TxDOT contract A00141254 bid tabulation
Rehabilitate Existing Roadway, IH 35E (IH 20 to Ann Arbor Ave.). Let by Texas DOT on May 7, 2026, Dallas, Dallas District. 3 bids received; low bid $11,542,446 by Altus Construction LLC, -12% against the engineer's estimate of $13,090,783.
- Owner
- Texas DOT
- Letting
- 07 MAY 2026
- Pay items
- 98
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Altus Construction LLC | $11,542,446 | Low | -12% |
| 2 | Ragle Construction, Inc. | $11,682,457 | +1.0% | -11% |
| 3 | Gibson & Associates, Inc. | $12,519,894 | +8.0% | -4.0% |
Engineer's estimate: $13,090,783.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Altus Construction LLC | 2. Ragle Construction, Inc. | 3. Gibson & Associates, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 11 | $5,000.00 | $52,467 | $40,070 | $6,600.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 110 | $20.00 | $31.90 | $25.00 | $27.50 |
| 3 | Removing concrete (curb) (104-7016) | LF | 155 | $20.00 | $5.81 | $15.00 | $11.00 |
| 4 | Excavation (channel) (110-7002) | CY | 1,912 | $15.00 | $7.40 | $35.00 | $33.00 |
| 5 | Embankment (final)(OC)(type C) (132-7005) | CY | 119 | $27.00 | $13.51 | $40.00 | $55.00 |
| 6 | Compost manuf topsoil (4") (161-7002) | SY | 1,771 | $5.00 | $1.44 | $3.00 | $8.80 |
| 7 | Block sodding (162-7002) | SY | 1,771 | $4.00 | $4.00 | $13.75 | $7.15 |
| 8 | Hydro mulch seed (permanent_urban_clay) (164-7020) | SY | 637 | $5.00 | $0.06 | $2.50 | $9.01 |
| 9 | Vegetative watering (168-7001) | TGL | 358 | $35.00 | $5.52 | $40.00 | $291.50 |
| 10 | Soil ret BLKT(SL_mod_clay_short_roll) (169-7009) | SY | 637 | $3.25 | $1.51 | $3.00 | $9.01 |
| 11 | SP mixes SP-C sac-B PG76-22 (344-7031) | TON | 5,965 | $125.00 | $217.61 | $180.00 | $204.12 |
| 12 | Tack coat (344-7077) | GAL | 5,965 | $5.00 | $1.62 | $6.00 | $0.01 |
| 13 | Flexible pavement structure repair(8") (351-7007) | SY | 1,000 | $100.00 | $134.66 | $90.00 | $123.12 |
| 14 | Plane & text asphalt concrete pavement(0" to 3") (354-7003) | SY | 8,927 | $2.50 | $21.51 | $8.50 | $8.78 |
| 15 | Planing asphalt concrete pavement(0" to 2") (354-7032) | SY | 54,193 | $2.50 | $3.14 | $2.50 | $2.96 |
| 16 | Full - depth repair CRCP (8") (361-7049) | SY | 1,400 | $250.00 | $204.69 | $245.00 | $205.20 |
| 17 | Full - depth repair CRCP (13") (361-7058) | SY | 700 | $425.00 | $323.19 | $350.00 | $324.00 |
| 18 | Full-depth rep(BR appr slab)(9"-13") (361-7068) | SY | 3 | $600.00 | $276.96 | $1,400.00 | $1,500.00 |
| 19 | Flowable backfill (401-7001) | CY | 144 | $250.00 | $300.42 | $270.00 | $660.00 |
| 20 | Class C concrete (abutment)(HPC)(extend) (420-7017) | CY | 14.80 | $600.00 | $5,273.43 | $1,500.00 | $4,500.00 |
| 21 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 8 | $200.00 | $148.65 | $400.00 | $594.00 |
| 22 | Concrete structure repair(rapid deck rep(PRT DPT) (429-7004) | SF | 315 | $120.00 | $55.90 | $50.00 | $165.00 |
| 23 | Concrete structure repair(rapid deck rep(full DPT)) (429-7006) | SF | 1,056 | $125.00 | $226.23 | $90.00 | $80.00 |
| 24 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 8,708 | $100.00 | $109.69 | $125.00 | $183.60 |
| 25 | Concrete structure repair(rapid vert and overhead) (429-7008) | SF | 12 | $350.00 | $140.71 | $250.00 | $405.00 |
| 26 | Riprap (concrete)(5 in) (432-7002) | CY | 58 | $500.00 | $530.90 | $630.00 | $693.00 |
| 27 | Riprap (concrete)(flume) (432-7012) | CY | 40 | $600.00 | $585.37 | $680.00 | $693.00 |
| 28 | Riprap (mow strip)(4 in) (432-7013) | CY | 164 | $600.00 | $439.54 | $580.00 | $693.00 |
| 29 | Riprap (stone protection)(12 in) (432-7041) | CY | 2,018 | $125.00 | $132.99 | $145.00 | $172.80 |
| 30 | Riprap (stone protection)(18 in) (432-7043) | CY | 7,541 | $150.00 | $118.66 | $145.00 | $178.20 |
| 31 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 1,324 | $40.00 | $9.43 | $18.00 | $27.00 |
| 32 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 3,929 | $50.00 | $29.63 | $23.00 | $31.32 |
| 33 | Cleaning existing joints (438-7008) | LF | 504 | $40.00 | $14.87 | $20.00 | $27.00 |
| 34 | Polyester polymer concrete overlay (2") (439-7017) | SY | 10,659 | $220.00 | $213.41 | $210.00 | $220.00 |
| 35 | Retrofit rail (type SSTR)(HPC) (451-7025) | LF | 1,568.10 | $175.00 | $147.68 | $170.00 | $161.70 |
| 36 | Raising existing struct (495-7002) | EACH | 3 | $25,000 | $32,825 | $45,000 | $36,000 |
| 37 | Mobilization (500-7001) | LS | 1 | $1,238,743 | $1,148,503 | $1,100,000 | $801,000 |
| 38 | Barricades, signs and traffic handling (502-7001) | MO | 19 | $25,000 | $30,376 | $32,340 | $35,500 |
| 39 | Portable changeable message sign (503-7002) | EACH | 6 | $15,000 | $7,002.38 | $25,000 | $14,000 |
| 40 | TMA (stationary) (505-7001) | DAY | 620 | $225.00 | $119.36 | $300.00 | $350.00 |
| 41 | TMA (mobile operation) (505-7003) | DAY | 25 | $400.00 | $161.41 | $680.00 | $350.00 |
| 42 | Rock filter dams (install) (type 3) (506-7003) | LF | 2,345 | $35.00 | $48.80 | $70.00 | $35.20 |
| 43 | Rock filter dams (remove) (506-7011) | LF | 2,345 | $14.00 | $6.82 | $14.00 | $16.50 |
| 44 | Construction exits (install) (type 1) (506-7020) | SY | 848 | $35.00 | $23.87 | $38.00 | $22.00 |
| 45 | Construction exits (remove) (506-7024) | SY | 848 | $11.00 | $8.15 | $12.00 | $11.00 |
| 46 | Temporary sediment control fence (install) (506-7039) | LF | 5,725 | $4.50 | $1.82 | $3.99 | $3.63 |
| 47 | Temporary SDMT cont fence (inlet protection) (506-7040) | LF | 1,000 | $25.00 | $1.76 | $10.00 | $5.50 |
| 48 | Temporary sediment control fence (remove) (506-7041) | LF | 6,725 | $1.40 | $0.91 | $1.00 | $1.10 |
| 49 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 1,000 | $15.00 | $4.19 | $5.00 | $6.60 |
| 50 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,000 | $5.00 | $0.30 | $1.25 | $1.10 |
| 51 | PTB (furnish and install)(steel) (512-7072) | LF | 1,120 | $150.00 | $50.42 | $150.00 | $40.00 |
| 52 | PTB (move)(steel) (512-7074) | LF | 1,840 | $50.00 | $9.94 | $50.00 | $9.41 |
| 53 | PTB (remove)(steel) (512-7076) | LF | 1,120 | $25.00 | $21.79 | $20.00 | $10.74 |
| 54 | Concrete curb (type I) (529-7001) | LF | 150 | $50.00 | $14.34 | $22.00 | $55.00 |
| 55 | Concrete curb (type II) (529-7002) | LF | 5 | $40.00 | $24.13 | $90.00 | $88.00 |
| 56 | Metal W-beam guard fence (timber post) (540-7001) | LF | 3,162.50 | $25.00 | $20.84 | $23.50 | $27.28 |
| 57 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 17 | $1,500.00 | $1,892.66 | $1,800.00 | $2,194.50 |
| 58 | Downstream anchor terminal section (540-7015) | EACH | 7 | $3,000.00 | $1,229.35 | $1,200.00 | $1,848.00 |
| 59 | Remove metal beam guard fence (542-7001) | LF | 2,987.50 | $3.00 | $2.63 | $2.50 | $2.20 |
| 60 | Remove terminal anchor section (542-7002) | EACH | 7 | $500.00 | $255.35 | $150.00 | $220.00 |
| 61 | Guardrail end treatment (install) (544-7001) | EACH | 10 | $2,800.00 | $3,447.86 | $3,000.00 | $3,729.00 |
| 62 | Guardrail end treatment (remove) (544-7003) | EACH | 10 | $700.00 | $237.71 | $250.00 | $220.00 |
| 63 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 4 | $3,000.00 | $586.35 | $1,800.00 | $1,259.50 |
| 64 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $3,000.00 | $703.13 | $1,000.00 | $907.50 |
| 65 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $8,000.00 | $6,747.92 | $15,000 | $8,563.50 |
| 66 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012) | EACH | 55 | $50.00 | $16.34 | $20.00 | $16.50 |
| 67 | Install delineator assembly (D-DY)SZ 1(BRF)GF2 (658-7052) | EACH | 50 | $75.00 | $22.00 | $25.00 | $27.50 |
| 68 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 968 | $0.75 | $0.75 | $1.00 | $7.00 |
| 69 | Reflectorized pavement marking type I (W)6"(lane drop)(100MIL) (666-7012) | LF | 450 | $3.00 | $0.81 | $1.00 | $1.10 |
| 70 | Reflectorized pavement marking type I(W)(entr gore)(100MIL) (666-7069) | EACH | 6 | $1,100.00 | $1,373.54 | $1,450.00 | $1,595.00 |
| 71 | Reflectorized pavement marking type I(W)(exit gore)(100MIL) (666-7072) | EACH | 7 | $2,250.00 | $1,912.19 | $2,250.00 | $2,475.00 |
| 72 | Pavement sler 6" (666-7347) | LF | 90,078 | $25.00 | $0.15 | $0.15 | $0.17 |
| 73 | Pavement sler (entr gore) (666-7361) | EACH | 6 | $500.00 | $323.19 | $400.00 | $440.00 |
| 74 | Pavement sler (exit gore) (666-7362) | EACH | 7 | $500.00 | $538.64 | $500.00 | $550.00 |
| 75 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 18,016 | $1.00 | $0.57 | $0.53 | $0.58 |
| 76 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 36,031 | $1.00 | $0.54 | $0.50 | $0.55 |
| 77 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 36,031 | $1.00 | $0.54 | $0.50 | $0.55 |
| 78 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 901 | $8.00 | $4.09 | $3.75 | $4.13 |
| 79 | Eliminating existing PM & markers (6") (677-7002) | LF | 90,078 | $0.35 | $0.64 | $0.55 | $0.61 |
| 80 | Eliminating existing PM & markers (entr gore) (677-7016) | EACH | 6 | $500.00 | $861.83 | $300.00 | $330.00 |
| 81 | Eliminating existing PM & markers (exit gore) (677-7017) | EACH | 7 | $450.00 | $1,292.75 | $400.00 | $440.00 |
| 82 | Pavement surface preparation for marking (entr gore) (678-7017) | EACH | 6 | $150.00 | $538.64 | $150.00 | $165.00 |
| 83 | Pavement surface preparation for marking (exit gore) (678-7018) | EACH | 7 | $400.00 | $861.83 | $200.00 | $220.00 |
| 84 | Longt crack cleaning and sealing (CRCP) (713-7005) | LF | 210 | $50.00 | $22.82 | $25.00 | $31.32 |
| 85 | Spalling repair (polymeric) (semirigid) (720-7003) | GAL | 500 | $65.00 | $118.50 | $95.00 | $118.80 |
| 86 | Fiber reinforced polymer patching materials (721-7001) | LB | 2,000 | $6.00 | $20.47 | $10.00 | $20.52 |
| 87 | Repair (steel post W/base plate) (776-7002) | EACH | 1 | $300.00 | $4,039.84 | $1,500.00 | $2,000.00 |
| 88 | Concrete rail repair (in-kind) (778-7001) | LF | 3 | $200.00 | $342.62 | $900.00 | $1,750.00 |
| 89 | Concrete rail repair (miscellaneous) (778-7002) | LF | 127 | $200.00 | $52.85 | $30.00 | $80.00 |
| 90 | CNC crack repair (discrete)(gravity) (780-7001) | LF | 388 | $40.00 | $21.09 | $25.00 | $27.00 |
| 91 | CNC crack repair (discrete)(inject) (780-7002) | LF | 628 | $25.00 | $43.02 | $25.00 | $64.80 |
| 92 | Rep steel bridge MBR (anchor bolt nuts) (784-7021) | EACH | 3 | $200.00 | $296.17 | $450.00 | $250.00 |
| 93 | Bridge joint replacement (concrete) (785-7009) | LF | 409 | $200.00 | $420.10 | $145.00 | $520.00 |
| 94 | Bridge joint replacement (armor) (785-7010) | LF | 963 | $250.00 | $379.99 | $260.00 | $615.00 |
| 95 | Carbon fiber reinforced polymer strengthning (786-7002) | SF | 114 | $100.00 | $38.83 | $175.00 | $105.00 |
| 96 | Concrete beam repair (CFRP) (788-7002) | EACH | 11 | $10,000 | $6,497.97 | $3,500.00 | $1,000.00 |
| 97 | Deck drain system dle (4060-7001) | LS | 1 | $15,000 | $4,039.84 | $75,000 | $22,000 |
| 98 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 3 | $700.00 | $605.22 | $880.00 | $1,188.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.