TxDOT contract A00135286 bid tabulation
Bridge Replacement, S MINNESOTA AVE (Minnesota Ave. @ Drainage Ditch to NBI #: 210310C01256001). Let by Texas DOT on August 7, 2025, Cameron, Pharr District. 4 bids received; low bid $1,646,413 by Lucania Contractors LLC, -10% against the engineer's estimate of $1,837,310.
- Owner
- Texas DOT
- Letting
- 07 AUG 2025
- Pay items
- 77
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lucania Contractors LLC | $1,646,413 | Low | -10% |
| 2 | Foremost Paving, Inc. | $2,088,201 | +27% | +14% |
| 3 | Ioc Company LLC | $2,179,170 | +32% | +19% |
| 4 | 3LW Civil LLC | $3,229,539 | +96% | +76% |
Engineer's estimate: $1,837,310.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Lucania Contractors LLC | 2. Foremost Paving, Inc. | 3. Ioc Company LLC | 4. 3LW Civil LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 6.83 | $3,000.00 | $2,000.00 | $14,000 | $15,000 | $5,364.13 |
| 2 | Removing concrete (miscellaneous) (104-7046) | SY | 9 | $60.00 | $90.00 | $162.80 | $200.00 | $200.00 |
| 3 | Remove (8"-12") TRT/untrt base & asphalt pavement (105-7008) | SY | 1,844 | $30.00 | $16.00 | $10.40 | $15.00 | $32.81 |
| 4 | Excavation (roadway) (110-7001) | CY | 344.70 | $18.00 | $13.00 | $55.30 | $25.00 | $51.25 |
| 5 | Excavation (channel) (110-7002) | CY | 522 | $28.00 | $25.00 | $33.00 | $25.00 | $58.13 |
| 6 | Embankment (final)(DC)(type C) (132-7006) | CY | 424.60 | $30.00 | $20.00 | $41.60 | $40.00 | $166.88 |
| 7 | Furn & place topsoil (4") (160-7002) | SY | 2,311 | $5.00 | $8.00 | $7.00 | $4.00 | $20.26 |
| 8 | Drill seed (permanent_rural_sand) (164-7009) | SY | 2,311 | $1.00 | $1.50 | $2.00 | $1.75 | $1.35 |
| 9 | Drill seed (temporary_warm_cool) (164-7015) | SY | 2,311 | $1.00 | $1.50 | $1.50 | $1.35 | $1.36 |
| 10 | Vegetative watering (168-7001) | TGL | 42 | $35.00 | $30.00 | $107.30 | $80.00 | $82.81 |
| 11 | FL BS (compacted in place)(type E GR 4) (10") (247-7108) | SY | 2,021 | $40.00 | $25.00 | $16.30 | $15.00 | $43.13 |
| 12 | Geogrid base reinforcement (type 2) (250-7002) | SY | 2,143 | $1.50 | $2.50 | $3.70 | $5.00 | $5.00 |
| 13 | Lime (commercial lime slurry) (260-7004) | TON | 29 | $400.00 | $381.00 | $403.40 | $400.00 | $10.94 |
| 14 | Lime TRT (existing material)(12") (260-7009) | SY | 2,143 | $10.00 | $10.00 | $20.00 | $15.00 | $200.00 |
| 15 | CM TRT(PT MX)(CL M)(type E)(GR 4)(FN pos) (276-7095) | CY | 561 | $200.00 | $190.00 | $55.60 | $300.00 | $312.50 |
| 16 | Aggregate(type-D GR-4 sac-B)material & haul (302-7008) | CY | 16 | $300.00 | $500.00 | $101.50 | $750.00 | $1,168.75 |
| 17 | Prime coat (MC-30) (310-7004) | GAL | 387 | $10.00 | $10.00 | $10.70 | $10.00 | $18.75 |
| 18 | Asphalt (tier II) (316-7266) | GAL | 618 | $7.00 | $10.00 | $39.20 | $10.00 | $17.50 |
| 19 | D-GR HMA type D sac-A PG64-22 (341-7044) | TON | 308 | $250.00 | $200.00 | $197.50 | $300.00 | $250.00 |
| 20 | Cem stabil BKFL (400-7010) | CY | 34 | $260.00 | $200.00 | $220.00 | $150.00 | $355.27 |
| 21 | Flowable backfill (401-7001) | CY | 9 | $530.00 | $300.00 | $220.00 | $600.00 | $621.42 |
| 22 | Trench excavation protection (402-7001) | LF | 168 | $11.50 | $8.00 | $1.10 | $5.00 | $23.65 |
| 23 | Drilled shaft (24 in) (416-7004) | LF | 940 | $270.00 | $260.00 | $275.00 | $219.81 | $289.54 |
| 24 | Class C concrete (abutment) (420-7012) | CY | 26.80 | $1,430.00 | $1,500.00 | $3,300.00 | $2,200.00 | $1,373.42 |
| 25 | Class C concrete (cap) (420-7022) | CY | 18 | $1,800.00 | $3,200.00 | $4,400.00 | $3,650.00 | $2,156.19 |
| 26 | Class C concrete (column) (420-7038) | CY | 6.70 | $1,700.00 | $3,000.00 | $6,600.00 | $3,900.00 | $1,499.31 |
| 27 | Reinforced concrete slab (slab beam) (422-7007) | SF | 3,600 | $29.00 | $25.00 | $27.50 | $31.00 | $21.41 |
| 28 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 689.50 | $290.00 | $275.00 | $311.30 | $245.00 | $215.97 |
| 29 | Riprap (mow strip)(4 in) (432-7013) | CY | 7 | $1,200.00 | $700.00 | $1,100.00 | $1,500.00 | $787.98 |
| 30 | Riprap (stone protection)(18 in) (432-7043) | CY | 513.50 | $180.00 | $200.00 | $220.00 | $325.00 | $421.13 |
| 31 | Rail (type T223) (450-7008) | LF | 224 | $185.00 | $250.00 | $330.00 | $300.00 | $244.41 |
| 32 | Sealed expansion joint (4 in) (SEJ - B) (454-7006) | LF | 66 | $150.00 | $200.00 | $264.00 | $200.00 | $266.61 |
| 33 | RC pipe (CL III)(18 in) (464-7003) | LF | 6 | $110.00 | $185.00 | $132.00 | $650.00 | $322.41 |
| 34 | RC pipe (CL III)(24 in) (464-7005) | LF | 158 | $140.00 | $100.00 | $165.00 | $220.00 | $300.88 |
| 35 | Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128) | EACH | 1 | $8,000.00 | $6,000.00 | $8,800.00 | $6,000.00 | $7,085.00 |
| 36 | Inlet(complete)(pazd)(FG)(4FTX4FT-4FTX4FT) (465-7160) | EACH | 1 | $7,900.00 | $6,800.00 | $9,790.00 | $6,500.00 | $9,500.19 |
| 37 | Inlet(complete)(pazd)(FG)(5FTX5FT-4FTX4FT) (465-7162) | EACH | 1 | $9,775.00 | $6,100.00 | $10,010 | $6,000.00 | $10,342 |
| 38 | Inlet (complete)(drop) (465-7346) | EACH | 1 | $7,500.00 | $5,800.00 | $8,250.00 | $6,000.00 | $8,784.73 |
| 39 | Headwall (CH - FW - 0) (diameter= 24 in) (466-7005) | EACH | 2 | $8,000.00 | $10,000 | $7,700.00 | $20,000 | $4,417.27 |
| 40 | Jack bor or tun pipe(24 in)(RC)(CL IV) (476-7021) | LF | 48 | $1,925.00 | $1,500.00 | $385.00 | $975.00 | $2,599.16 |
| 41 | Removing structure (inlet) (496-7002) | EACH | 1 | $1,850.00 | $580.00 | $770.00 | $2,500.00 | $3,201.92 |
| 42 | Removing structure (headwall) (496-7006) | EACH | 1 | $2,300.00 | $580.00 | $770.00 | $2,500.00 | $3,201.92 |
| 43 | Removing structure (pipe) (496-7007) | LF | 66 | $24.50 | $10.00 | $33.00 | $50.00 | $87.73 |
| 44 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $48,000 | $40,000 | $88,000 | $50,000 | $62,861 |
| 45 | Mobilization (500-7001) | LS | 1 | $164,210 | $70,000 | $200,000 | $240,000 | $353,037 |
| 46 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $4,000.00 | $3,700.00 | $5,396.90 | $3,491.25 | $4,091.72 |
| 47 | Portable changeable message sign (503-7002) | EACH | 4 | $13,000 | $7,000.00 | $10,461 | $20,006 | $10,148 |
| 48 | TMA (stationary) (505-7001) | DAY | 18 | $200.00 | $1.00 | $355.70 | $229.73 | $218.75 |
| 49 | Construction exits (install) (type 2) (506-7021) | SY | 111 | $22.00 | $30.00 | $34.00 | $50.00 | $207.79 |
| 50 | Construction exits (remove) (506-7024) | SY | 111 | $8.00 | $10.00 | $18.10 | $25.00 | $19.04 |
| 51 | Construction perimeter fence (506-7034) | LF | 340 | $5.00 | $35.00 | $22.00 | $6.94 | $5.03 |
| 52 | Temporary sediment control fence (install) (506-7039) | LF | 1,163 | $4.50 | $4.00 | $5.10 | $4.60 | $1.45 |
| 53 | Temporary sediment control fence (remove) (506-7041) | LF | 1,163 | $1.50 | $1.00 | $2.60 | $2.30 | $7.08 |
| 54 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 365 | $7.25 | $5.00 | $10.40 | $9.45 | $1.16 |
| 55 | Biodegradable erosion control logs (remove) (506-7046) | LF | 365 | $3.00 | $1.50 | $2.70 | $2.45 | $562.50 |
| 56 | Driveways (ACP) (530-7010) | SY | 29 | $325.00 | $85.00 | $298.80 | $325.00 | $268.75 |
| 57 | Driveways (base) (530-7015) | SY | 58 | $27.50 | $40.00 | $70.30 | $150.00 | $67.83 |
| 58 | Metal W-beam guard fence (timber post) (540-7001) | LF | 12.50 | $50.00 | $50.00 | $57.50 | $42.22 | $2,256.22 |
| 59 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 1 | $1,800.00 | $1,700.00 | $4,240.50 | $1,881.23 | $59,728 |
| 60 | TL-2 31" short radius (complete) (540-7036) | EACH | 1 | $2,000.00 | $21,600 | $24,558 | $19,881 | $3,384.16 |
| 61 | Guardrail end treatment (install) (544-7001) | EACH | 1 | $3,900.00 | $4,300.00 | $4,251.50 | $3,922.80 | $63,917 |
| 62 | Crash cushion attenuator (install)(R)(N)(TL2) (545-7009) | EACH | 3 | $20,000 | $22,750 | $29,535 | $21,869 | $409.41 |
| 63 | Chain link fence (install) (6') (550-7001) | LF | 20 | $40.00 | $75.00 | $110.00 | $200.00 | $39.34 |
| 64 | Chain link fence (remove) (550-7007) | LF | 20 | $30.00 | $10.00 | $55.00 | $64.13 | $1,875.00 |
| 65 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 1 | $875.00 | $950.00 | $863.50 | $690.00 | $2,625.00 |
| 66 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 1 | $930.00 | $950.00 | $1,017.50 | $1,000.00 | $2,125.00 |
| 67 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $890.00 | $320.00 | $935.00 | $850.00 | $687.50 |
| 68 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 1 | $940.00 | $500.00 | $467.50 | $670.00 | $187.50 |
| 69 | Remove SM RD SN sup&AM (644-7073) | EACH | 13 | $200.00 | $200.00 | $203.50 | $95.00 | $156.25 |
| 70 | Install delineator assembly (D-SW)SZ 2(WC)GND (658-7009) | EACH | 9 | $36.00 | $50.00 | $137.50 | $62.00 | $56.25 |
| 71 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 10 | $35.00 | $50.00 | $137.50 | $24.50 | $93.75 |
| 72 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 12 | $18.00 | $18.00 | $82.50 | $75.00 | $2.81 |
| 73 | Pavement sler 6" (666-7347) | LF | 560 | $2.00 | $1.50 | $2.50 | $2.25 | $3.75 |
| 74 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 806 | $2.35 | $3.50 | $3.30 | $3.00 | $3.75 |
| 75 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 20 | $3.50 | $3.50 | $3.30 | $3.00 | $3.75 |
| 76 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 1,158 | $3.30 | $3.50 | $3.30 | $3.00 | $43.75 |
| 77 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 16 | $16.00 | $8.20 | $38.50 | $35.00 | $11.88 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 7, 2025. Compiled by Mirage Metrics.