type-E, GR-5)(sac-B) (316-7194) | CY | 3 | $600.00 | $650.00 | $500.00 | $600.00 | $500.00 |
| 13 | Aggregate (type-PE, GR-4)(sac-B) (316-7232) | CY | 3 | $445.00 | $100.00 | $500.00 | $600.00 | $500.00 |
| 14 | Asphalt (AC 20-5TR or AC-20XP or CRS-2P) (316-7264) | GAL | 150 | $20.00 | $5.00 | $5.00 | $12.00 | $150.00 |
| 15 | Sheet piling (PZ - 22) (407-7001) | SF | 2,684 | $90.00 | $48.00 | $80.00 | $57.00 | $125.00 |
| 16 | Class C concrete (abutment) (420-7012) | CY | 19.90 | $925.00 | $1,700.00 | $2,000.00 | $3,100.00 | $5,500.00 |
| 17 | Class C concrete (rail foundation) (420-7052) | CY | 5.20 | $1,300.00 | $850.00 | $2,000.00 | $1,250.00 | $5,500.00 |
| 18 | Class C concrete (coping) (420-7143) | LF | 69 | $155.00 | $160.00 | $500.00 | $172.00 | $385.00 |
| 19 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 12 | $250.00 | $400.00 | $200.00 | $500.00 | $650.00 |
| 20 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 100 | $215.00 | $350.00 | $200.00 | $150.00 | $550.00 |
| 21 | Riprap (concrete)(4 in) (432-7001) | CY | 6 | $825.00 | $600.00 | $600.00 | $900.00 | $1,250.00 |
| 22 | Riprap (stone protection)(18 in) (432-7043) | CY | 256 | $300.00 | $300.00 | $300.00 | $262.00 | $450.00 |
| 23 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 24 | $50.00 | $125.00 | $50.00 | $50.00 | $95.00 |
| 24 | Multi-layer polymer overlay (439-7014) | SY | 110 | $65.00 | $275.00 | $550.00 | $107.00 | $650.00 |
| 25 | Clean & paint existing STR (system III-A) (446-7010) | LS | 1 | $100,000 | $85,000 | $300,000 | $300,000 | $525,000 |
| 26 | Rail (end parapet) (450-7074) | LF | 37.20 | $200.00 | $650.00 | $100.00 | $536.00 | $350.00 |
| 27 | Shot blasting (483-7016) | SY | 110 | $50.00 | $75.00 | $50.00 | $4.60 | $95.00 |
| 28 | Mobilization (500-7001) | LS | 1 | $74,200 | $75,000 | $50,000 | $140,000 | $125,000 |
| 29 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $3,500.00 | $2,900.00 | $5,000.00 | $38,170 | $10,000 |
| 30 | Rock filter dams (install) (type 1) (506-7001) | LF | 50 | $42.00 | $40.00 | $20.00 | $39.00 | $50.00 |
| 31 | Rock filter dams (remove) (506-7011) | LF | 50 | $12.00 | $15.00 | $5.00 | $7.50 | $20.00 |
| 32 | Sandbags for erosion control (506-7035) | EACH | 50 | $8.00 | $17.00 | $10.00 | $12.00 | $50.00 |
| 33 | Temporary sediment control fence (install) (506-7039) | LF | 100 | $10.00 | $3.00 | $5.00 | $3.40 | $5.00 |
| 34 | Temporary sediment control fence (remove) (506-7041) | LF | 100 | $5.00 | $1.00 | $1.00 | $2.25 | $5.00 |
| 35 | Wire fence (type A) (552-7001) | LF | 50 | $30.00 | $10.00 | $25.00 | $22.00 | $65.00 |
| 36 | Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057) | EACH | 2 | $600.00 | $599.50 | $800.00 | $530.00 | $1,650.00 |
| 37 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $200.00 | $115.00 | $500.00 | $125.00 | $185.00 |
| 38 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 8 | $30.00 | $32.00 | $5.00 | $35.00 | $125.00 |
| 39 | Install delineator assembly (D-SW)SZ 1(WFLX)GNDLL (658-7105) | EACH | 12 | $150.00 | $75.00 | $50.00 | $125.00 | $250.00 |
| 40 | Install object marker assembly (OM-3L)(WFLX)SRFLL (658-7266) | EACH | 2 | $90.00 | $600.00 | $400.00 | $205.00 | $750.00 |
| 41 | Install object marker assembly (OM-3R)(WFLX)SRFLL (658-7272) | EACH | 2 | $90.00 | $600.00 | $450.00 | $205.00 | $750.00 |
| 42 | Rep steel bridge member (truss vertical) (784-7004) | EACH | 8 | $7,000.00 | $4,000.00 | $500.00 | $3,100.00 | $9,500.00 |
| 43 | Rep steel bridge member (truss rail) (784-7012) | EACH | 2 | $7,000.00 | $6,000.00 | $60,000 | $19,600 | $82,500 |
| 44 | Rep steel bridge MBR (straighten memb) (784-7020) | EACH | 4 | $15,000 | $8,500.00 | $5,000.00 | $5,000.00 | $25,000 |
| 45 | Rep steel bridge member(repl rivet/bolt) (784-7024) | EACH | 120 | $200.00 | $200.00 | $80.00 | $500.00 | $185.00 |
| 46 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 2 | $8,800.00 | $2,500.00 | $500.00 | $610.00 | $3,500.00 |
| 47 | Bridge chord cleaning (7001-7004) | EACH | 2 | $300.00 | $2,500.00 | $2,000.00 | $610.00 | $3,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 6, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.